1 / 31

SMACC Twentieth report [20 min ] 14/03/2014

Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Twentieth report [20 min ] 14/03/2014. Activities since last LSC (28/02/2014) Arc splices installation By Activities By sectors SIT DFBA Dashboards Specials Update on overheated splices End of project issue

Download Presentation

SMACC Twentieth report [20 min ] 14/03/2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project SMACC Twentieth report[20 min]14/03/2014

  2. Activities since last LSC (28/02/2014) • Arc splices installation • By Activities • By sectors • SIT • DFBA • Dashboards • Specials • Update on overheated splices • End of project issue • Activities for the next 2 weeks • Conclusions

  3. SMACC Main activities for the last 2 weeks From last LSC (28.02.2014) • Sector 56 : • Final leak test and reconnection of DFBAK • Sector 67 : • Complete interventions on NC, recloseinsulation vacuum • Sector 78 • Work on NC, • Reconnection of DFBAO-SHM • Sector 81 (Priority) • Progress on insulation vacuum leak test • Sector 12 • Complete last IC (#1) • Progress on closure of ICs • Sector 23 • Progress on the installation of electricalinsulation • Complete Q diodes consolidation • Complete M line rewelding (but NCs) • Sector 34 • Complete installation of electricalinsulation • Workon overheatedsplices • Start consolidation of Q diodes • Sector 45 • Complete resoldering of splices • Progress on installation of shunts DFBAK SHM reconnection on-going [Splices are resoldered], Only the last subesector remains to be leak tested  Interventions completed, ICs to be reclosed then final LT   > 98% reclosed, 12/14 vac subsectors leak tested  DFBAK SHM reconnection on-going [Splices are resoldered],  Leaks on K hoses repaired, > ½ is finally LT All shunts are installed   > 75% reclosed  >98 % done  Completed  > 95% rewelded  > 90% injected and controlled  1 out of 4 repaired, on-going  > 40% done  Resoldering completed  >95 % of the shunts are installed

  4. SEQUENCE AND STATUS Completed Install DN200 Completed Completed Completed Open M sleeves Open ICs OK to open Completed Undo / Redo splices ElQC(new splices) Cancelled ElQC(old splices) Machine Cu ElQCafter Cu mach. Completed > 7.9 sectors > 7.9 sectors Consolidate Q diodes ≈ 6.5 sectors Weld M Leak test M Close IC Final LT Insulate splices ElQCafter shunt Install shunts ≈ 7.9 sectors ≈ 7.9 sectors ≈ 7 sectors ≈ 6 sectors > 4.5 sectors ≈ 3.5 sectors ≈ 5.5 sectors Non-conformities (Before P Test) Non-conformities (After P Test) Almost completed in 1st sector (67) 1 completed ≈ 3.5 sec-eq

  5. SMACC Progress report by activity • Resoldering: Completed for the whole LHC • Some desoldering/resoldering will be necessary because of NC Degradation after Cu machining, non-conformities,… • Competence and minimum capacity will be kept up to the end of the project Courtesy H Prin

  6. SMACC Progress report by activity • Cu machiningcompleted in > 7.9 sectors-eq • Completed in 3 sectors • Only 11 remaining, mostly linked to overheated splices and DFBA SHM reconnection Courtesy MDumas

  7. SMACC Progress report by activity • Shunts are installedin ≈ 7.9 sectors-eq • 2 weeks ahead of schedule • Saturation effect is seen • Completed in 3 sectors (67, 81, 12) • Only 16 ICs remains in the whole LHC (≈1%) Shunt weekly installation rate (4 weeks sliding average) *Estimate for W11 Courtesy H Prin

  8. SMACC Progress report by activity • Insulation box: Installed in > 6.5 sectorsequivalent (4 weeks sliding average) *Estimate for W8 • On the baseline • > 3 weeks buffer wrt welding • Only 8 ICs left in 6 first sectors (<1 %) • but it was 12 ICs 2 weeks ago •  Issue with some tooling components (mixer), should be solved next week •  A fall back solution exists Courtesy H Prin / G Maury

  9. SMACC Progress report by activity • Consolidation of Q Diodes: in ≈ 6.5 sectorsequivalent • Detailed schedule worked out • Should not interfere with welding activities • NC of un~/badly coated BB • Already decided to “use as is” if on magnet side • Decision extended to diode side [Diodes WG 26.02.2014] was confirmed at TETM 11.03.2014 Courtesy L Grand-Clement,

  10. SMACC Progress report by activity • M Welding : Done in ≈ 6 sec-eq: • Routinely 60 ICs/week • Work concentrated in 1 sector, starting in 34 (7th/8) • No major disturbance • Exactly on the baseline presented on 4.10.2013 • Detailed presentation at next LSC 18 weeks @ 51 As presented LSC 4.10.2013 Slightly ahead of revised schedule 11 weeks @ 34 Courtesy S Atieh

  11. SMACC Progress report by activity • M sleevesleaktesting : Completed in ≈ 5.5 sec-eq • Following the M lines rewelding, less regular by nature (sectorization) • ≈ 3 weeks behind schedule • Under recovery as for the M welding Courtesy P Cruikshank / L Mourier

