1 / 19

Utility Cost Estimating In Practice

Utility Cost Estimating In Practice. Scott Riddle Vice President – Public Utilities KCI Technologies Inc. Overview. Maryland’s Process Milestones Responsibilities Tools Production History Rate of Success Next Steps…. Background. 17 Years of Experience with Utilities

kineks
Download Presentation

Utility Cost Estimating In Practice

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Cost EstimatingIn Practice Scott Riddle Vice President – Public Utilities KCI Technologies Inc.

  2. Overview • Maryland’s Process • Milestones • Responsibilities • Tools • Production History • Rate of Success • Next Steps…..

  3. Background • 17 Years of Experience with Utilities • Majority of KCI’s Work is Directly for the Utilities. • Understanding of DOT’s Needs and Schedules. • Success with Utility Coordination Comes From Successful Relationships.

  4. Maryland’s Process • Project Planning • Utility Estimates by Highway Planners. • Rough Assessment Approach. • 2002: SHA asked KCI to Develop “Planning Level Utility Estimating Matrix”.

  5. Planning Estimate

  6. Preliminary Investigation • 30% Plans Are Sent To The Utility Companies • Rough Drainage • No MOT • Incomplete Grading • Utility Company Resource Issues • Many Projects Die Between P.I. and Final • Provide High “Ball Park” Estimates That Will Often “Kill” Project.

  7. Semi Final – PS&E • As SHA Plans Improve • Drainage Is Complete • Test Pitting Clarifies Impacts • Utility Estimates Are Updated • As Real Impacts Are Known, Estimates Become More Focused • Estimates Maintain High Contingencies Factor Because of “Risk”

  8. Prior Rights • SHA initiates the “RW57” Form Process • Utilities identify impacted facilities • Utilities research for existing easements and Rights of Ways • Submit to SHA for review • SHA reviews and validates research • Final percentage is: Total “Covered” Facilities/Total Facilities

  9. Prior Rights • Grey Areas • Pole Outside of Right of Way, Conduit in Right of Way • Cables Feeding from County Road

  10. Risk Management • DOT’s Risk • Under Estimate Funding Request • Higher Bids Due to Unknown Utility Involvement • Delay Claims Due to Concurrent Utility Work • Higher Bids Due to Construction Methods • Overhead Clearances • Handwork

  11. Risk Management • Utility Company’s Risk • Under Estimate Project Funding • Loss of Service to Customers • Increased Effort for Relocation

  12. Maryland’s Process Utility Estimate By Highway Planner Estimate By Utility with 30% of Information Planning Estimate Impacted Utilities Known, Estimates With Contingences and Prior Rights Complete Final / PS&E Estimate Actual Construction Rubber Meets the Road

  13. Results – Data Source • SHA’s Project Cost Database • 925 Total Projects Since 1992 • 773 Projects with Complete Data • 45 Projects with Cost Not Estimated • 107 Projects without Final Cost

  14. Results – Total Dollars Values In Millions

  15. Results – Total Cost Values In Millions

  16. Results – By Project

  17. Process Issues • Wide Variation on Individual Projects • Utility Estimates During Design Excessively High often Killing Projects • DOT Can’t Verify or Predict Utility Estimate • Utility Company can’t Respond to the Schedule or Flexible needs of DOT

  18. New Approaches • Consultant Involvement with Utility Review • Relieves burden on Utility Companies • Works to DOT’s Schedule • Develop Utility Cost Data • Interactive Coordination During Design • Reduce Changes • Continue to Develop Relationship with Utilities.

  19. Questions

More Related