200 likes | 376 Views
Electricity Network Connectivity Between the GCC Countries. Presented By: Adnan I. Al-Mohaisen May 17, 2005. BIRTH OF THE GCC POWER GRID. Originated in the early 1980’s by a local GCC committee from the electricity sector.
E N D
Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005
BIRTH OF THE GCC POWER GRID • Originated in the early 1980’s by a local GCC committee from the electricity sector. • In 1986 the first project study was conducted by a committee from the GCC in coordination with the Kuwait Research Institute and King Fahad University of Petroleum and Minerals. • The study was updated in 1990 by Gulf Investment Bank and SNC-Lavalin to confirm the interconnection was economical and financially viable. • In 2003 another study update was undertaken as a final preparation for the project financing and tendering, in which the following topics were covered: • Techno-Economic Analysis • Market Study • Financial Analysis • Interconnection Agreement • Implementation Strategy
GCC INTERCONNECTION AUTHORITY • Established in July 2001 by a Royal Decree No. M/21. • Owned by the six GCC Countries the authorized share capital is ($US 1,100,000,000) divided into (1,100,00) shares of ($US 1,000) each share. • The Authority is managed by a (twelve member) Board of Directors; each member country is represented by two members. The Chairmanship is rotated among the member states every three years. • The official domicile of the Authority is Dammam, with the Control Center to be located in Ghunan, Saudi Arabia. • The primary objective of the Authority is to: • link up the power grids of the six GCC countries • operate and maintain the interconnection
Founders No. of Shares Nominal Value Percent United Arab Emirates 169 , 400 $ 169 , 400 , 000 15 . 40 % Kingdom of Bahrain 99 , 000 99 , 000 , 000 9 . 00 % Kingdom of Saudi Arabia 347 , 600 347 , 600 , 000 31 . 60 % Sultanate of Oman 61 , 600 61 , 600 , 000 5 . 60 % State of Qatar 128 , 700 128 , 700 , 000 11 . 70 % State of Kuwait 293 , 700 293 , 700 , 000 26 . 70 % Total 1 , 100 , 000 $ 1 , 100 , 000 , 000 100 . 00 % INTERCONNECTION SHARE CAPITAL Based on the 1990 Project Study it was determined that the share of the cost of the interconnection will be the present worth of the capacity savings.
INTERCONNECTION LINK The interconnection is to be constructed in 3 phase, namely: Phase II Phase I Phase III Phase I will interconnect Al-Zour (Kuwait), Al-Fadhili, Ghunan, Salwa (KSA) and Doha South (Qatar) with a 400 kV OHL, and a 400 kV Land & Submarine cable with Al-Jasra (Bahrain). Phase II will integrate the UAE system with a 400 kV OHL from Shuwaihat to Al-Ouhah. Phase III will interconnect Salwa and Shuwaihat with 400 kV OHL and Al-Ouhah and Al-Waseet in Oman with a 220 kV OHL.
KUWAIT AL ZOUR AL ZOUR 400kV 400kV 1200 MW SAUDI ARABIA 310km SEC - ERB AL FADHILI 400kV HVDC 112km BACK TO - BACK - BAHRAIN 1200MW 90km 90km JASRA 400kV 600MW GHUNAN 290km 290km 400 kV 100km 100km QATAR DOHA SOUTH SUPER 400kV DOHA SOUTH SUPER 400kV SALWA SALWA 750MW 400kV 400kV 150km 150km 900 MW 400MW OMAN SHUWAIHAT 400kV 400kV EMIRATES NATIONAL OMAN NORTHERN GRID GRID AL OUHAH AL WASEET U.A.E. 52km 220 kV 220kV 220kV INTERCONNECTION CRITERIA
PHASE I : CUMULATIVE PW OF BENEFITS AND COSTS IN $ MILLION ( Jan . 2008 @ 6% ) 3000 2500 2000 1500 Cumulative PW of Benefits and Costs 1000 500 0 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 Year Phase I Benefits Phase I Costs BENEFITS & COSTS Upon the completion of Phase-I and the reduction of generation capacity the total cost savings rate of return after 4 years from operations is 2.5 billion US Dollars.
PHASE I&III : CUMULATIVE PW OF BENEFITS AND COSTS IN $ MILLIONS ( Jan . 2008 @ 6% ) 3500 3000 2500 2000 Cumulative PW of Benefits and Costs 1500 1000 500 0 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 Year Phase I & III Benefits Phase I&III Costs BENEFITS & COSTS Upon the completion of Phase-III the total cost savings rate of return after 3 years from operations is 3.35 billion US Dollars.
Lot Capital Cost Total O&M Cost Transmission Lines 392 14 Cable System 293 6 Substations 172 4 Converter Station 302 6 Control Station 30 1 Total 1,189 30 PROJECT ECONOMICS The capital cost of constructing Phase I estimated at US$ 1,189 million is depicted below: It is further estimated that it will cost approximately $ 30 million annually to operate and maintain the Grid: • The estimated cost for constructing Phase III is $US 137 million. • Although the construction of Phase II is not under GCCIA task it is estimated that its construction to be approximately $US 300 million.
Load (MW) Total Installed Capacity Reserve (MW) 105 781 MW 12 085 93 781 Load (MW) Total Installed Capacity Reserve (MW) 100 726 MW 6 945 93 781 PROJECT ECONOMICS The GCC Grid is expected to reduce the amount of new generation capacity required by the GCC member states by sharing the reserve capacity that needs to be maintained by each system to ensure reliability and provide protection against outages. The capacity benefits to Year 2028 are shown below: Isolated System Interconnected System The cumulative benefit in MW of the interconnected system as opposed to isolated systems will be 5,113 MW.
INTERCONNECTION BENEFITS • Reduce generation reserves; • Provide power exchange and strengthens supply reliability; • Improve the economic efficiency of the electricity power systems; • Strengthens operational efficiency; • Promoting utilities to construct larger generation units to share extra generated power; • Provide opportunities for industrial customers and utilities to shop around for more attractive supply of power; • Adopt technological development and use the best modern technologies; • Providing long-term environmental advantages by reducing waste emissions from increasing generation plants.
GLOBAL INTEGRATION • The technical and economical feasibility study for the GCC Interconnection has been proven. • The GCC Interconnection will enhance the Power Systems of the GCC Countries. • The GCC Countries will be a significant part of the Pan-Arab Grid. • The GCC Interconnection is the main gateway towards a Regional and Pan-Arab Power Pools. • The Power Grid is a fundamental step leading to the liberalization of regional power market.
6 7 4 4 22 PROJECT STATUS • September 2004 SNC-Lavalin of Canada was hired to perform the Tendering and Adjudication for the Phase I Project. • Thirty three (33) out of the sixty five (65) companies were pre-qualified; where some companies qualified for only one lot and some qualified for all five lots. Pre-qualified companies were from local GCC and international countries. GCCIA will engage an international consulting firm affiliated with a local GCC firm for the Supervision of the Construction of the Phase-I Project.
TASKS DATE Pre-Qualification Exercise August 2004 Pre-Tender Meetings March 2005 Tender Submittals June 2005 Technical Bid Opening June 2005 Commercial Bid Opening TBA Evaluations August 2005 Contract Awarding October 2005 Operations Commencement 1st Qtr 2008 PROJECT SCHEDULE
For further information you can access our website at: www.gccia.com.sa THANK YOU