An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NPRR515, Day-Ahead Market Self-Commitment of Generation Resources Matt Mereness ERCOT Manager DAM & CRR Carrie Bivens ERCOT Supervisor DAM ERCOT Public

  2. Background on Current Self-Commitment • Adding a self-commitment mechanism to DAM was a late change prior to nodal go-live • As such, it isn’t as flexible as it could be nor does it align with RUC’s treatment of self-committed generation • The purpose is to be able to offer a reduced quantity of MWs and co-optimize with AS • Energy Only Offers lose the co-optimization benefits • Example on next slide:

  3. Background on Current Self-Commitment • A Resource has 150 MW LSL and 400 MW HSL, and the QSE has already committed 300 MW of the Resource bilaterally or otherwise. • The QSE wishes to offer the remaining 100 MW, which would otherwise be ignored due to the LSL constraint. • The Resource can provide up to 50 MW of Ancillary Services • The QSE submits a self-committed offer for 100 MW and an AS Offer for 50 MW. 450 (HSL) Available for energy or A/S 400 Available for energy 350 Unavailable for commitment 150 (LSL) 0 MW

  4. Current Implementation • How it works (mechanics): • Submit startup and minimum energy offers as NULL (must be for all hours submitted) • Offer curve starts at 0 MW • If the resource is selected for Ancillary Services, no requirement to also award TPO at LSL (since LSL treated as 0) • Current implementation is that the choice must be for the entire day. • DAM does not consider temporal constraints or LSL for this offer

  5. Purpose of this NPRR • Provide a way to allow Resources the flexibility to be self-committed in some hours and available for commitment by DAM in others • Offers can be shaped to line up with their true availability • Since the current mechanism is so restrictive, some might be staying out of DAM altogether, or not offering in the whole day • Note that an analysis of participation year-to-date shows that roughly 30% of the generation MWs offered into DAM are self-committed