An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Building for the Next Generation: Maintain the Pride An Opportunity for our Communities

  2. Beautiful homes Imagine Our Communities!Great Places to Live! Communities with … • Excellent schools • Good families • Excellent leadership • Community support • Quality educators

  3. Goals for Today • Listen to each other. • Learn about the role of the Ohio Schools Facilities Commission. • Learn about what this means to our communities. • Learn what this project can do for your schools. • Learn about the cost of the project. • Have some fun together!

  4. Brainstorming Activity

  5. Our Communities working together! What do you most value and appreciate about your schools? As you think about the schools describe how you would like the schools to look in the future? Looking into the future what should be done to improve our schools and school buildings? Looking into the future what do you think would happen if nothing was done to improve our schools? It has been decided to improve our schools. Working together how can we make it happen?

  6. Our Communities Coming Together! Our plan will be successful and together we can make it happen!

  7. What is the Ohio Schools Facilities Commission? • The Ohio Schools Facilities Commission (OSFC) is the agency that oversees the rebuilding of Ohio Schools. (http://www.osfc.state.oh.us/) • The OSFC mission is: "To provide funding, management oversight, and technical assistance to local school districts for construction and renovation of school facilities in order to provide an appropriate learning environment for Ohio's school children."

  8. What is the Ohio Schools Facilities Commission? • Funding for the rebuilding of schools started in 1998/1999 through the OSFC. • OSFC views themselves as a co-owner in all projects until the projects are complete. • They have considerable input since they are contributing considerable dollars representing the State of Ohio.

  9. Our past relationship with the OSFC. • The Middle School HVAC project was completed by OSFC standards. • Those dollars will be credited as part of our share of any potential OSFC project. ($2.6 million credit) • We were required to establish a “master plan” (OSFC term) as a part of that project.

  10. Opportunity for our Communities! An opportunity to: Bring tax dollars back to the communities. Build now at a reduced rate or a full rate at a later time. Provide safe, healthy, effective educational facilities for Pre K – 12. (kids, kids, kids – education, education, education) Reduce the number of buildings from 5 – 4.

  11. The Math • Current Tax Collections: • 7.04 Bond Issue for the High School is now an average of 1.9 effective mills (last collection was July 07’) • 1 mill permanent improvement is now an average of .56 effective mills • Requested millage = 5.8 mills

  12. The Math: continued 1.9 mills expired 5.8 mills requested + .56 mills (reduced from 1 mill) -2.46 mills reduced = 2.46mills =3.34 mills 3.34 mills = NEW AND RENOVATED SCHOOLS

  13. Why New Schools: • Kids, Kids, Kids and their future • Better educational environment – tons of research to indicate that the physical environment of a school does impact educational achievement. • Safety and security concerns. • More uses for the communities. • The health of the district and communities.

  14. The Project Cost: • State Contribution = $31,648,926 • Issuance of Bonds = $27,500,000 • Finances by the district = $ 6,931,190 Total: $66,080,116

  15. Local Share and Locally Funded Initiatives • Total Co-Funded Project Cost including the middle school project - $50,236,391 • 37% of $50,236,391 = $18,587,465 • LFI’S - $15,900,000 • Minus Local Financing- $7,000,000 • Total Bond Request $27,500,000

  16. What the schools have done for you… • Earned a prestigious rating as an Effective School on the State Report Card • Last year’s graduating seniors earned over 1 million dollars in scholarships and rewards • The district has added innovative educational options to ensure that every student has the opportunity to receive a quality education • The Board of Education has spent the citizens’ tax dollars wisely and responsibly

  17. What have we done… We have identified the unique needs of the schools and communities and provided quality options to meet those needs.

  18. Why do we need the Bond Issue? • To Construct two new elementary buildings • To renovate and add on to the Middle School • To renovate and update the High School • To incorporate community amenities in the school buildings • To make the schools central to our community • It will provide facilities for the next 50 - 75 years

  19. The Need… • Centennial – age 59 • Cridersville – age 68 • Northridge – age 40 • Middle School – age 49 • High School – age 18

  20. Major Needs at the schools… • Out dated heating systems • Inadequate instructional space

  21. Major needs… • Outdated electric power controls • Paving/concrete issues • Inadequate Lighting • Inadequate Parking

  22. The Board of Education has a plan that is shaped to the strengths, needs and vision for our communities!

  23. Our Plan is… POSITIVE! HONEST! An investment for the future . . . & Failure is not an option! Our Plan is clear and will be understood by the stakeholders!

  24. How will this impact me? • Cost to owner of a $100,000 home • About $102.29 per year … that’s $8.52/month • Cost to owner of a $150,000 home • About $153.43 per year … that’s $12.79/month • Cost to owner of a $200,000 home • About $204.58 per year… that’s $17.05/month

  25. The risks of inaction… • The community loses value • Further decline of facilities • Increased physical risk to students and faculty • Increased strain on academics due to inadequate facilities • A negative message for future residents • OUR CHILDREN LOSE FAITH IN US!

  26. Community The spirit of the community is one of shared responsibility and collaborative inquiry. Everyone’s voice is valued. Each person or group’s contribution is essential. And learning and sharing are ongoing and not just confined to the classrooms. Tony Wagner, Harvard University

  27. Don’t be afraid to go beyond the corn…

  28. The Board of Education Thanks You for attending and sharing your thoughts. We want your support and help to make our communities the best they can be for all!