Day Ahead Market Working Group

Day Ahead Market Working Group. March 31, 2003. Agenda. Review minutes - March 24 Coral Proposal - Working Group Discussion Loads/LDCs and DAM. DAM Design Requirements. Design requirements - at a high level what we want the DAM to look like

ulla
Download Presentation

Day Ahead Market Working Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Day Ahead Market Working Group March 31, 2003

  2. Agenda • Review minutes - March 24 • Coral Proposal - Working Group Discussion • Loads/LDCs and DAM

  3. DAM Design Requirements • Design requirements - at a high level what we want the DAM to look like • Lead to development of detailed design and how the DAM will be built • DAM from the perspective of different classes of MPs • Financial Market Participants - March 24 • Loads/LDCs - March 31 • Generators - April 7 • Importers/Exporters - April 14

  4. Loads/LDC’s • Buy/Sell in DAM - Close out position in RT • DA MCP and MCQ set based on DA generation offers and load bid • Two Settlement System equation: QDA(PDA-PRT) + QRT PRT can also be expressed as QDA PDA+ PRT (QRT- QDA ) • If QDA =QRT then PRT is not relevant

  5. Non-Dispatchable Load with no Physical Bilateral Contract Bids DAM 100MW @ $100 and 50MW @ $75 • DA MCP = $90 • QDA scheduled 100MW @ PDA$90 = Profit of $10/MW • If 100MW consumed then load pays: • QDA PDA+ PRT (QRT- QDA ) = • 100MW x $90 + PRT(100MW-100MW) = $ 9,000 • Note: when QRT = QDA, PRT is not relevant

  6. Non-Dispatchable Load with no Physical Bilateral Contract • If 175MW consumed and PRT is $120 then load pays: • 100MW x $90 + $120(175MW-100MW) = $18,000 • If 175MW consumed and PRT is $60 then load pays: • 100MW x $90 + $60(175MW-100MW) = $13,500 • If 80MW consumed and PRT is $120 then load pays: • 100MW x $90 + $120(80MW- 100MW)) = $6,600 • If 0MW consumed and PRT is $120 then load pays: • 100MW x $90 + $120(0MW- 100MW)) = -$3,000 that is, the load receives +$3000

  7. Dispatchable Load • Submits bids into DAM and RTM (for this example, they submit the same bid curve into both markets) • Dispatched according to bid curve in RT market • QRT can be responsive to and consistent withPRT drivers • Examples: Bids DAM 100MW@ $40 and additional 50 MW @ $30; say DA MCP = $35 and QDA = 100 MW • Say RT MCP = $38, QRT = 100 MW 100MW x $35 + $38(100MW - 100MW) = pays $3500 • Say RT MCP = $50, QRT = 100 MW (dispatched off) 100MW x $35 + $50(0MW - 100MW) = receives $1500 • Say RT MCP = $20, QRT = 150 MW 100MW x $35 + $20(150MW - 100MW) = pays $4500

  8. Non-dispatchable load with a Physical Bilateral Contract • Load has 2 production lines - each consumes 100 MW • Load has PBC with another participant to buy 100MW @ $100 • Typically operates production line 1: • Can stop production line 1 and consume 0 MW • Can start production line 2 and consume 200 MW • Submits to DAM: • Offer to sell 100MW @ $200 • Bid to buy 100MW @ $50

  9. Physical Bilateral Contracts Example 1 DA MCP = $250; load is accepted to sell 100MW and chooses to consume 0 MW based upon the DAM result Load pays: QDA PDA QRT QDA -100MW x $250 + PRT ((0MW-100MWPBC) - (-100MW)) = -$25,000 • Load actually receives $25,000 from IMO • Load pays $10,000 to PBC counter-party • Load receives net $15,000 for not running production line 1

  10. Physical Bilateral Contracts Example 2 Say, DA MCP = $40; QDA = 100 MW based upon DAM bid In RT load consumes 200MW to run production line 2 based upon PBC and DAM result QDA PDA QRT QDA (100MW)($40) + PRT((200MW-100MWPBC) - (100MW)) = $4,000 • Load pays IMO $4,000 • Load pays PBC $10,000 to PBC counter-party • Load pays net $14,000 to run production lines 1& 2 (200 MW)

  11. Discussion Points • LDCs • Bill 210 • Multi-part - Bid/Offer Structure • Energy, OR, Intertie trading • Ramp Rate impact • Positions closed out next day - 5 minute/HOEP • Prudentials - Exposure due to PRT not known until next day • Settlement - Financial vs. Physical schedule • Other Markets - i.e., NYISO

  12. Next Meetings • Generators - April 7 • Importers/Exporters - April 14