1 / 13

Modeled NAAQS Non-compliance in NE Minnesota and Proposed Path Forward

Modeled NAAQS Non-compliance in NE Minnesota and Proposed Path Forward. Summary. Modeled non-compliance for 1-hr SO 2 and 1-hr NO 2 NAAQS in NE Minnesota Identified during modeling required for PolyMet’s environmental review

lang
Download Presentation

Modeled NAAQS Non-compliance in NE Minnesota and Proposed Path Forward

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Modeled NAAQS Non-compliance in NE Minnesota and Proposed Path Forward

  2. Summary • Modeled non-compliance for 1-hr SO2 and 1-hr NO2 NAAQS in NE Minnesota • Identified during modeling required for PolyMet’s environmental review • Modeling indicates that nearby sources, not PolyMet, are culpable • 2 EGUs, 3 Taconites • Proposing path forward to Risk Managers

  3. 1-hr SO2 Culpable Sources (number of receptors exceeded) • Minnesota Power Laskin (2) • US Steel Minntac(10) • Northshore Peter Mitchell Pit (15) • ArcelorMittal (23) • Virginia Public Utilities (28)

  4. Receptors in Red Exceed the Standard

  5. 1-hr NO2 Culpable Sources (number of receptors exceeded) • Northshore Peter Mitchell Pit (1) • Virginia Public Utilities (30) • ArcelorMittal (791) • US Steel Minntac (853)

  6. Receptors in Red Exceed the Standard

  7. MPCA Guidance • 12/19/12 Memo to Resolve non-project NAAQS/MAAQS Exceedances • Goal: resolve modeled exceedancesvia enforceable conditions • The project manager, modeler and permit engineer prioritize list of culpable sources and recommend actions to the Risk Managers for approval

  8. EPA Guidance • Each receptor showing an exceedance is equal and must be addressed • Environmental review must consider the ramifications of a NAAQS violation and possible non-attainment • Non-PSD permits can be issued, if they don’t exceed the SIL • PSD permits can not be issued without an enforceable, detailed plan with timelines in place for all facilities contributing to exceedance

  9. Why now? • PolyMetEIS must contain a description of the path forward for the culpable sources by March 2013 • PolyMetis a non-PSD source, therefore it is not necessary to resolve the NAAQS non-compliance in order for permitting

  10. Why now? • There will be future PSD permits submitted in the region, as soon as mid-year 2013 • Solutions will be iterative and time intensive, so advantageous to start ASAP • PolyMet modeling shows exceedances only within its receptor grid – not the full extent of the impacts • Likely to rely on concurrent, parallel efforts

  11. Proposed Resolution Team Lead: Air Policy Staff with modeling, enfocement, and permitting support • Letter to all culpable facilities putting them on notice of modeled exceedances • Require submittal of a plan within 45 days including actions to resolve modeled exceedances • Iterative steps, based on facility-specific plan, to get to final action • MPCA conducts cumulative modeled to confirm actions will result in compliance prior to becoming enforceable • Final action, via permit or enforceable agreement, must be taken by late-2013

  12. Proposed Resolution • If facility does not submit plan, does not submit adequate plan, or is not cooperative, the MPCA would issue a unilateral enforcement action requiring the facility to take action • MPCA may need to specify needed emission reductions

More Related