1 / 17

Use of Rubber Gloves & Protectors for Underground Cable Splicing

Use of Rubber Gloves & Protectors for Underground Cable Splicing. Joseph P. Carey, PE Principal Engineer National Grid. Purpose. National Grid is reviewing a work methods change that may require the use of rubber gloves & protectors while splicing medium voltage underground cables.

kristian
Download Presentation

Use of Rubber Gloves & Protectors for Underground Cable Splicing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Use of Rubber Gloves & Protectors for Underground Cable Splicing Joseph P. Carey, PE Principal Engineer National Grid

  2. Purpose • National Grid is reviewing a work methods change that may require the use of rubber gloves & protectors while splicing medium voltage underground cables.

  3. Current Work Practice CONDUCTOR SHEATH MH J Bonding Splicer Bracket GND Bracket GND Ground Rod • Isolated, Red Tagged, Tested De-Energized and Grounded (with Bracket Grounds) • & Work Bare Handed

  4. Background • National Grid made many contacts throughout the industry to review other utilities UG grounding procedures and work methods. • National Grid reviewed existing studies on step and touch potential on underground distribution systems.

  5. Findings • Various studies have identified step & touch potential hazards from an accidental energization or a fault from an adjacent circuit, in the order of several thousand volts. • There are many different views and approaches to UG grounding across the industry. Approaches include: Establishing an Equipotential Zone, Insulation, and Isolation.

  6. National Grid Study • Early 2008 a decision was made to perform an internal study. The decision to perform the study was based on the need for data that would represent the National Grid system. • National Grid is currently working to complete this study. Source Substation Side 1 MH Side 2 CONDUCTOR SHEATH Core (Side 2) Bonding Core (Side 1) Sheath (Side 1) Sheath (Side 2) Vs Ground Rod

  7. Study Observations to Date • National Grid’s study confirmed the potential hazards identified in previous studies. • Further results from National Grid’s study indicated: • Accidental Energization • The EPZ Mat is effective at reducing potential hazards when a cable is under repair. • The best location for bracket grounds: • With an EPZ mat, is close to the work site • Without an EPZ mat, the grounds at the substation • Fault On an Adjacent Circuit • Installing Bracket grounds close to the work site significantly reduces voltage levels • In some situations the use of an EPZ mat can increase touch potentials

  8. Rubber Glove Evaluation • The evaluation of undergroundsplicing with rubber gloves was performed at the Millbury Learning Center. • A 15kV hand applied splice was built on 1/C 1000MCM Al XLPE Cable. The splice was built with Class 2 Rubber Gloves and Protectors. • A 15kV Cold Shrink Splice was built on 1/C EPR 500MCM CU EPR Cable. The splice was built using Class O Rubber Gloves and Protectors. • A 15kV Live Seal Stop End was built on 3/C PILC 350MCM Jacketed Cable. The splice was built using Class 2 Gloves and Protectors. Midway through the splicing process the splicer switched to Class 1 Gloves and Protectors.

  9. Splicing Observations

  10. Splicing Observations

  11. Splicing Observations

  12. Splicing Observations

  13. Splicing Observations

  14. Splicing Observations

  15. Splicing Observations • The contaminants from the rubber glove protectors were transferred to the splice. • Metal filings, compounds, oils & leather material • The contaminants observed raised a concern of the level of the reliability of the splice. • Oil & compounds migrated through the protectors to the rubber gloves. • There may be an issue with degradation of rubber gloves when using oil based tapes and silicon tapes. • The towelettes that are used to clean the cable were contaminated by the protectors. • Dexterity may be an issue with some of the splicing tasks.

  16. ASTM Committee Input • It is National Grid’s determination that there is a potential for damage to the rubber gloves when used without protectors during some cable splicing activities. • National Grid is seeking the help of the ASTM sub-committee for further exceptions or alternatives to the current leather protector requirements. • Different style leather protector (coated) • Exception of using protectors on rubber gloves Class 1 and higher • Other solutions

  17. Questions?

More Related