An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HINS 6-Cavity Test 3 Month PlanJan 12, 2012

  2. Current Schedule • 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall slits and fast Faraday cup. • Shutdown for H- upgrade scheduled to start Feb 6 (Monday). • Estimate 3-4 weeks to finish all upgrade mechanical work. • Lab shutdown still scheduled to start March 1. • Main injector quads may be reclaimed at the end of March. • New klystron scheduled to arrive in early spring.

  3. BPM Upgrade Shutdown • Install buttons on all blanked off BPM ports. • Replace cavity wire scanner with a BPM. • Install new can for slit scanner and fast Faraday cup. New BPM Location New can Location

  4. Pre-upgrade Studies • Perform cavity phase scans using new BPM. • Tune cavities to specified amplitude and phases, and measure beam emittance using quadrupoles and slits. • Document final settings before H- shutdown.

  5. More realistic (?) schedule • Feb 1st, H- source to alignment • Depends on how much time needed for alignment • Simply need to be early enough • Feb 3rd, last H+ run • Feb 6th, start removing H+ source • Mostly electrical first (cables and such), then mechanical (source and stand out) • Feb 16th, new stand installed • Feb 24th, H- source installed • Includes vacuum connected (may be not pumped down) • Includes all electrical connections • Feb 27th, alignment • Feb 28th, start commissioning • HV => Plasma => Beam 3 weeks

  6. Other HINS Shutdown Activities • Waveguide distribution from klystron to test area will be removed. Klystron will only power beam line. • Modify klystron interlocks, to remove monitoring of RF test areas. • Complete documentation necessary for remote operation of facility. • LLRF work on vector modulator feed-forward.

  7. H- Startup • Will start (hopefully) sometime in early March, contingent upon good vacuum, working power supplies, controls, and safety approval. • May need a week to optimize LEBT for best RFQ transmission. • Retune cavities for transmission to diagnostic line. • Measure emittance of new beam with slit scanner.

  8. Loss of MI Quadrupoles • NOVA project will want the spare MI quads when they are ready to construct magnet girders. • Present commitment date is end of March. • This will render diagnostic line and Buncher 2 useless, but RF work and beam through Cavity 4 can continue. These quads go away.

  9. Other Items During AD Shutdown • Complete 6-cavity test with vector modulator controls. • New klystron due to arrive in spring. Current plan is to swap out klystrons (will this require mech. support?). • Complete beam line design for 2.1MeV chopper test.