FEE Installation & Commissioning TPC Meeting, 22 November 2005. Content Installation Schedule Installation Procedure FEE Commissioning. Installation and Commissioning Schedule 1/2. Preliminary remarks. FECs Status Nr. of tested FECs: ~ 2000
E N D
FEE Installation & Commissioning TPC Meeting, 22 November 2005 • Content • Installation Schedule • Installation Procedure • FEE Commissioning
Installation and Commissioning Schedule 1/2 Preliminary remarks • FECs Status • Nr. of tested FECs: ~ 2000 • Nr. of FECs with cooling plates and cables (ready for installation): ~ 800 • Completion of the test and assembly February ‘06 • RCU Production (240 units including 10% spares) • completed in November ‘05 • RCU Mass Test • 50 units completely tested (100%) • completion of the tests: December ’05 • Delivery of tested DCS cards: December ‘05 • Delivery of tested SIU cards: April ‘06 • Assembly and final test of RCU + SIU + DCS: May ‘06
Installation and Commissioning Schedule 2/2 PHASE I • Installation of FECs and Backplanes Dec ’05 - Feb ’06 • functional and electrical test of each FEC • test of the connection between FECs and pad plane • test of the connection between FECs and readout backplane PHASE II • Inspection of the system with RCUs Mar – Sep ’06 • Inspection of up to 12 readout partitions (2 Sectors) concurrently • Comprehensive test: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required) PHASE III • Installation of RCUs May – Jun ’06 • thorough test of all (216) readout partitions
FE Cards Installation 1/3 STEP I Insertion of the card
FE Cards Installation 2/3 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) • Readout of trigger related data (pulser) • Connection to the pad plane • Measurement of VCCA, VCCD, IA, ID and T • Test of all CSRs, Control & Readout path U2F Card
FE Cards Installation 3/3 STEP II Mounting the backplanes