An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report to the WRAP Emissions Forum EDMS Testing September 27, 2005 Presented by: Eastern Research Group, Inc.

  2. Overview of Presentation • Scope and Objectives • Methodology • Schedule for Completion Beta test-to-Beyond-Beta Test Comparison

  3. Beta Test Usability Functionality Main/home pages Standard reports GIS/Dynamic reports (limited) Data upload (limited) Data Integrity Inventory 1: 2002 Draft NEI Beyond-Beta Test Bug Resolution Functionality Ad hoc reports Standard reports (limited) GIS/Dynamic reports Data upload Data Integrity Inventory 8: Version 1.2 Revisions, fire, biogenics Specifications Compliance Scope and Objectives

  4. Beta Test Test Plan General Main/home All areas of functionality Test Worksheets Bugzilla Reporting Findings, statistical analysis Recommendations Beyond-Beta Test Acceptance Plan (Pechan) Test Plan New/revised functionality, data Bugzilla reports Specifications checklist Reporting Findings Recommendations EDMS Testing Methodology

  5. EDMS Bug Resolution • Beta Test Bugs: • 113 by ERG + 98 by Others • 211 Total • Beyond-Beta Test to Confirm: • 183 Closed • 20 Open - Enhancement • 8 Open - Unresolved • Others

  6. General Requirements Basic capabilities User’s Manual Data Requirements General Point, Area, Onroad, Nonroad, Fire, Biogenics, Tribal and County Accounting, Data Versions Functional Requirements General Import, GIS, Fire, Reporting, Export, Security Reports Standard, Ad hoc, Sector-specific Cross-Reference to Reported Bugs Specifications Checklist Reference: “EDMS Software and Hardware Development Plan,” Pechan 4/16/04

  7. Specifications Evaluation Process • First-time Test? • Applicable Closed Bug? • Evaluation: • Acceptable? • Unacceptable? • Cannot be Determined?

  8. EDMS Testing – Next Steps • Develop Queries from NIF files: 9/30 • New fire and biogenics data • Revised point, area, mobile, nonroad data • Begin Testing: 10/3 • Complete Testing: 10/28 • Draft Report: 11/15 • Final Report: 12/15

  9. THANK YOU! Any questions?