1 / 9

FEE Installation & Commissioning TPC Meeting, 22 November 2005

FEE Installation & Commissioning TPC Meeting, 22 November 2005. Content Installation Schedule Installation Procedure FEE Commissioning. Installation and Commissioning Schedule 1/2. Preliminary remarks. FECs Status Nr. of tested FECs: ~ 2000

leala
Download Presentation

FEE Installation & Commissioning TPC Meeting, 22 November 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FEE Installation & Commissioning TPC Meeting, 22 November 2005 • Content • Installation Schedule • Installation Procedure • FEE Commissioning

  2. Installation and Commissioning Schedule 1/2 Preliminary remarks • FECs Status • Nr. of tested FECs: ~ 2000 • Nr. of FECs with cooling plates and cables (ready for installation): ~ 800 • Completion of the test and assembly February ‘06 • RCU Production (240 units including 10% spares) • completed in November ‘05 • RCU Mass Test • 50 units completely tested (100%) • completion of the tests: December ’05 • Delivery of tested DCS cards: December ‘05 • Delivery of tested SIU cards: April ‘06 • Assembly and final test of RCU + SIU + DCS: May ‘06

  3. Installation and Commissioning Schedule 2/2 PHASE I • Installation of FECs and Backplanes Dec ’05 - Feb ’06 • functional and electrical test of each FEC • test of the connection between FECs and pad plane • test of the connection between FECs and readout backplane PHASE II • Inspection of the system with RCUs Mar – Sep ’06 • Inspection of up to 12 readout partitions (2 Sectors) concurrently • Comprehensive test: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required) PHASE III • Installation of RCUs May – Jun ’06 • thorough test of all (216) readout partitions

  4. FE Cards Installation 1/3 STEP I Insertion of the card

  5. FE Cards Installation 2/3 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) • Readout of trigger related data (pulser) • Connection to the pad plane • Measurement of VCCA, VCCD, IA, ID and T • Test of all CSRs, Control & Readout path U2F Card

  6. FE Cards Installation 3/3 STEP II Mounting the backplanes

  7. FE Cards Installation – Test Software

  8. FE Cards Installation – Test Software

  9. FE Cards Installation – Test Software

More Related