1 / 21

Public hearing on conditional grants and capital expenditure: 3rd quarter

Public hearing on conditional grants and capital expenditure: 3rd quarter. Presentation to Select Committee on Finance Northern Cape’s Department of Agriculture and Land Reform 19 February 2007. Overview. Equitable share versus Conditional Grant allocation

Download Presentation

Public hearing on conditional grants and capital expenditure: 3rd quarter

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Public hearing on conditional grants and capital expenditure: 3rd quarter Presentation to Select Committee on Finance Northern Cape’s Department of Agriculture and Land Reform 19 February 2007

  2. Overview • Equitable share versus Conditional Grant allocation • 3rd quarter expenditure on conditional grants • Conditional grant spending vs. cash allocation • Conditional Grant expenditure Jan 2007 • Expenditure trends per month • Situation analysis on conditional grants • Monitoring and Evaluation • Challenges for conditional grants • Plans to improve delivery on conditional grants

  3. Trends: equitable share versus conditional grant allocation

  4. 3rd quarter expenditure – Conditional Grants

  5. Conditional Grant spending versus cash allocation

  6. End January 2007 expenditure – Conditional Grants

  7. Expenditure trends per month

  8. Situation Analysis - CASP • Situation analysis • 28 projects implemented during 2005/6 with a budget of R 13,148m • Struggled to complete all projects and thus requested R6,719 m rollover • Only 12 new projects approved for 2006/7 with budget of R15,777 m • Officials concentrated on completing projects remaining from 2005/6 and implementing new projects for 2006/7 • Expenditure 3rd quarter • The total transfer received from National to Province by the third quarter is R 12,622 million and • R12,460m actual expenditure as at end December ’06. • 99% of the transfer received was spent

  9. Situation Analysis – Land Care • Situation analysis • 15 projects implemented during 2005/6 with a budget of R2,000 m • Requested rollover of R1,873 m • 15 projects approved for 2006/7 with a budget of R5,785 m • Expenditure • R 4,629 m transferred from National to Province by the 3rd quarter and • R 6,019 m actual expenditure as at end Dec ’06. • 130% oftransfer received was spent • Issues requiring on-going attention • Monitoring of the implementation phase • Conflict management within communities/project beneficiaries • All projects tenders already advertised • Project schedule still on track

  10. Situation Analysis - PIG • Situation analysis • 8 projects implemented during 2005/6 with a budget of R3,172 • R1,588 requested for roll over • 5 projects approved for 2006/7 • Expenditure • Transfer from National to Province by 3rd quarter is R1,611 • R2,632 m actual expenditure as at end December ’06. • 163% of the transfer received was spent • Issues requiring on-going attention • PIG projects in tendering phase during 1st quarter • Implementation only in 2nd and 3rd quarter

  11. Monitoring and Evaluation • Senior management evaluates expenditure monthly • Project Coordinating Committee established and meetings held quarterly • Assesses project proposals • Recommends for approval • Assesses and evaluates progress

  12. Challenges for conditional grants • Same officials have to implement new projects and provide after-care at the same time • More demands by other land reform beneficiaries especially the more they see implementation and changes in the neighbouring approved projects or communities • Credit facilities for BEE contractors problematic thus a delay in delivery of material and other services • Some of the suppliers do not deliver material on the agreed timeframes and that delays payment • Some of the companies experience cash flow problems during the course of completing a project

  13. Plans to improve delivery on conditional grants • 2006/7 projects • Ensure that 2006/7 projects are implemented according to plans • Not to allow any roll-overs from 2006/7 • Monitor and assess implementation through

  14. Plans to improve delivery on conditional grants • Monthly review of expenditure • Holding quarterly reviews with project leaders • Senior managers visiting projects regularly to monitor progress • 2007/8 projects • Completed business plans for 2007/8 projects by end of September 2006 • Advertise tenders between Jan-March 2007 • Start implementing as of April 2007

  15. Trends in capital expenditure

  16. Solar Power for Stock Watering

  17. Sub surface Drainage Installation

  18. Sub surface Drainage Installation

  19. Soil Conservation

  20. THANK YOU