An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Belt Line Project Cost Update May 27, 2014

  2. Belt Line – Project Overview • Undergrounding of aerial utilities – electrical and telecom • Two Phases – Marsh to Midway; Midway to Tollway • Phases based on Oncor service sections • Bonds Approved – $20 million • Bond amounts based on unit costs from Spring Valley undergrounding, increased to account for greater complexity on Belt Line • Assumed cost to relocate telecom utilities would be reimbursed • Assumed ability to use public right-of-way on north and south sides of Belt Line Road

  3. Changes to Concept Design • Asphalt overlay upgraded to higher quality material - black rock aggregate; better aesthetics, better contrast with markings • Subsurface Utility Exploration (SUE) showed more congestion in north and south rights-of-way than anticipated • Necessitated use of left-hand turn lanes in Belt Line – increased traffic control costs, night work, and safety considerations • Increased number and length of service duct banks and lateral lines • Additional traffic signal upgrades needed; mid-block crossing for connectivity project added

  4. Current Market Conditions • Large number of construction projects in the Dallas area – IH635, NTTA Chisholm Trail, various TxDOT projects, DFW Airport projects, transit projects • Limited contractor availability due to number of ongoing projects • Greater competition for personnel and materials – higher prices • Small volume project vs. large volume projects • Concrete and asphalt pours, etc • Duct banks in left-hand turn lanes increases traffic control, safety, and night work costs • Restricted lane closures reduces productivity and leads to higher bid prices • Selective in responsive bidders; low bidder must have previous experience with similar projects

  5. Belt Line Project Elements • Undergrounding utilities: electrical, three telecommunication companies: Oncor, AT&T, Time Warner Cable, Fiberlight • Three concrete ducts, service lines, laterals w/ multiple conduits • Switch gears, utility pads, manholes to accommodate access for utility companies • R.O.W. acquisition for easements and sight visibility corners • ADA compliance • Sidewalk widening to enhance safety • Traffic signal upgrades; new mid-block crossing signal • Minor water and storm water infrastructure improvements • Restoration of displaced areas: pavement, parking lots, driveways, and landscaping • Asphalt overlay, restriping

  6. Belt Line Project Timeline • February 13, 2013: Design kick-off meeting • December 12, 2013: Phase 1 Design 100% Complete • February 7, 2014: First request for bids posted • March 4, 2014: One bid received; bid rejected; rebid process initiated • March 28, 2014: Bid request reissued • April 17, 2014: Three bids received • April 22, 2014: John Burns Construction lowest responsive bidder • May 13, 2014: Council authorized contract with John Burns and Alliance Geotech Group

  7. Belt Line Phase II Status – Midway to Tollway • 60% design submission now complete • 90% design submission due August 1 • 100% design submission due in November

  8. Phase I Summary of Cost • Civil Construction $ 8,820,802 • Contingency $ 352,000 • Overlay     $ 843,000 • Land Acquisition $ 930,000 • Oncor Reimbursement $ 4,600,000 • Telecom Reimbursement $ 903,000     • Engineering $ 1,206,000 • PM & Construction Inspection $ 362,000 • Appraisal fee $ 113,000 • Geotech & Materials Testing $91,000 • Direct Costs (Printing, Adv., Etc.) $ 71,000 Phase I Total $18,291,802

  9. Phase II Estimated Costs • Civil Construction $ 10,400,000 • Construction Contingency $ 1,040,000 • Overlay     $ 843,000 • Land Acquisition $ 930,000 • Oncor Reimbursement $ 4,600,000 • Telecom Reimbursement $ 903,000     • Engineering $ 1,206,000 • PM & Construction Inspection $ 362,000 • Appraisal fee $ 113,000 • Geotech & Materials Testing $91,000 • Debt Service $142,000 • Direct Costs (Printing, Adv., Etc.) $ 71,000 Phase II Estimated Costs$ 20,701,000

  10. Options / Recommendation • Cancel project; do not execute contracts; complete final invoicing for work performed • Move forward with Phase I; assess whether to move forward with Phase II when 100% design on Phase II received • Recommendation: Option 2 – continue with Phase I and assess whether to proceed when Phase II design is complete