An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Science investigations on Landers «Luna-Resource» and «Luna Glob» Программа научных измерений на поверхности Луны для КА «Луна-Ресурс» и ПсМ «Луна-Глоб» V. Tretyakov, Space Research Institute, Moscow, Russia 12October2011 г.

  2. Science goals (Научные задачи) Задача 1: Исследование состава реголита и физических процессов на лунных полюсах Задача 2: Исследование свойств экзосферы на лунных полюсах и процессов взаимодействия космической плазмы с поверхностью Задача 3: Исследование внутреннего строения Луны методами сейсмометрии Goal1: Study of mineralogical, chemical, elemental and isotopic content of regolith and volatiles in polar area of Moon Goal 2: Study of plasma and dust exosphere of Moon and interaction of space environment with Moon’ surface Goal 3: Investigation of inner structure of Moon by means of seismic measurements

  3. Landersstructure(Конфигурация КА) ЛУНА-РЕСУРС / LUNA-RESOURCE Radiator Solar array Main Science Deck RITEG Robotic Arm Mini Rover(India) RIT Additional Science Deck

  4. Landersstructure(Конфигурация КА) ЛУНА-РЕСУРС / LUNA-RESOURCE ЛУНА-ГЛОБ / LUNA-GLOB Radiator Solar array Main Science Deck RITEG Robotic Arm Mini Rover(India) RIT Drilling system Additional Science Deck

  5. Science payload(Научная аппаратура)

  6. Mission’ scenario(Сценарий миссии)

  7. Main stages(Основные этапы) • Flight to Moon and landing (Перелет до Луны и посадка) • After landing commissioning(Этап диагностирования и тестирования аппаратуры после посадки) • Minimal success of mission(Выполнение задач для обеспечения минимального успеха миссии) • Operation on sunset(Работа на закате) • Preparation to night (Переход к ночи) • After night commissioning (Этап диагностирования и тестирования аппаратуры после ночи) • Operation (Штатная работа в течение основного и дополнительного сроков миссии) • Close of mission(Завершение миссии)

  8. 1. Flight to Moon and landing (Перелет до Луны и посадка) Goal – devices test after launch, background measurements • Flight to Moon • Background measurements (ADRON, RAT, PML, other -?) • Landing(no science operation except TV!).

  9. 2. After landing commissioning(Диагностирование аппаратуры после посадки) Goal– devices test after landing, correction of cyclograms according to real parameters P=[Wt], I=[Mb], Т=[оС]for planning • SC systems tests + charging • TV-panorama и TV-stereo • Mini Rover tests (на L-R) • Robotic Arm test (+ Drilling system for L-G) • BUNI tests • Other devices tests (depend on power)

  10. 3. Minimal success of mission(Обеспечение минимального успеха миссии) Goal– minimal set of science measurements • TV panorama and TV shooting for circumstances (1). • Mini Rover operation start (forL-R) • Testing Area selection for TVRPM and LIS. • Testing Area excavation by means Robotic Arm • TV shooting of Testing Area from TVRPM and LIS. • Delivery the sample of regolith by Robotic Arm to Chromatograph and LASMA • Analysis the sample of regolith by Chromatograph and LASMA • Repetition the TVRPM and LIS shooting of Testing Area up to time T, • where T=Sundown - Nearth days (see Rem. 1) • 9. Operation of monitoring device (ARIES, ADRON, SEISMO, TVKS, RAT, PML), TERMO (on L-G) and RADIOBEAKON up toT. REM 1: T= (Sundown - Nearth days) depend on landing site and power needs for night surviving. N 1

  11. 4. Operation on sundown (Работа на закате) Goal– safe operation and measurement before and after sundown • Stop science operation for time T. • Battery charging to 100% • BUNI turn on • Operation of ARIES, SEISMO, TVKS, RAT, PML, TERMO (on L-G) • Measurements during Y hours (see Rem. 2) • Data downlink on Earth • Science devices and BUNI turn off REM 1: T (=Sundown - Nearth days) depend on landing site and power needs for night surviving. N 1 REM 2: Y depend on power!

  12. 5. Preparation to night (Переход к ночи) Goal– safe transition to night regime • Parking of Robotic Arm and Drilling System • Charging to 100% • TM data downlink on Earth • Science devices and BUNI turn off

  13. 6. After night commissioning(Диагностирование аппаратуры после ночи) Goal– tests after night , correction of cyclograms according to real parameters P=[Wt], I=[Mb], Т=[оС]for planning • Charging to 100% + SC systems tests • Robotic Arm tests (+ Drilling system tests for L-G) • TVRPM and LIStests • BUNI test • Science devices turn on and tests

  14. 7. Operation(Штатная работа) Goal– routing science measurements • Wake up after night. • TVpanoramaandTVstero shooting circumstance. • TV shooting of Testing Area from TVRPM and LIS • Shooting of closes landscape from TVRPM и LISof SC • Drilling system operation for sample of regolith from depth • Robotic Arm delivery of sample of regolith to Chromatograph and LASMA • Sample of regolith analysis by Chromatograph and LASMA • Operation of monitoring device (ARIES, ADRON, SEISMO, TVKS, RAT, PML), TERMO (on L-G) and RADIOBEAKON up toT=Sundown - Nearth days • Preparation to Power Off mode during night

  15. 8. Close of mission(Завершение миссии) Goal – end of operation and start the support of future mission by means of beacon radio signal • Science devices turn off • PADIOBEACON turn to RITEG power • BUNI turn off • SC turn off

  16. Tasks(Задачи) • Program of science investigation during mission • Base set of cyclograms for operation on Moon. • Software for illumination and up/down radio link condition on landing site («Moon-Environment»). • Software for planning of device operation on Moon («Moon-Operation»). • On-Earth science experiment support segment (Hardware + «Moon-Environment» + «Moon-Operation» + Inetrnet + DataBase + Lasers + so on) • Tests and verification of device operation during on-earth (pseudo data and pseudo telemetry; hardware/software tests, cyclograms verification, failure mode analysis)