Superload Move. April 06, 2013 Prasad Nallapaneni & Jonathan Mallard Structure and Bridge, VDOT. Superload - Route. Superload - Details. Total Distance : Approximately 96 Miles Number of Structures: 62 (61 VDOT) Bridges: 25 Culverts: 37 VDOT Structures: Analyzed in-house: 47
E N D
Superload Move April 06, 2013 Prasad Nallapaneni & Jonathan Mallard Structure and Bridge, VDOT
Superload- Details • Total Distance : • Approximately 96 Miles • Number of Structures: 62 (61 VDOT) • Bridges: 25 • Culverts: 37 • VDOT Structures: • Analyzed in-house: 47 • Third Party Analysis: 16
Superload - Detials • Analysis Method: • In house: LFR/LRFR – • VIRTIS if available • Compared Simple span moments with HS20 ratings • Third Party: LRFR -16 Bridges • Verified hand calculations • / LFR analysis • Structures Jumped: 5 (five)
Superload • Attempt Made: • Run few bridges in 6.5 with Non Standard Gage Vehicle • Compare with calculations received from Third Party and in-house STAAD runs
Superload • Bridge Fed ID: 24505
Superload Bridge Fed ID:24505 Wheel Configuration: Straight
Superload • Bridge Fed ID: 25334
Superload Bridge Fed ID:25334 Wheel Configuration: Straight
Superload • Bridge 24231
Superload Bridge Fed ID:24231 Wheel Configuration: Straight
Superload Difficulties Faced • Installation issues with 64 vs. 32 bit • Long time run process • Memory issues • Run only from bridge explorer • Not able to get a detailed LL output.
Superload • http://www.youtube.com/watch?v=Dmacnt5GaHw • http://www.youtube.com/watch?v=v8_3uyecXSc
Field Operations • Field Surveys • LIDAR survey was taken before and after on 5 long span structures. • Calculated LL deflections from vehicle were up to 6” • Survey showed before and after elevations of the bridge deck surface and the bottoms of the girders were within the tolerance of the method used. • Any post move deflection was undetectable from a survey perspective.
Field Operations • Structure 10720, Lee County • Originally designated to be ‘jumped’ • Field review of route raised concerns about limited hospital access for an extended period. • Detour length = 50 miles. • Hauler’s consultants recommended removing a 20 kip counterweight from each of the tractors. • Tractors effectiveness was limited due to traction loss.
Field Operations • Structure 24362, Norton • Rated by private consultant. Substructure controlled at pier due to uneven span arrangement • Travel restrictions were issued. • During transport, hydraulic line broke while crossing the structure. Lead tractor was over critical pier. • After line replacement, vehicle initiated movement from rear tractor, which was not on bridge.
Field Operations • Structure 22454, Norton • Simple Span Plate Girder with partial depth welded diaphragms • First diaphragm on girder 4 cracked at the base. • Retrofitted by drilling, arrested by next inspection cycle.