1 / 6

Week 5

Week 5. MDR Updated Check the website if you have any mission requirement questions!. Timeline. Project Timeline Week 5 - PDR complete by end of week DURING: Evaluation of design alternatives for each phase END: PDR is update to MDR, final design requirements are documented

kohana
Download Presentation

Week 5

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Week 5 • MDR Updated • Check the website if you have any mission requirement questions! [Solomon Westerman] [PM]

  2. Timeline • Project Timeline • Week 5 - PDR complete by end of week • DURING: Evaluation of design alternatives for each phase • END: PDR is update to MDR, final design requirements are documented • END: Will have X1 and X2 complete by end of week to satisfy PDR requirements • Week 6-7 – CDR complete by end of week (~3 weeks away) • DURING: Evaluation of design alternatives for each phase (priority). If subsystem has already reached maturity and we are fairly confident of its selection, perform detailed analysis (sub-priority) • END: All design alternatives will have reached maturity • END: “Alternative Design Freeze” - no other alternatives will be able to be analyzed • END: Selection of final configuration • END: Draft writing begins • Week 8-9 – Final Design Freeze at end of week (Spring Break!) • DURING: Detailed analysis on selected mission configuration. Changes to configuration will be made only if serious issues occur. • END: Final mass/power/volume budgets set for all phases • END: Draft writing nearly complete (due Wed. after spring break to PM) • After Spring Break – Crunch time • 2 weeks until your final report due to PM • 2 weeks + weekend until your final slides due to PM

  3. Today • Preliminary scalability analysis (almost) complete (X2) • Have power to focus on alternative designs (X3,X4) • Numbers from X1,X2 analysis will indicate if design changes will benefit system • Separate alternative designs into three levels: • Level 1: Large system change, possibly affecting more than one phase • Level 2: Medium system change, has a > 10% affect on mass, power, volume from X1 or X2 for a particular phase • Level 3: Small system change, < 10% affect on mass, power or volume from X1 or X2 but can make integration simpler, system more reliable, cheaper, etc. • Most promising alternatives for each phase will be listed today • Each level 1 and 2 alternative assigned a POC (Point of Contact) and APOC (Alternative POC) by Phase lead • Each level 3 alternative assigned a POC by Phase lead • Will provide responsibility and set deliverables for POC (can be used for presentation material)

  4. Alternative Design Deliverables (not complete) Order-of-magnitude mass/power/volume savings (kg,W,m^3) Potential complexity/cost/ease of integration savings Complexity of analysis (days to reach maturity) Recommend use for GLXP size? Recommend use for arbitrary payload size?

  5. To-Do • PM • Upload Design Alternative List (by 4:00PM) • Upload Design Alternative form (by tomorrow) • Upload Draft writing expectations (by tomorrow) • Phase Leader • Assign POC to all design alternatives, modifying Design Alternative List (by 8:00 PM) • POC • Complete Design Alternative form (by 6:00PM Monday 2/16)

More Related