50 likes | 177 Views
EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE. Status on PRR recommendations and actions. Guillaume Prévôt APC, Paris. - Recommendations status - PRR Review report: actions - Conclusion. Recommendations. 3 recommendations : - Project organization
E N D
EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Status on PRR recommendationsand actions Guillaume Prévôt APC, Paris • - Recommendations status • - PRR Review report: actions • - Conclusion
Recommendations • 3 recommendations: • - Project organization • - First flight as soon as possible • - Schedule control • Project organization • “ Defining the CNES organization, introducing an electrical architect, identifying all the activities relative to the harness, clarify the participations to the AIT, the instrument GSE responsibilities.” • Action 1.1: The team has provided the updated organization. • Action 1.2: The team has provided the updated development plan to CNES. Status on PRR actions
Recommendations • First flight as soon as possible • “In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.” • Schedule control • “In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.” • Action 3.1.1: The 3 laboratories have done a proposition for a new project manager and it has been accepted by CNES. • Action 3.4.1: The team has provided the updated instrument planning to CNES. Status on PRR actions
PRR Review report: actions • 41 actions have been taken with answers from the project team expected for the design review. • Updates of: • The TechnicalSpecifications document (EUSO-TS-INST-206-LAL_V2.0) • The Instrument Definition document (EUSO-DF-INST-204-LAL_V2.0) • The Organization Note (EUSO-ON-INST-201-LAL_V2_6) • The Compliance Matrix (EUSO-PA-INST-203-LAL_V2.0) • The RiskAnalysis document (EUSO-RI-INST-404-IRAP V1.1) • The Development Plan (EUSO-DP-INST-207-LAL_V2.0) • Writingof: • A Thermal Analysis document (EUSO-TA-INST-409-IRAP V1.0) • A Mission Analysis document (CNES) • ICD documentation (EUSO-IC-INST-407-IRAP_V1.0 (electronics) and EUSO-MI-INST-408-IRAP_V1.0 (mechanics)) • A AIT Plan document (EUSO-AI-INST-251-LAL_V1.0) • A calibration Note (EUSO-CN-INST-003-APC_V1.0) Status on PRR actions
PRR Review report: actions • 39 actions have been closed by the team. • 2 actions are open (about cleanliness strain). • FB-14 and OLM-14 are open and they will be dealt with on a specific note delivered at the AIT Key Point. Status on PRR actions