Superload Move

Superload Move. April 06, 2013 Prasad Nallapaneni & Jonathan Mallard Structure and Bridge, VDOT. Superload - Route. Superload - Details. Total Distance : Approximately 96 Miles Number of Structures: 62 (61 VDOT) Bridges: 25 Culverts: 37 VDOT Structures: Analyzed in-house: 47

leona
Download Presentation

Superload Move

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Superload Move April 06, 2013 Prasad Nallapaneni & Jonathan Mallard Structure and Bridge, VDOT

  2. Superload - Route

  3. Superload- Details • Total Distance : • Approximately 96 Miles • Number of Structures: 62 (61 VDOT) • Bridges: 25 • Culverts: 37 • VDOT Structures: • Analyzed in-house: 47 • Third Party Analysis: 16

  4. Superload - Detials • Analysis Method: • In house: LFR/LRFR – • VIRTIS if available • Compared Simple span moments with HS20 ratings • Third Party: LRFR -16 Bridges • Verified hand calculations • / LFR analysis • Structures Jumped: 5 (five)

  5. Superload - Permit

  6. Superload - Permit

  7. Superload - Jump

  8. Superload - Restrictions

  9. Superload - Crabs

  10. Superload

  11. Superload

  12. Superload • Attempt Made: • Run few bridges in 6.5 with Non Standard Gage Vehicle • Compare with calculations received from Third Party and in-house STAAD runs

  13. Superload • Bridge Fed ID: 24505

  14. Superload Bridge Fed ID:24505 Wheel Configuration: Straight

  15. Superload • Bridge Fed ID: 25334

  16. Superload Bridge Fed ID:25334 Wheel Configuration: Straight

  17. Superload • Bridge 24231

  18. Superload Bridge Fed ID:24231 Wheel Configuration: Straight

  19. Superload Difficulties Faced • Installation issues with 64 vs. 32 bit • Long time run process • Memory issues • Run only from bridge explorer • Not able to get a detailed LL output.

  20. Superload

  21. Superload • http://www.youtube.com/watch?v=Dmacnt5GaHw • http://www.youtube.com/watch?v=v8_3uyecXSc

  22. Field Operations • Field Surveys • LIDAR survey was taken before and after on 5 long span structures. • Calculated LL deflections from vehicle were up to 6” • Survey showed before and after elevations of the bridge deck surface and the bottoms of the girders were within the tolerance of the method used. • Any post move deflection was undetectable from a survey perspective.

  23. Field Operations • Structure 10720, Lee County • Originally designated to be ‘jumped’ • Field review of route raised concerns about limited hospital access for an extended period. • Detour length = 50 miles. • Hauler’s consultants recommended removing a 20 kip counterweight from each of the tractors. • Tractors effectiveness was limited due to traction loss.

  24. Field Operations • Structure 24362, Norton • Rated by private consultant. Substructure controlled at pier due to uneven span arrangement • Travel restrictions were issued. • During transport, hydraulic line broke while crossing the structure. Lead tractor was over critical pier. • After line replacement, vehicle initiated movement from rear tractor, which was not on bridge.

  25. Field Operations • Structure 22454, Norton • Simple Span Plate Girder with partial depth welded diaphragms • First diaphragm on girder 4 cracked at the base. • Retrofitted by drilling, arrested by next inspection cycle.