Experimental and Micromechanical Computational Study of Pile Foundations Subjected to Liquefaction-Induced Lateral Spreading - Task 1 (1g Tests)S. Thevanayagam, UBResearch Progress MeetingSeptember 11, 2006, 2-4 pm; UB-VTCPI: R. Dobry, co-PI’s: A. Elgamal, S. Thevanayagam, T. Abdoun, M. ZeghalUB-NEES Lab: A. Reinhorn, M. Pitman, J. Hanley, T. AlbrechcinskiTulane: Usama El ShamyStudents: UB and RPI Students
Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)
Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)
umax= ±0.74’’ umin= ±0.01’’ f = 2 Hz Revised Ground Motion
Preparatory Shake Test #1 3m Box Test : 9/21 – 10/05 Step 1: Fill the box with water for leak test & reduce level to 2 ft. Step 2: Pump the slurry to the laminar box up to 3m; density tests; CPT tests Step 3: Install accelerometers top of the soil Step 4: Remove Top 3m Rings Step 5: Safety Cables; Shaking/Actuator controls; Sensor/DAQ tuning Step 6: NDS & DS Shaking Step 7: Pump the slurry back to storage
3m Box Test Instrumentation • Ring and Base Instrumentation: • Accelerometers (Already installed) • Soil Instrumentation: • Put a steel/wood plate on top of the soil and install X-Accelerometers & Y-Accelerometers
Preparatory Shake Test #2 6m Box – LG-0 – 10/06-10/25/06 Step 1: Install limited soil instruments inside the box Step 2: Fill the box with water up to 2 ft. Step 3: Pump the slurry to the laminar box up to 6m; Density tests Step 4: CPT Step 5: Safety cables, Actuator/sensor/DAQ fine tuning Step 7: NDS & DS Shaking Step 8: CPT Step 9: Pump the slurry back to the storage areas
Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)
Next Meeting? – 10/16/06 ?? • To review 3m Box Test Data & Fine tune Test LG-0