  12. SMACC Progress report by activity • Reclosure of interconnections : > 4.5 sec equivalent are reclosed • Workmainlyin S12 and starting in S23 • On the baseline • The 1000th IC will be closed this afternoon Courtesy A Chrul / A Musso

  13. SMACC Progress report by activity • Final leak test: > 750 ICsvalidated, > 3.5 sec equivalent • 3 weeks to have results after repumping • S56: only DFBAK subsectorremains • S67: fullyvalidated but subsectors to berevalidatedafter interventions on NC • S78: 12 subsectorsvalidated • S81: 11 subsectorsvalidated, 3undertest, several interventions • S12: 6 subsectorsundertest • About 1 week behind schedule, was 3 weeks at last LSC 

  14. SMACC Sector 67 • 2 leaksfixed, one not localised, accepted as is • On-going: • Reclosure and final leak test of insulationvacuum SMACC Sector 81 Remaining : Less than half of W leak test and DN200 (Back on baseline )

  15. SMACC Progress report by sector • Main activities are : • Welding of M lines • Leak test of M lines • Start reclosure of Ics (Today) • Main activities are : • Leak test of M lines • Closure of interconnections • 6/14 subsectors are underfinal LT

  16. SMACC Progress report by sector • Main activities are : • Work on overheated splices(More info in next slides) • Q diodes consolidation • Rewelding of M lines • Main activities are : • Installation of shunts • Installation of electricalinsulation

  17. SMACC Dashboards • Shunting is slowing down (Difficult cases: overheatedsplices, DFBAs,… ) • The installation of insulation boxes is ahead of the baseline • Welding and M leak test rates are recovering the baseline schedule in parallel • Reclosure: On baseline, nominal rate achieved • Insulation vacuum leak test : RECOVERING • Disturbances of leak tests (M lines and insulation vacuum) have to beminimised

  18.  Completed New New  Completed

  19. SMACC Progress report SIT • SIT • Team isreduced but canberemobilisedveryquickly • Activitieslinked to NC, leaks and overheatedsplices Courtesy N Bourcey, S Le Naour

  20. SMACC DFBA 95% of splices are consolidated OK for just in time (New schedule) Many operations are well advanced but not completed 8 DFBAs are completed Courtesy A Perin, E Vergara

  21. SMACC Dashboards Baseline: 76.9 % (72.8 %) Completed: 74.9 % (69.0 %) Delay 10 (20) days Baseline: 82.7 % (77.4 %) Completed: 84.2 % (78.9 %) Delay -3 (-3) days • Ahead of schedule  Decreasing delay • Arc splices: Stable but difficult cases ahead • SITDelay decreases, waiting validation • DFBA: Many activities on-goingIn the shadow of the arcs  Recovering Baseline: 85.7 % (81.1 %) Completed: 67.1 % (57.4 %) Delay 3 (4) months

  22. SMACC Dashboards Progress: Baseline: 82.5% (77.5 %) Completed: 82.1% (76.6 %) Delay2 (6) days Decreasing ; Δbaseline <≈ Δcompleted

  23. SMACC Overheated splices From LSC of 07.02.2014 9 5 1 6 Confirmed as is Within the presentschedule, possible to repair 4 to 5 spliceswith new cables [Forecastismax 6] Courtesy C Scheuerlein, F Savary

  24. End of project issue In order to alleviateeffect of the end of workatmosphere, presence in the tunnel isincreased: * One extra staff (Thx TE-VSC) to second worksitesupervisors * Auditors are reinforced and are intensifying audits Courtesy R Ostojic, M Struik

  25. SMACC Summary on progress Main 13 kA Splices:  On schedule  Q Diodes consolidation : Almost all components are at CERN and tested  Overheatedsplices: to befollowed up closely  Leak test rate isaccording to forecast,  slightly more needed Special Interventions:  Delay is decreasinng  Almost all planned interventions are completed  Focus on NC DFBA:  Activities are back in the shadow of arc splices (except 56-78) SMACC:  About 2 days of delay, reducingwrt schedule defined one year ago !! Very slightly more than nominal rate achieved these last 24 weeks !

  26. SMACC Main activities for the next 2 weeks • Sector 56 : • Final leak test and reconnection of DFBAK • Sector 67 : • Recloseinsulation vacuum and start final leak tests • Sector 78 • Work on NC • Reconnection of DFBAO-SHM • Sector 81 (Priority) • Complete insulation vacuum leak test • Sector 12 (Priority) • Reclose last ICs • Progress on insulation vacuum leak test • Sector 23 • Complete the installation of electricalinsulation • Complete M line rewelding (but NCs) • Progress on M-linesleaktesting • Start reclosure of ICs • Sector 34 • Workon overheatedsplices • Complete consolidation of Q diodes • Sector 45 • Progress on installation of shunts • Progress on electricalinsulation

  27. Conclusions • Project isalmost back on schedule (-2 days) • Mind the last X % effect • Leaktestingisreaching the planned rates • DFBA consolidation isprogressingverywell • Overheatedsplices : On the criticalpath • S67 isalmostready for nextstep(ElQAbeforecooldownforeseen end of April) • S81 shouldbeready on time for pressure test (8.04.2014)

  28. Advancement is > 80 % …. But

More Related