1 / 12

SPS 2, 3, 4 and 6 during W31-34 2019

This update provides information on the scheduled works at SPS facilities during weeks 31-34. The works include transformer installations, ventilation upgrades, cable campaigns, maintenance activities, and more.

lburke
Download Presentation

SPS 2, 3, 4 and 6 during W31-34 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS 2, 3, 4 and 6 during W31-34 2019 J.MEIGNAN EN-ACE-OSS 07/08/2019

  2. SPS 2: Works W31/32 • BA2: Surface • Transformer works (new one isbeinginstalled) • Toiletrenovation: Finishednextweek • Transformer consolidation for MBE.2103M (x3 replace by 1) RMT112/A2 • HV electricalworks • Underground: • Replacement of the emergency lighting • Shaft/TA • FS_(WP4) Installation Sprinkler (Shaft) • TT20 • FS_(WP2) Air Sampling Networks & Exhaust Lines Installation (TT20): Refused for ALLARA reasons J.MEIGNAN

  3. SPS 2: Works Scheduled W33/34 • BA2: Surface • FS WP4 surface works (05/08) • HV electrical works • EPC work on transformers • Underground: • Cable campaign (LSS2+,TT20,Arc2+) (12/08) • Replacement of emergency lighting • Shaft/TA • WP4 Installation Sprinkler (Shaft) J.MEIGNAN

  4. SPS 3: Works W31/32 • BA3: surface • Cable Campaign everywhere • BA3 - Upgrade ventilation 'Faraday Cage' • HV Electrical Works • Consolidation of the electrical infrastructure in SPS3. • SPS 200 MHz amplifiers maintenance / consolidation • Low Level RF Upgrade (Decommissioning & De-cabling / Faraday-cage upgrade (CV, Lighting, Rach, Floor,..)) • RF powering consolidation • Shaft/TA: • Blowing of the optic fibre • LSS3: • Blowing of the optic fibre • CV pipes: pressure tests J.MEIGNAN

  5. SPS 3: Works Scheduled W33/34 • BA3: surface • Cable Campaign (everychere) • BA3 - Upgrade ventilation 'Faraday Cage' • HV Electrical Works • SPS RF Low Level upgrade for LIU • Consolidation of the electrical infrastructure in SPS3. • SPS 200 MHz amplifiers maintenance / Consolidation • Low Level RF Upgrade • Shaft/TA: • Blowing of Fibre optic cables • LSS3: • Blowing of Fibre optic cables J.MEIGNAN

  6. SPS 4: Works W31/32 • BA4: Surface • Optic fibre installation • ECX4: • Crane PR-571 (“palan”) • BB4/ECA4: • Transformer consolidation for RBI.410010 (x1 replace by 1) RMT310/B4(cabling) • TT40/TI8 • TI8 Smoothing (Vertical/horizontal) J.MEIGNAN

  7. SPS 4: Works Scheduled W33/34 • ECX4: • Crane PR-571 (“palan”) • BB4/ECA4: • Transformer consolidation for RBI.410010 (x1 replace by 1) RMT310/B4 (LV cabling)) • TT40/TI8 • TI8 Smoothing (Vertical/horizontal) J.MEIGNAN

  8. SPS 6: Works W31/32 • BA6: Surface • Transformer refurbishment RMT117/A6 • BA6 travauxtuyauterie Eau Glacée pour BM6: until end of week 33 • Shaft/TA: • FS WP4 tests: delayed until 26/08/2019 • Septa conditioning: delayed • LSS6: • Install Fire door in LSS6+: done • WP3 installation + TT60 J.MEIGNAN

  9. SPS 6: Works Scheduled W33/34 • BA6: Surface • Cast Resin Transformer maintenance • Transformer refurbishment RMT117/A6 • HV electrical works • LSS6: • WP3 installation J.MEIGNAN

  10. Earthworks at SPS 6 Civil works at SPS 6 to be executed from week 23 to week 25 and from week 30 to week 32. Works include 2 main normal trenches. In red circles the areas that FAMY will deploy In blue rectangle the area that TE-EPC needs for maintenance activities only for week 24 (4 trafos, 1 day per trafo, no machinery needed by TE-EPC) BM6 BA6 J.MEIGNAN

  11. SPS 7: Works W29/32 • BA7: Surface • (BA7) Access Point & Site Rack Installation • Transformer maintenance J.MEIGNAN

  12. Any questions?

More Related