Progress Report. 1 st Birthday. Signing of the FAIR Convention by representatives of the founding countries Finland, France, Germany, India, Poland, Romania, Russia, Slovenia and Sweden in Wiesbaden on 4/10/2010. OrgChart FAIR Company. FAIR Council. AFC. Scientific Council. IKRB. MAC.
E N D
Progress Report NuPECC, Milano, 9/3/12
1st Birthday Signing of the FAIR Convention by representatives of the founding countriesFinland, France, Germany, India, Poland, Romania, Russia, Slovenia and Swedenin Wiesbaden on 4/10/2010 NuPECC, Milano, 9/3/12
OrgChart FAIR Company FAIR Council AFC Scientific Council IKRB MAC ManagementBoard Staff Office LegalAdvisor CouncilIssues Secretariat BFC Internal Auditing Research TechnicalDivision Site &Buildings Admin. Expert C‘ttee Experiments Project OfficeExperiments Project Office Techn. Division Reporting Project Office Site & Buildings Internal Services APPA TechnicalServices M&E Advisor Civil Eng. Advisor Controlling CBM In-Kind Coordination M&E Eng. Automation, IT Finance NuSTAR TechnicalFollow-up M&E Eng.Power, Mat. Purchasing PANDA M&E Eng. Thermo, Refrig. Personnel M&E Eng.Liqu., Gases Constr. Eng.Building, Geo. Constr. Managem. Eng. NuPECC, Milano, 9/3/12
OrgChart FAIR-GSI Collaboration NuPECC, Milano, 9/3/12
Modularised Start Version M0 M3 M1 M3 M2 CBM/HADES APPA PANDA Experiments M1: APPA M1: CBM/HADES M2: NuSTAR M3: PANDA NuSTAR NuPECC, Milano, 9/3/12
Costs MSV in 2005 € (inflationescalationuntil 2018: ca. +50%) * Total experimental end stations (excluding Super-FRS):ca. 210 M€ (2005) = 315 M€ (2018) NuPECC, Milano, 9/3/12
Timeline 2011 2012 2013 2014 2015 2016 2017 2018 2019 9 11 12 6 7 8 10 Building permits Site preparation Civil construction contracts Building of accelerator & detector components Completion of civil construction work Installation & commissioning of accelerators and detectors Start Data taking 10 6 7 12 8 9 NuPECC, Milano, 9/3/12 11
Civil Construction NuPECC, Milano, 9/3/12
Applications & Permits 11.11.11 31.08.11 19.01.12 20.01.12 21./23.11 NuPECC, Milano, 9/3/12
First Post Drilling 31/8/2011 NuPECC, Milano, 9/3/12
Clearing Construction Site 6/12/2011 NuPECC, Milano, 9/3/12
Further Preparatory Work NuPECC, Milano, 9/3/12
Planning Activities NuPECC, Milano, 9/3/12
Accelerators • Orderedfor SIS100 from Babcock Noell in Jan. 2012 (German in-kind contribution, BMBF grantto GSI) • Manyotherpartsof SIS100 and CR in preparation (in-kind ortender) • HESR readytogo out fortender (BMBF grantofferedto FZ Jülich) • IKRB meetingat FAIR on 28/3/12 • MAC meetingat FZ Jülich on 2/4/12 Compact & cost effective Fast cycling superconducting magnetsdB/dt~ 4T/s NuPECC, Milano, 9/3/12
MSV Experiments NuPECC, Milano, 9/3/12
APPA • Board of APPA Collaborationsestablished • SpokesmanandDeputyelected • Layout of APPA hall finalised • Options exploredforexperimentsat • HESR • Cryring @ ESR APPA NuPECC, Milano, 9/3/12
CBM • HADES detectorupgraded • CollaborationwithDubna (NICA) beingconsidered • Finishing R&D work CBM NuPECC, Milano, 9/3/12
NuSTAR • Hall LEB being considered by Collaboration • search for funds outside of MSV budget • Exp. @ HESR being considered Super-FRS NuSTAR NuPECC, Milano, 9/3/12
PANDA • R&D being finished • Remaining TDRs being finalised • Premounting @ FZ Jülich being prepared PANDA NuPECC, Milano, 9/3/12
Timeline Experiments • Finish R&D phase 2012 • Deliver prototypes of all essential parts • Submit complete sets of TDRs 2012 • Take decisions on alternative technical solutions • Co-ordinate with 2012 • Civil construction requirements & accelerator setup schedule • Identify critical pathways, submit risk management plan 2012 • Timelines, milestones, deliverables • Secure funding, negotiate MoUs between Collaborations,Funding Agencies and FAIR 2012/13 • (Europe-wide) tendering 2013 • Build detectors 2013-16 • Commission detectors 2017 • Initial period of data taking 2018-21 NuPECC, Milano, 9/3/12
Commissioning & Operation • Commissioning MSV, Modules 0-3 • Top priority: Module 0 – SIS100 • Sequence of experiments depends on • Civil construction • Progress in • Prototyping & building of accelerators (storage rings) • Prototyping & building of production targets (RIB & anti-proton targets) • Prototyping & setting up of large-scale experimental equipment • Funding (majority from outwith FAIR MSV budget) • Operation MSV, Modules 0-3 • Signing of agreement on financing the FAIR operation budgetthree years after project has started (autumn 2013 at the latest) • Development of model for fair share of costs for operating FAIR • Explore • Contributions from participating countries that are not shareholders • Set up common collaboration funds for running the experiments (cf. DESY & CERN) • Modules 4 & 5, Phase B • Secure funding for civil construction, accelerators and experiments of Modules 4 & 5 • Continue R&D, in particular for SIS300, HESR Electron Cooler and NESR Electron Ring NuPECC, Milano, 9/3/12
FAIR Open Space Planning NuPECC, Milano, 9/3/12 22
Thank you very much NuPECC, Milano, 9/3/12