Two Step Scroll Field Check Out Process- Cooling or Heating Cycle

This process involves checking the compressor current and verifying the reduction in current when the second stage is activated. It helps ensure proper functioning of the cooling or heating system.

kwaddell
Download Presentation

Two Step Scroll Field Check Out Process- Cooling or Heating Cycle

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Two Step ScrollField Check Out Process- Cooling or Heating Cycle TPA020 – TPA051

  2. Two Step ScrollField Check Out Process- Cooling or Heating • Adjust the indoor thermostat set-point to its max/min setting to initiate a call for 2nd stage cooling/heating. • Verify that 24 volts are present at the Y1 and Y2 pigtails in the outdoor unit. • Measure and record the compressor current. • Carefully remove the wire from the Y2 terminal and measure the compressor current. • There should be a reduction in compressor current in accordance with the attached compressor specification sheets. • If there is a reduction in compressor current when the wire is removed from Y2, the compressor successfully went into part load capacity mode.

  3. 4T*X6024 / 4A**6024

  4. 4T*X6024 / 4A**6024 Low Load; Very Little Change

  5. 4T*X6024 / 4A**6024 High Load; ~2 amps Change

  6. 4T*X6036 / 4A**6036

  7. 4T*X6048 / 4A**6048

  8. 4T*X6060 / 4A**6060