An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Genset Sizing with SpecSizer Steven Baker EP Commercial Marketing

  2. SpecSizer

  3. Under-sizing Over-sizing SpecSizer Value • Accurately sized gen-sets • Perform efficiently • Meet site operating demands • Improperly sized gen-sets • Adds cost • Poor performance • Undersize • Additional gen-sets to meet job site requirements • Job site footprint designed around smaller genset • Oversize • Competitive bid/price disadvantage • Engines operate continuously at light load; prone to wet stacking, slobber (cylinder bore and liner glazing) Least Cost Installation

  4. SpecSizer Performance to Standards • Specifying generator sets for voltage and frequency transient response • NFPA 110 • North American spec • Generator must start, pick up full-rated load, maintain stable voltage and frequency • ISO8528-5 • world-wide standard • defines operating limit values for performance classes G2-G4, for critical genset sizing parameters • transient frequency deviation (dip), transient voltage (dip), and frequency and voltage recovery time

  5. SpecSizer Performance Capability • Influencing Parameters Genset Transient Response • Project Parameters: Conventional vs. Frequency Limited Sizing • SpecSizer Help

  6. Getting Started • Select • New 3-Phase or Single Phase Project • Open Existing Project • Use Wizard Tip: Easier to use the Wizard icon for Wizard. Wizard Icon

  7. Set Your Preferences • Menu bar • File, Preferences • (8) Languages

  8. Help (Project Parameters) Generator Set Duty Sizing Methodology Emissions Certification Menu bar Help Topics Help is Available

  9. Links for Sales Support • Menu bar • Cat.com • Spec Sheets • Cat.com • http://www.cat.com/cda/layout?m=37480&x=7 • Dealer locator • http://www.cat.com/powergeneration/specsizer

  10. Project Parameters Features • Standby Caterpillar & Olympian • Caterpillar 300 – 3100 kVA • C175-20 (5000 kVA) • Olympian 13.8 – 700 kVA • Best Fit Transient Performance • CDVR @ Std vs. Optimized VR Slope • Percent of Intermittent Motors • diversity factor for competitive sizing

  11. Non-Linear Loads Load Scenario • Linear & Non-Linear Loads • 3-phase Motor (w/ VFD/VSD, Soft Starter) • Single phase Motor • 3-Phase Air Conditioning (w/ VFD/VSD, Soft Starter) • Single Phase Air Conditioning • Centrifugal Pump (w/ VFD/VSD, Soft Starter) • Lighting • Fluorescent, Incandescent, Gas Discharge, Ultraviolet • Resistive • Office Equipment • UPS • Battery Charger • Medical • Elevator • Induction Furnace (w/ Thyristor) • Welder • Miscellaneous (w/ Pulse Rectifier) Range < 40%

  12. Generator Set Selection • Sizes & Selects Genset • Load Analysis Summary • Algorithms • Site Conditions + Load Scenario • Inrush, Running & Non-Linear kW & kVA • Load dialog inputs • Load sequencing • % Genset Rated Capacity (EkW)

  13. Generator Set Selection • Starting & Selection Analysis • Genset list per • Region installed (price list) • Site Conditions (e.g. Standby) • Selection per • Load characteristics (e.g. linear vs. nonlinear) • Site Conditions (e.g. Altitude & Ambient) • Derate

  14. Generator Set Selection • Starting & Selection Analysis • Genset Transient Capability • Factory genset transient performance tests • Volts/Hz Optimization C175 3000 kVA vs. 3516B 2500kVA

  15. Generator Set Selection • Go to Best Fit Genset • Guide Spec • MS Word doc, editable • Paralleling • Customer/Dealer Sales Support Links

  16. Generator Set Selection • Note provided:Why the next smallest genset fails Load requirement Loads require 1613.9 RkW 2500kVA Genset capable of 1497.8 RkW when derated

  17. Generator Set Selection • Alternator Frame Options Alternative Genset (with capable alternator) to sized genset in Inventory? Table provides Cat dealer options.

  18. Technical Tab • Sizing Report • Load Analysis Summary • Generator Set • Engine Technical Data • Alternator Technical Data • Load Report • Permitted Dip • Predicted Dip • Load Analysis • Maximum Step and Maximum Peak SkVA/SkW • Final Running kVA/kW • Step transient performance graph • Transient Performance Report • Step Fdip and Vdip • Step Transient Performance Graph • Block Load Transient Performance Table • Block Load Transient Performance Graph

  19. SpecSizer - Load Transients & Genset Transients Load Transients Genset Transients

  20. Accurate Sizing Continuous development since 1/2006 NPI updates 2x-3x annual Pre-release regression testing Competitive Sizing Benchmark against competitor tools Robust algorithms Factory gen-set transient response test data Sizing Competitive Gensets

  21. Restrictive Fdip / Vdip Wizard 20 Steps, Optimum step Motor Starting Reduced Voltage Starters Motor Starting, Low Inertia Motors Non-linear loads, Filters & Pulse Rectifiers Efficiency, Air Conditioners EER & SEER Voltage Regulator Optimization @Site Voltage (Amps) Load Factor (Duty Point) Competitive Sizing Options

