Intervention scheduling at other labs Some interesting ideas seen at ARW conference
Brookhaven, New York • System in place since 2005 • Very similar to our situation • Not connected to access system (although that would be a wish)
SNS, Oak Ridge TN • Electronic Logbook • D7i / Infor EAM • Custom tool to read and write • Work scheduling
Oak Ridge Management Information Systems • Beam Time Accounting • Operations Accounting System (OAS) • Shift by Shift account of downtime • Electronic Logbook • Narrative account of shift activities including threaded discussion of breakdown and repair • CMMS – DataStream 7i (Infor) • Equipment Tracking • Asset Structure tables with parent-child relationships • “Cradle to Grave” tracking by position, location, asset • Asset status (Installed, In-Repair, Spare, Disposed Of) • Work Control • Use the same “Data Structures” for each: System, Sub-System, Sub-Sub-System , Sub-Sub-Sub-System, Asset, Position. Location • All 3 MIS Systems “Tied Together” through the Work Order Numbers
SLAC, CA • Radiation Safety Work Control Form • Work flow • Scheduling • Integrated with CATER “logbook”
SLAC RSWCF - Requirements • Accessible yet secure • History – Audit trail • Documentation Configuration Control • Work Flow • Electronic Signature • Integration with CATER (Comprehensive Accelerator Tool for Enhancing Reliability) Online RSWCFs
SLAC - CATER • Web-based tool for reporting and tracking problems and scheduling maintenance • Oracle database • Developed using Oracle Application Express (APEX) Online RSWCFs
Michigan Univeristy, NSCL Experimental schedule is determined 3 - 4 months in advance Preventive maintenance is scheduled in between experimental periods The maintenance group solicits tasks from other departments to add to the maintenance schedule Microsoft Project 2008 is used to build the maintenance schedule NSCL written software is used by the employees to get a list of their tasks The same software is also used by the employees to report the status of their tasks back to the project leader
ESRF, Grenoble • J5 software (south african company) • E-logbook • Integrated tool • Maintenance management