1 / 10

Background

Grizzly-Summer Lake 500 kV Line Planned Outage May 27-June 15 2008 1900-2400 hours Mike Viles – BPA Transmission Operations Technical Management Team June 4, 2008. Background.

leroy
Download Presentation

Background

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Grizzly-Summer Lake 500 kV LinePlanned OutageMay 27-June 15 20081900-2400 hoursMike Viles – BPA Transmission OperationsTechnical Management TeamJune 4, 2008

  2. Background • A continuous outage of sections of the Grizzly-Summer Lake line had been planned for spacer damper replacement for May 27 – June 15 • A planned outage of this line is hard to get because: • It significantly reduces the California-Oregon Intertie (COI) capability • OTC reduces from above 4000 MW to 2800 MW north to south to protect for the next double contingency • Ponderosa 500/230 kV transformer forced out of service and creates potential load service issues except during lighter load conditions • Late spring loads are lighter due to mild temperatures compared to winter and summer loads

  3. G Legend JOHN DAY SLATT 230kV 500kV O/S BUCKLEY MARION Cascades ALVEY GRIZZLY SAME CORRIDOR DIXONVILLE PONDERSOA CENTRAL OREGON LOAD MERIDIAN KLAMATH COGEN G SUMMER LAKE IDAHO CAPT JACK MALIN OREGON-CALIFORNIA INTERTIE OLINDA ROUND MTN

  4. Outage • In early May it was decided to cancel this line outage due to concerns about the impact of the outage on the COI with a late runoff • Work to replace gun shot insulators, repair conductor and repair overhead ground wire on the line had also been planned • There was a need to get that work done to prevent an unplanned outage of the line • There would not be another window of opportunity to take a planned outage of this line in 2008

  5. Damaged Insulator String

  6. Repairing Insulator String

  7. Outage • Daily outages from 1900 to 2400 hours were coordinated to minimize the impact of the outage • All the repairs that are needed can be done during this 20 day period • Some of the work is being done during darkness so only the local line crew that is familiar with the terrain is willing to do the work

  8. Outage Impacts • The COI OTC is reduced to 2800 MW • The next slide shows the actual COI flow versus the scheduling limit which is lower than the OTC • The PDCI is allowed to go to full 3100 MW capacity during the outage

  9. COI Actual Flow vs Scheduling Capacity

  10. The End

More Related