An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Experimental and Micromechanical Computational Study of Pile Foundations Subjected to Liquefaction-Induced Lateral Spreading - Task 1 (1g Tests)S. Thevanayagam, UBResearch Progress MeetingSeptember 11, 2006, 2-4 pm; UB-VTCPI: R. Dobry, co-PI’s: A. Elgamal, S. Thevanayagam, T. Abdoun, M. ZeghalUB-NEES Lab: A. Reinhorn, M. Pitman, J. Hanley, T. AlbrechcinskiTulane: Usama El ShamyStudents: UB and RPI Students

  2. Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

  3. Box Assembly - Ready

  4. Membrane - Ready

  5. Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

  6. umax= ±0.74’’ umin= ±0.01’’ f = 2 Hz Revised Ground Motion

  7. Schedule for Preparatory Shake Tests

  8. Preparatory Shake Test #1 3m Box Test : 9/21 – 10/05 Step 1: Fill the box with water for leak test & reduce level to 2 ft. Step 2: Pump the slurry to the laminar box up to 3m; density tests; CPT tests Step 3: Install accelerometers top of the soil Step 4: Remove Top 3m Rings Step 5: Safety Cables; Shaking/Actuator controls; Sensor/DAQ tuning Step 6: NDS & DS Shaking Step 7: Pump the slurry back to storage

  9. 3m Box Test Instrumentation • Ring and Base Instrumentation: • Accelerometers (Already installed) • Soil Instrumentation: • Put a steel/wood plate on top of the soil and install X-Accelerometers & Y-Accelerometers

  10. 3m Box Test - Instrumentation

  11. Preparatory Shake Test #2 6m Box – LG-0 – 10/06-10/25/06 Step 1: Install limited soil instruments inside the box Step 2: Fill the box with water up to 2 ft. Step 3: Pump the slurry to the laminar box up to 6m; Density tests Step 4: CPT Step 5: Safety cables, Actuator/sensor/DAQ fine tuning Step 7: NDS & DS Shaking Step 8: CPT Step 9: Pump the slurry back to the storage areas

  12. LG-0 Instrumentation

  13. LG-0 Instrumentation (NS & EW View)

  14. Instrumentation Table: Test LG-0

  15. Agenda – 9/11/06 • Review of Minutes (ST, RD) • UB Progress (ST) • Actuators (MP, AMR, ST) (Final stages, 2 or 3 more days of fine tuning work remains) • Laminar Box Readiness (NE) (Ready) • Preparatory Shake tests (ST, MP) • 3m Box, Base & Rings & Top of Soil – 9/21-10/05/06 • 6m Box – LG-0 – 10/06-10/25/06 • Project Shake Tests (ST, RD) & Impacts on Project Coordination • 6m Box – LG-1 – 10/30 – 11/15/06 • 6m Box – SG-1 – 11/15 -11/30/06 • Single Pile – Test 1A – 3/15-4/15/07 • Single Pile – Test 1B – 4/15-5/15/07 • Group Pile – Test 2 – 6/1-7/30/07 • Lateral shaking tests (3 & 4) – 8/1-11/30/07 • Non-Destructive Shaking (ST) • Consensus on ND Motion (MP, AE, MZ, RD) (revised motion to be sent before meeting)

  16. Next Meeting? – 10/16/06 ?? • To review 3m Box Test Data & Fine tune Test LG-0