An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DOE Review of the LCLS Project Project Planning & Controls M. Reichanadter / SLAC

  2. Outline • DOE and Multi-Lab Coordination • Project Office Support/Processes • Management • Procurement • Quality Assurance • Finance Support • Cost/Schedule Controls • Summary

  3. DOE-LCLS Coordination • Good working relationship between LCLS and DOE-BES program. • Weekly teleconferences • Monthly reports, quarterly status reports, semiannual reviews • Regular interaction with programmatic and construction support • Working relationship between LCLS and DOE-SSO is also good. • Weekly meetings between FPD and PD/CE. • FPD regularly attends Project meetings and interacts with staff at all levels. • LCLS meets weekly with DOE Site Manager on ES&H issues. • Impacts to project and possible future risks • CD-2b approved (Apr05) after extended EIR. Process not well defined, with periodic and unscheduled draws upon staff. Not sure when done. Next EIR? • 1Q-FY05 CR, funds arrived in Jan05. Cost impact with interim A/E, less assimilation time for staff. LCLS making workaround plans for FY06 CR.

  4. LCLS Project Coordination • ILCC meets quarterly to address issues affecting resource allocation and coordination to the LCLS project at the partner laboratories. • Federal Project Director is invited to ILCC meetings. • FAC meets semiannually and provides advice on the construction and technical capabilities of the LCLS. • SAC meets semiannually and provides advice on the scientific program of the LCLS.

  5. LCLS Multi-Lab Coordination • Staffing – Good Experience. • ANL and LLNL are ~staffed to planned (near peak) levels. • Recently added scope to partner labs; • ANL (Laser R&D, undulator supports) • LLNL (Laser R&D) • Procurement Performance/Reporting – Good experience. • LCLS decentralizes procurements to each lab. • Procurements >$5K are reported to the Project Office monthly. • EV Performance/Reporting – Good experience. • Technical status/issues reports reported to the Project Office monthly from ANL/LLNL PD’s. • CV’s and SV’s are modest and understood. Milestones are being met. • Actuals are reported to the Project Office monthly using a common Cost Account format. • Communication & Coordination – Good experience. • ILCC – meets Quarterly • LCLS Weeks – Quarterly (may reduce this to 2-3/year) • Provide good interaction when the design is rapidly advancing. • Periodic meetings with LLNL/ANL Management • Funding Transfers – Working but slow and time-consuming • Current system (TA) does not provide the flexibility to maintain agreement with P3 database. • Investigating DOE fund transfers in FY06 and beyond.

  6. LCLS Technical Addenda (TA) SLAC/ANL–LLNL TA define annual work scope, budgets and resources. Support IWO’s & MPO’s, CAO’s & provides staffing guidance TA Process; PO prepares draft TA in July for following FY. Basis approved P3 scope of work. Signature process (at the Lab Director level) starts 01Aug. SLAC transfers ~90% of approved funding. CR’s may delay the IWO/MPO but not the TA BCR’s are processed at SLAC in subsequent months. Reevaluate funding needs mid-FY (source P3). Amend TA. Authorize or rescind additional funds. Director’s signatures required. Begin planning for next FY in July. Problem: TA provides very detailed scope of work Duplicates in words the P3 Dbase. No longer in agreement with P3 after approved BCR. Possible solutions; TA to provide a high-level description of scope and reference the P3 dbase as the detailed scope of work. Replace TA with DOE fund transfer to each Lab. Do a mid-year correction Look at other multi-lab projects (i.e., SNS) This is a solved problem.

  7. LCLS Authorization @ ANL,LLNL Common drawing database used for all labs. LCLS QA manager working on ACD. Done via LCLS Transmittal Memo

  8. LCLS Project Office Support @ SLAC • ANL/LLNL have additional project office support for; • Finance • C/S (ANL only) • Procurements • QA

  9. Change Control • LCLS has been under Configuration Control and tracking since Oct04. Will start reporting into PARS M/E Apr05. • OECM certification of LCLS EVMS is tentatively scheduled for Sep-Oct 2005. • Review of all BCR’s for: • Cost changes >$100K • L2 milestone changes > 1 month • Technical interfaces or performance changes • Implement Technical/Change Control Board • Members are leaders of subsystems, PM, procurement, project controls, QA. • CCB provides advice/recommendation to Project Director. • CCB members meet monthly to address BCR actions and evaluate overall performance, variances, and overall project status.

  10. LCLS BCR Thresholds

  11. LCLS Risk Management • The LCLS RMP describes the process to identify, quantify, assess and develop management strategies for known risks to the LCLS project. • Some Known Risks at ANL • Vacuum Chamber, Mach Protection System • RF BPM Timing • Undulator Delivery Schedule • Some Known Risks at LLNL • Gas & Solid Attenuators • Imager Noise & Backgrounds • Some Known Risks at SLAC • Safety (we do not plan to matrix safety) • Overall Project Cost, Schedule Coordination • Laser, RF Gun, Injector Emittance • Alignment, Mag Meas Facility • Construction (Market Forces, Tunneling, CM)

  12. LCLS Risk Registry • Risk Registry (RR) monitors list of known risks to be managed until retired. • 4 risks have been retired since the last review. • Cont (>$73M) is adequate to address risks. Cum P(i) ~$12M • Managed and updated monthly • Readable copies of the RR are available on the web or in the hardcopy binders

  13. LCLS Advance Procurement Management Plan • Describes the roles and responsibilities of the key managers for LCLS procurements. • LCLS Procurement Manager • $2M Authority for LCLS Purchases • LCLS Procurement Expediter • LCLS Fabrication Expediter • Biweekly meetings SLAC Pur/LCLS • Currently meeting weekly to ensure good coordination and communication

  14. Quality Implementation Plan • Describes the roles and responsibilities of key managers for implementing and assuring quality processes on the LCLS. • Identifies control of LCLS technical, drawings, and document specifications and signature process. • Describes quality assurance and management as it is applied to the LCLS Project. • Quality and quantity of specs for the LCLS needs improvement. • Too much information still in the verbal domain. • Have recently added LCLS Quality Assurance Manager. • Spec/SOW writing class scheduled for June. • Added metrics to monitor progress on spec writing.

  15. ANL & LLNL QIP Quality standards at ANL / LLNL / SLAC are comparable

  16. Technical Specifications(define the LCLS baseline)

  17. Actual Cost Validation ProcessAll labs invoice/report at the task level Partner Lab Cost Data(Excel) SLACAccountingSystem (PeopleSoft) LCLSCost Database (MS Access) Invoices/AccountingReports Validate Totals LCLS Cost Data Reconcile by LCLS Fin Mgr Partner LabCost Data PMCSDatabase(P3/Cobra) Monthly LCLSAccountingReports Monthly CostData File(10th working day) LCLSCost Data Validate Totals Reconcile by LCLS Fin Mgr

  18. LCLS Req Approvals • SLAC Director’s signature required for >$100K procurements. • LCLS Procurement Mgr has $2M signature authority

  19. Summary • Management team and control processes are in place to manage the LCLS baseline • Procurements well underway • Need more/better technical specifications. • Multi-lab financial transfers needs improvement • EVMS has been tracking performance on the full integrated TPC of the LCLS since Oct04 • System is stable and reporting monthly • OECM validation in the Sep-Oct timeframe

  20. End of Presentation