An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam Position MonitorsFAC ReviewOctober 29-31, 2007 • Stripline BPM Performance • and AFE Modifications • Cavity BPM Electronics • BPM Digitizer Comparison

  2. Stripline BPM PerformanceandAFE Modification

  3. BPM Performance • Take data synchronized pulse-by-pulse • Use linear prediction of each BPM from adjacent BPMS • Example: Compare bunch charge pulse-pulse 300 pulses 17 BPMs • Average rms/mean 0.0007 • May include pulse-pulse variation in losses

  4. Performance • Predict BPM position reading from linear fit to adjacent BPMs (model-independent) • 300 machine pulses Effective beam charge 0.35 nC sx = 2.5 microns sy = 1.7 microns

  5. BPM Performance • Q~ 200 pC • Resolution requirement is 10 microns for the small aperture BPMs • Meets resolution requirements

  6. AFE Modifications • CAL – Additional switch to improve isolation • CAL – Add on/off control to oscillator • CAL – Replace BP filter with packaged unit • Chan – Replace 2nd attenuator with 0-31 dB unit • Chan – Put anti-alias BP filter on the PCB • Revise limiter • Revise layout and connectors

  7. Status • Plan to build 53 modules for BSY/LTU/Dump. • Includes 3 spares for the injector. • And 3 modules for sector 24/25 (at the request of the commissioning team). Installation in January. • Most parts for AFE, PAD, and Clock Board on order (certainly long lead items). • Bulk of modules ready for installation in March/April.

  8. Cavity BPM Electronics

  9. LTU and Undulator BPM System Specification

  10. Cavity BPM Electronics

  11. VME ADC Module

  12. BPM Digitizer ComparisonSteve SmithAugust 8, 2007

  13. Analysis • CW input from RF generator • Through 140 MHz bandpass filter to reduce generator harmonics • Digitize • Plot spectrum • Find apparent frequency from data • Fit sine curve to data • Look at residuals to fit • Compare phase noise

  14. VME Digitizer @ -1 dBFS • Fit good to 6.5 ADC counts rms • ENOB = 11.5 • Harmonics <-80dBc

  15. VME digitizer • PAD @ -1 dBFS • Fit good to 16 ADC counts rms • ENOB = 10.2 • Harmonics <-72dBc

  16. Compare • Noise floor • Harmonic distortion • Other lines in spectrum • Input range

  17. Digitizer Comparison • VME 5 dB better on noise floor • VME 8 dB better on worst harmonic

  18. Comparison • Simplification • Reduces the number of accelerator ethernet ports, private ethernet ports, and DIGI ports. Communication with the ADC is over the VME backplane. • PAD would require enclosure and PS not yet designed. • Simplifies clock distribution (10 vs 18 dBm input) • Performance • Reduces broadband noise and harmonics. • FPGA has more computing power than the Coldfire. • Comparable data transfer rates ( measured 28 Mbytes/s for VME ADC). • Software • Both would need modification of the IOC software. • VME ADC needs a driver.

  19. Status • Two VME ADC modules produced and tested. • Production of 40 additional modules to start in November. • Cable plant is designed and in CAPTAR. • Clock and LO distribution is being designed (Andrew Young). • Power supplies and power distribution is being designed (Steve Smith). • Hardware and software will be ready by April.

  20. AFE Modification(Additional Slides)

  21. AFE Modifications

  22. Calibration • Calibrate through BPM • Via stripline-stripline coupling • Performance not yet verified

  23. CAL Modifications

  24. RF BPM AnalysisSteve SmithSeptember 5, 2007Updated Oct. 26

  25. Procedure • Calibrate with 2 mm scans: • LCLSscan_Horiz_Cal_200pc_2000um_VertOffset3mm_1_HighGain-2007-232-0820-131859.x.sdds • LCLSscan_Vert_Cal_200pc_2000um_VertOffset3mm_1_HighGain-2007-232-0820-131157.y.sdds • Check against other calibration scans • Analyze • LCLSscan_Vert_Cal_200pc_200um_VertOffset3mm_2_HighGain-2007-232-0820-161336.y.sdds • Take 1st 50 pulses to fix BPM-to-BPM alignment • Predict • X2 = linear combination of (X1, Y1, X3) • Y2 = linear combination of (X1, Y1, Y3) • For remaining events • Compare (X2, Y2) to predictions from (X1, Y1, X3, Y3) • All data taken at 200 pC charge

  26. Calibration

  27. Check Calibration Scales • Analyze two more independent sets of calibration data • Confirms scale • Note apparent mover inconsistency for last step of X scan

  28. Data Set • In middle of run beam (mover?) changes • Position jumps ~200 microns • Apparent beam angle changes • Study only first 150 pulses

  29. X sx = 360 nm

  30. Y sY = 270 nm

  31. Resolution Conclusion • Both X & y resolution are below 500 nm • Movers are a pain • Beam jitter is troublesome • Requires large scans to get a calibration • Should move BPMs independently • Then beam jitter doesn’t affect calibration

  32. Stability Tests(Sept. 6)

  33. Check Short Term Stability • Data: LCLSsynchlog_200pc_Horiz_00um_Vert_3000um_1_HighGain-2007-232-0820-132521.sdds • 1000 points at 6 Hz • Digitizer trigger glitch points removed • Y steering during first 30 points, ignore them • Alignment fit to next 50 points • Drift, resolution taken from remaining ~900 pulses • Resolution: sx =440 nm sY = 380 nm • Drift ~ 200nm in X, less than 100 nm in Y in 2.5 minutes

  34. LCLSslowlog_1HourStab_4-2007-234-0822- 161515.sdds • 30 pulses every minute • 5345 pulses total ~ 3 hours • Many multi-mm jumps pulses 350 and 700 • Clock seems unlocked from 390 to 490 • Ignore first 700 pulses • Use next 150 pulses (5min) of data for alignment • Estimate resolution and drift from remaining pulses • Resolution: • sX = 1.6 microns • sY= 1.9 microns • Drift: • Look at fit residual plots • (Vertical axes are in mm) • ~5 microns in X • ~3 microns in Y • Over 2.5 hours • Biggest motions coincide with beam motion • (miscalibration) 3 Hour Cruise

  35. Stability Conclusions • Stability results are almost good enough • Probably need better calibration • Maybe mechanical stability • Calibration is from 2 days prior to stability run • ???