An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Air Permitting of Combustion Sources Fred P. Osman, P.E. Osman Environmental Solutions Harrisburg, PA April 21, 2011

  2. 8 EPA Major Combustion Rules in Past Year

  3. Air Permitting 101

  4. GHG Tailoring Rule

  5. Tailoring Rule Approach Tailoring Rule sets higher thresholds for GHGs Step 1. Jan 2 – July 1, 2011 – Anyway sources Step 2. July 1, 2011 and after: New PSD/Title V 100,000 TPY CO2(e) PSD modification 75,000 TPY CO2(e) Step 3 – EPA, effective July 1, 2013 – thresholds TBD Important Note: Biogenic Emissions are deferred(maybe)

  6. TAILORING RULE IMPLICATIONS Triggering major source for GHG requires: BACT - incorporates efficiency considerations Causes triggering for other pollutants as well Very few minor source permits

  7. Determination of non hazardous secondary materials that are solid waste Section 129

  8. Waste/Not-Waste

  9. CISWI (Commercial Industrial Solid Waste Incinerators) • Exempted • MWCs • QF’s homogeneous waste • MWI’s • SSI’s • HazWaste

  10. CISwi Implementation New or Modified Units – September 21, 2011 Existing Units – State Plan due 3/21/2012 Compliance due w/i 3 years of state plan approval or by March 21, 2016, which ever is sooner.

  11. Boiler MACT Major/Area Source? Only Gas Exempt Water Heaters Exempt No Size exemption

  12. Area source boiler mact Implementation New Units – Upon Startup Existing Units – March 21, 2012 No Emission Limits, just Work Practice Standards. Notice of Applicability due September 17, 2011 Biennial Tune-ups (1st due March 21,2012) Boilers >10 MMBTU/hr – one-time energy assessment

  13. Proposed Utility MACT Finalize by 11/16/11 Compliance in 3 years Hg Control PM surrogate for metals HCl or SO2 (some cases) Enhanced Monitoring

  14. Interstate transport rule Replaces CAIR Cap and Trade for SO2/NOX Trading more limited than CAIR

  15. Other current permitting issues New 1 hour NOX standard Problems with emergency engines New 1 hour SO2 standard Attainment by modeling and monitoring.