Control chart for variable

6. Control chart for variable. It is important to control over both the process mean and the process variability. Control the process by using the x chart Control the process variability by R chart Control chart has two plotting areas

Download Presentation

Control chart for variable

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 6

  2. Control chart for variable • It is important to control over both the process mean and the process variability. • Control the process by using the x chart • Control the process variability by R chart • Control chart has two plotting areas • An upper graph in which the individual or the average value of the sample or subgroup is plotted. • The lower graph plots the R chart or s chart or moving range chart.

  3. Subgroup Data with Unknown  and 

  4. Phase I Application of and R Charts • Eqns 5-4 and 5-5 are trial control limits • To determine if the process is in control when the initial samples were taken, plot the values of mean and R from each sample on the chart and analyze. If all the points are within the limit and there is no systematic pattern, then the trial control limits can be used in the future. • Determined from m initial samples • Typically 20-25 subgroups of size n between 3 and 5 • Any out-of-control points should be examined for assignable causes • If assignable causes are found, discard points from calculations and revise the trial control limits using the remaining points. • Continue examination until all points plot in control • Adopt resulting trial control limits for use • If no assignable cause is found, there are two options • Eliminate point as if an assignable cause were found and revise limits • Retain point and consider limits appropriate for control • If there are many out-of-control points they should be examined for patterns that may identify underlying process problems

  5. Revision of Control Limitsand Center Lines • Effective use of control charts requires periodic review and revision of control limits and center lines • Sometimes users replace the center line on the chart with a target value • When R chart is out of control, out-of-control points are often eliminated to recompute a revised value of which is used to determine new limits and center line on R chart and new limits on chart

  6. Phase II Operation of Charts • Use of control chart for monitoring future production, once a set of reliable limits are established, is called phase II of control chart usage (Figure 5-4) • A run chart showing individuals observations in each sample, called a tolerance chart or tier diagram (Figure 5-5), may reveal patterns or unusual observations in the data

  7. Rules for interpreting XmR charts • For X portion : apply WECO four rules • For mR portion apply rule 1 only.