An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Making the Move to PACS Monte Clinton, CRA Dartmouth-Hitchcock Medical Center

  2. Disclaimer • This presentation is about a PACS implementation at one facility (DHMC) with one vendor (IDX) and is being given as an example of a successful PACS implementation • Other facilities and vendors can do a similar PACS implementation using this partnering program and methodology • DHMC does not endorse IDX or any other vendor’s products and services

  3. Existing 3 MR + 1 Mobile 3 CT 3 VIR + 1 PICC 8 DX 3 R/F 5 US 3 NM + PET/CT 5 Mammo New in 2004 Replace in 2004 1 CT in new ED CT/Angio 1 Angio OR compatible 6 DR-- 4 CR 1 DR/CR in ED + 1 CR trauma 1 DR/Fluoro 2 US in new building 1 NM + Fixed PET/CT 2 DR – Mammo new building Radiology Equipment 2004

  4. Why Install a PACS? • Expansion to Provide New Space for: • Mammography • Nuclear Medicine • Vascular Interventional • Offices and conference space • New Outpatient Clinical Building to: • Eliminate over crowding • Add new MDs and exam rooms • Bring imaging to the patient • Minimize radiologist travel

  5. Why Install a PACS? • Save money – Increase reimbursement • Reduce medico-legal risk • Eliminate Film and processing costs • Reduce Film Library staff and space • Improve billing collections • Reduce medico-legal exposure

  6. Why Install a PACS? • Improve staff and imaging room productivity • Increased staff productivity • Reduction in the number of staff • Increased imaging room productivity • Eliminate imaging rooms

  7. Why Install a PACS? • Improve service to your customers • Single set of film images limits collaboration • Minimize lost studies and revenue • Minimize treatment delays • Speed service to referring clinician and patient

  8. DHMC’s Steps to Justify PACS • Internal justification – The major players • Large capital or operating cost impact requires multiple levels of approval – at DHMC this was: • Radiology • Information Systems

  9. DHMC’s Steps to Justify PACS • Internal justification – Institutional leadership • Administrative leadership • Finance Committee • Board of Trustees – final go or no go

  10. PACS: Getting Started • Outside experts – PACS consultants • Institutional experts • Radiology • Information Systems

  11. PACS: Getting Started • Educate yourself about PACS • Ask your colleagues about their experiences • Attend meetings such as this one • Vendor discussions and demonstrations at trade shows - AHRA, RSNA, SCAR • Understand your own environment and needs

  12. PACS: Getting Started • Request for Information (RFI) • Invite selected vendors to respond to RFI • Get a list of their customers to contact • How would their system fit into your facility • RIS and PACS compatibility

  13. Interface or Integrate • The critical relationship between the RIS and the PACS • Have the RIS and the PACS vendors worked together before? • Which vendor has primary responsibility or are you expected to do problem triage?

  14. PACS: Getting Started • Request for proposal (RFP) • Invite a limited number of vendors to bid • Vendor clarification meetings • RFP review and analysis • Site visits at working clinical sites • Final negotiation – Purchasing and Vendors

  15. Paying for a PACS • Capital Purchase or Operating Expense • Capital purchase • Major capital expense – compete for funding • Cost to upgrade and remain technologically current • Ongoing service and maintenance cost • Application Service Provider (ASP) • Costs are an operating expense • Always kept technologically current • All inclusive - charges fluctuate with activity

  16. The PACS Timeline • Develop a realistic implementation timeline with buy-in from all affected stakeholders Radiology – all levels Information Systems Institutional Leadership Referring Clinicians PACS Vendor

  17. DHMC’s PACS Timeline • Phase 1 • 1-2003 Archiving started in CT, MR, US • 4-2003 Live in CT, MR and US – stop film • Phase 2 • 9-2003 Archiving started in DX • 12-2003 Live in DX – stop printing film • Phase 3 • 8-2004 Archiving started in Angio and NM • 1-2005 Angio and NM after IDXrad V10

  18. Partnering with the PACS Vendor • Agreement with the vendor on the timeline and implementation phases • Appoint key staff from each stakeholder • This must be a win – win endeavor

  19. Planning the Implementation • Weekly meetings of the • PACS Working Group • Radiology Director • Radiology PACS Administrator • Radiology Clinical Operations Manager • Radiology Asset Manager • IS Director • IS Liaison

