1 / 13

Eastern Cape Province 2007/08 Expenditure Report on Q2 Conditional Grants & Infrastructure

Eastern Cape Province 2007/08 Expenditure Report on Q2 Conditional Grants & Infrastructure. Presentation by: W.H. Nel MEC for Finance (06 November 2007, Cape Town). Purpose. Budget Summary. Conditional Grants. Infrastructure. Expenditure trends on Conditional Grants. Discussion.

kineks
Download Presentation

Eastern Cape Province 2007/08 Expenditure Report on Q2 Conditional Grants & Infrastructure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Eastern Cape Province2007/08 Expenditure Report on Q2 Conditional Grants & Infrastructure Presentation by: W.H. Nel MEC for Finance (06 November 2007, Cape Town)

  2. Purpose. Budget Summary. Conditional Grants. Infrastructure. Expenditure trends on Conditional Grants. Discussion. Presentation Outline

  3. Purpose • The purpose of this report is to update the Select Committee on Finance on the second quarter performance of conditional grants and Infrastructure for 200708 financial year.

  4. Budget Summary • For 2007/08 financial year Eastern Cape has a budget of R31, 4 billion, of which: • Of this amount, Conditional Grant accounts for R3, 7 billion and Infrastructure R3, 8 billion.

  5. Conditional Grants • Q1 expenditure stood at R429 million against projections of R749, 7 million, recording an under spending of R320, 7 million. • Q2 expenditure somewhat improves with actual expenditure standing at R822, 2 million against projections of R599, 7 million, thus leading to an over expenditure of R222, 5 million.

  6. Infrastructure. • On a month-to-month basis, actual expenditure significantly increased in the reporting period. In the month of April for example, actual spending stood at R91, 9 million and increased to R98, 5 million in May. • In June the figure increased to R252 million, and again to R311, 8 million in July. In the month of August the figure increased to R365 million. • In the month of September the expenditure on infrastructure further increased to R377, 6 million. With regard to the under expenditure amount of R404, 8 million, the bulk of this total amount (R240, 2 million) relates to the Department of Education under-spending.

  7. Conditional Grants: Actual Expenditure

  8. Conditional Grants: Projected & Actual Expenditure

  9. Expenditure trends: Under expenditure

  10. Infrastructure Expenditure

  11. RECOMMENDATIONS AND WAY FORWARD • The following proposed steps to be taken to further improve the overall conditional grants spending in the Province: • Proper strategic planning; • Better alignment of budget with targets set out in the strategic plan; • Project design is properly done resulting in achievable cashflows; • Multi year commitments are planned and budgeted for; and • Better spending on planning budgets that would be continually monitored.

  12. THANK YOU

More Related