CRONOGRAMA DE CIERRE DE VÍAS

CRONOGRAMA DE CIERRE DE VÍAS. Latacunga – Cotopaxi 23 de Enero de 2012. INTERSECCIONES A CERRAR. Milton Patino con Eduardo Vaca Milton Patiño con Rafael Cajiao Enríquez Marco Aurelio Subia con Cepeda Manuel. Marco Aurelio Subia con Galo Torres.

larissa
Download Presentation

CRONOGRAMA DE CIERRE DE VÍAS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CRONOGRAMA DE CIERRE DE VÍAS Latacunga – Cotopaxi 23 de Enero de 2012

  2. INTERSECCIONES A CERRAR • Milton Patino con Eduardo Vaca • Milton Patiño con Rafael Cajiao Enríquez • Marco Aurelio Subia con Cepeda Manuel. • Marco Aurelio Subia con Galo Torres. • Marco Aurelio Subia con Canar.

  3. FECHA DE CIERRE 01 DE FEBRERO FECHA DE APERTURA 10 DE FEBRERO Milton Patiño con Eduardo Vaca

  4. FECHA DE CIERRE 11 DE FEBRERO FECHA DE APERTURA 21 DE FEBRERO Milton Patiño con Rafael Cajiao

  5. Marco Aurelio con Galo Torres FECHA DE CIERRE 01 DE FEBRERO FECHA DE APERTURA 10 DE FEBRERO

  6. FECHA DE CIERRE 11 DE FEBRERO FECHA DE APERTURA 21 DE FEBRERO Marco Aurelio con Cepeda Manuel

  7. Marco Aurelio Subia con Canar

  8. Marco Aurelio Subia con Canar

  9. Marco Aurelio Subia con Canar

  10. Marco Aurelio Subia con Canar

  11. Marco Aurelio Subia con Canar

  12. FECHA DE CIERRE 11 DE FEBRERO FECHA DE APERTURA 21 DE FEBRERO Marco Aurelio Subia con Canar