An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERL Status & Schedule R&D ERLERL Status & Schedule Gary McIntyre February 17-18, 2010

  2. ERL Status & Schedule • Although important to C-AD, ERL must compete for resources with machine operations – • Sharing resources limits the work that can be performed… • During shutdown periods • Operations maintenance days • Anytime ERL work is in conflict with operations efforts • Best efforts are being made by all ERL-involved groups but schedule slip can and does occur.

  3. ERL Status & Schedule Energy Recovery Linac Milestone Schedule 5-Cell Crymodule to Building 912 10/17/08 Start of Cold Emissions Testing 03/24/09 Gun Cavity begins processing 01/25/10 HTSS testing complete 03/09/10 Gun cavity string delivered to BNL 09/01/10 Gun Cryomodule moved to BLG 912 12/17/10 Sub systems connections to e-Gun Cryomodule complete 02/22/11 Testing start of Gun to 5-cell Cavity Cold with metal cathode 03/15/11 VTF Refrigerator operational 03/23/11 Removal of G-5 components and installation of Injection components 06/01/11 G-5 with Injection (Zig-Zag) Testing Starts 07/18/11 ERL component installation complete & checkout complete 10/24/11 ERL -All Systems- Testing 10/24/11

  4. ERL Status & Schedule • The critical path remains the electron gun cavity cryomodule • Steps to complete the cryomodule include: • Cavity processing • Hermetic Cavity String assembly • String installation into e-Gun cryomodule • G-5 (e-Gun to 5 cell Cavity) next major milestone • Followed by the full ERL complete e-Gun cavity with large grain R&D cavity

  5. ERL Status & Schedule • Cavity Processing – on going at JLab • Buffered chemical polishing - on-going • Vacuum firing to 600C - complete • High pressure rinsing - on-going • Vertical cold testing at 2K - expected start 02/23/10 e-Gun cavity in vacuum furnace (Jefferson Laboratory) Model of e-Gun cavity in Helium Vessel

  6. ERL Status & Schedule e-Gun Cavity Hermetic String Assembly e-Gun cavity in Helium Vessel Fundamental Power Coupler side thermal transition Cathode side thermal transition Assembly/transport cart Tooling design complete – parts of tooling package in fabrication, others in approval loop. All string components in-house or ordered , no negative schedule impact.

  7. ERL Status & Schedule • String installation into e-Gun cryomodule • Cathode transporter in house • Installation tooling design start scheduled for 04/2010 • All cryomodule components ordered with no negative schedule impact Ballast tank Cryomodule vacuum vessel Cathode transporter Cathode insertion point & choke joint High temperature SC Solenoid

  8. ERL Schedule • Major Milestones • G-5 Testing • Requires e-Gun installed in Cryomodule • All major cryomodule components ordered • e-Gun cryogenics lines routing design in process • Requires G-5 magnets, instrumentation and vacuum chambers • All magnets and stands in-house • Installation as time permits • Remainder of G-5 vacuum chambers due 04/28/10 • Beam instrumentation for G-5 & ERL due 08/26/10 • Removal of G-5 “straight” line & install “zig-zag” line • Additional testing with this configuration

  9. ERL Status & Schedule G-5 Layout E-Gun & cathode transporter 5-cell cavity with ballast tank

  10. ERL Status & Schedule • Complete ERL Installation • Requires removal of G-5 Test components • All Loop magnets, stands, and power supplies in-house • All Loop vacuum chambers in-house • Moveable arc stand in-house. • Magnet stand pre-survey underway. • ERL Dump due 03/26/10 • Loop Beam Instrumentation due 08/26/10 • Staging manpower remains biggest challenge

  11. ERL Status & Schedule ERL Layout in Building 912 5-cell Cryomodule ERL Loop e-Gun Cryomodule Laser Room ERL Dump 1MW Klystron 1MW IGBT Power Supply