Construction Project Reports Hazard Independent Schools May 16, 2013. Roy G. Eversole Elementary Walkertown Middle School. Roy G. Eversole Elementary. New faculty lounge and toilet room are complete and occupied. New First Aid suite is complete and occupied.
E N D
Construction Project Reports Hazard Independent SchoolsMay 16, 2013 Roy G. Eversole Elementary Walkertown Middle School
Roy G. Eversole Elementary New faculty lounge and toilet room are complete and occupied. New First Aid suite is complete and occupied. Renovation of second group of gang toilets is underway. Renovation of final group of gang toilets (adjacent to cafeteria) is underway. Contractor is completing renovation of last group of classrooms. All wheelchair lifts (three) are installed and operational. Renovation of Administrative suite and front exterior plaza is scheduled to start at end of school.
New faculty mailboxes Renovated faculty workroom New ADA compliant shower New ADA compliant faculty toilet
Walkertown Middle School Toilet renovation is complete. Renovation of the FMD suite is 75% complete. Renovation of the Science classroom is 90% complete. Renovation of Administrative suite is scheduled to start at end of school.
New Science classroom (in-progress) features include student sinks and counters, Instructor’s demonstration counter, and emergency shower