  20. Guiding the Implementation • PACS Implementation Team • bi-monthly meetings • Chairman of Radiology • Chief Information Officer • Vice President of Clinical Operations • The Six Working Group Members

  21. Before and After Implementation • Ongoing follow-up • Weekly calls - Radiology and vendor • Updates to the clinical departments • Regular updates to the Board of Trustees • Monthly updates to the Radiology faculty • Weekly updates to the Radiology staff

  22. Selecting the Hardware • Involve the end user in equipment selection • Radiologists given a choice of monitors • Referring clinicians given a choice of monitors • Specialty sections given choice of monitors • OR selected from 5 large flat panel monitors • ED selected the best monitor for their use

  23. Reading Room Design • Radiologists given a choice of layout • DHMC rejected the modular systems • Radiologists preferred two image monitors • Room lighting critical • Calculate room temperature requirements • Gradual phase out of alternators

  24. Dealing with Prior Studies • DHMC chose not to digitize prior studies • Prior studies are available if needed • After six months there was very little need for prior studies • Some studies are digitized so they can be used for comparison – joint replacements

  25. The Archive • DHMC’s PACS Archive • In-house dual servers maintained and remotely monitored 24/7 by vendor • External archive backed up daily to vendor’s San Diego archive facility • DHMC’s failsafe back-up archive -- DVDs burned daily and stored at DHMC

  26. Dartmouth Hitchcock Medical Center Imagecast™ RISv9.8/PACS Display Stations CT/Body Read Area (3) CT Rad/Onc Fiber Image Archive CT GE - 3 100MB 10/100 MB Imagecast PACS database Imaging Suite Neuro Read Area (3) MR GE- 4 MR Mobile RF Siemens 3 U/S Read Area (2) Dual DICOM Processors (~3 weeks) netCache (~6 months) Persistent Store (scalable life) DR Philips –6 CR Philips - 3 DX Read Area (5) ConnectRv4.0 IDXRad v9.8 ICU Offsite Disaster Recovery Film Digitizer 2 T-1 Enterprise Access via CIS US – 7 HDI Acuson Onsite Disaster Recovery HC5 DVD Server 10/100 MB LAN-10/100 Lebanon DHMC Campus U/S Kodak MiniPACS (priors only) Speare – Plymouth NH Kodak Drylaser Printer - 5 US – HDI 2 10/100 MB MR - Mobile CT Picker Any Image, Anywhere, Anytime 10 MB T-1 WAN/DSL/Cable Dated 05/05/03

  27. Training the Radiology Technologists and Support Staff • Modality integration in advance – Imaging Suite • Super users identified - trained in each section • On-line training with vendor for super users • Make the process exciting and rewarding

  28. Training of the Radiologists • Vendor provided 1 to 2 hours of one on one training 2 to 3 days before activation • Return visits after activation for more training if needed • Give them all the time and training they want • Ask radiologists and residents to offer suggestions for enhancements

  29. Keep Your Staff Informed • Being upfront about what is happening and when it will impact the lives of staff will head off rumors • Publish a PACS phase in plan – DHMC 1 year • Stop hiring permanent full time Film Library \employees a year before implementation • Work with HR to find jobs for displaced staff

  30. Contingency Plans • Referring clinicians demanding film • Acceptance of CD copies by other facilities • Urgent results reporting • Special requests • System failure – power failure, virus, etc.

  31. Partner With Your Vendor • Clear objectives spelled out in the contract • Agree on timeline, payment and penalties • Clearly define facility - vendor responsibilities • Track progress with regular reports • Make the PACS implementation a win – win program for both your facility and the vendor

  32. What DHMC Did Right • Developed and used a workflow analysis • Piloted PACS with 15 referring clinicians • Had a close relationship with the PACS vendor • Integrated modalities in advance • Integrated RIS/PACS with electronic medical record

  33. A Chairman’s Perspective • “ Never in my 29 years as a chairman have I made a decision that has received such universal acceptance from both the radiologists and the referring clinicians” • Peter Spiegel, MD • Chairman – Radiology

  34. A Director’s Perspective

  35. Contact Information • Monte Clinton, CRA • Dartmouth-Hitchcock Medical Center • Monte.Clinton@Hitchcock.org • www.dhmc.org/dept/radiology