  22. Restrictive Fdip / Vdip • Loads & Steps with restrictive frequency dip (Fdip) and voltage dip (Vdip) • cause all loads or load steps sequenced later in a Load Scenario to adopt the same restrictive frequency or voltage dip • (e.g. 30%) Fdip / Vdip loads adopt 10% Fdip / Vdip if the prior step contained restrictive dip • Avoids over-sizing the gen-set • If possible - sequence restrictive loads later in load scenario • e.g. UPS load • Must adhere to specification

  23. Restrictive Fdip / Vdip Resized:2500kVA 3516  1750kVA 3512B Step#1 Motor load with 10% Fdip moved to Step#2

  24. Restrictive Fdip / Vdip 1750kVA 3512B

  25. 4 Steps  15 Steps 20 Step Wizard & Optimum Step 3512 (1137kVA)  C18 (545 kVA)

  26. 64% 80% tap (Wye Delta) Variable Variable VFD / VSD Reduced Voltage Starters SpecSizer’s 3-phase Motor Reduced Voltage Options & Respective Torque Limitations • Reduced Voltage Starter • Cost-benefit analysis • Cost of Starter • vs. • Cost of a larger Genset

  27. D.O.L. VSD Autotransformer 80% Autotransformer 65% Autotransformer 50% Wye Delta Reactance 80% Resistance 80% Paralleled (2) gensets Soft Starter Reduced Voltage Starters • Load Scenario: (2) 420 HP motors & (1) 150 kW Resistive load 3000 kVA 880 kVA

  28. Unloaded, Low Inertia Motors • Low Inertia, 3-Phase Motors can be sized with a 15% reduction in Starting kW (SkW) by deselecting the ‘Motor starting under load’ checkbox • Low inertia motors • brake, adjustable, automotive, servo, explosion proof, pump, brushless DC, metric, multispeed, washdown & vector motors • suitable for use with machine tools, conveyors, speed reducers, hoists,...

  29. Unloaded, Low Inertia Motors

  30. Non-linear loads • Create harmonics and voltage distortion • Degrades performance of genset • % of voltage distortion is critical in data center applications • Alternator must be properly sized to limit voltage distortion to acceptable level • Types of non-linear loads: • Uninterruptible Power Supply (UPS) • Battery Charger • Elevator • Variable Frequency Drive Motors – VFD (60 Hz) • Variable Speed Drive Motors – VSD (50 Hz)

  31. Non-linear loads, Filters & Pulse Rectifiers • To offset unfavorable effects of non-linear loads • Upsize alternator vs. recommend higher rated genset • Add filters or increase genset’e pulse rectifier count • 6 pulse to 12-18-or-24 pulse • Reduces harmful effects of non-linear loads • Extends alternator life (avoids distortion overheating) • Maintains or improves power quality • Can allow for a smaller ekW/kVA rated genset • Potential to reduce initial purchase cost

  32. Non-linear loads, Filters & Pulse Rectifiers • Filters, Loads with Filter Option • Some converter type non-linear loads can be fitted with an electronic filter that mitigates the effect of the non-linear load as seen by the alternator. These filters, can be expensive, but if non-linear load is controlling the alternator size, the cost of the filter may be more than offset by the savings from a smaller genset • Pulses, Loads with Pulse Option • Many loads contain AC to DC converters, and these converters may trigger 6, 12, 18 or 24 times per electrical cycle; this is referred to as their pulse count. Lower pulse devices are generally less costly, but also impose a higher non-linear load on the alternator. More non-linear load (lower pulse count) requires a higher alternator capacity

  33. Filters & Pulse Rectifiers • UPS load, 6-Pulse & No Filter • C27 / 3412 • 937.5 kVA • 1052.6 TkVA • UPS load, 6-Pulse with Filter • C27 / 3412 • 875 kVA • 986.8 TkVA

  34. Filters & Pulse Rectifiers • UPS load, 24-Pulse & No Filter • C18 • 687.5 kVA • 866.9 TkVA

  35. 3-Phase AC 6 EER 11 EER 6-20 EER 20 EER 1-Phase AC Energy Efficiency Ratio on Air Conditioning • 6 EER – 1250 kVA C32 • 11 EER – 562 kVA C15 • 20 EER – 437 kVA C15

  36. Volts/Hz Optimization • Voltage regulator optimization (3:1 slope) • low frequency dip, high voltage dip • (e.g. 10%, 35%) • motor loads • footprint • purchase cost • fuel cost • gen-set shipping weight / cost CDVR benefit, all Gensets !

  37. @Site Voltage (Amps) • Loads w/ Amps Adjustment • 3-phase Motors (LRA) • 3-Phase Air Conditioning (LRA) • Single Phase AC • Centrifugal Pump (LRA) • Lighting • Resistive • Office Equipment • Medical • Elevator • Induction Furnace Genset phase voltage = 277V Load voltage = 240V 200V / 277V * 200A = 174A Ratio 240/277 = 0.87 200 Amp load adjusted to 174 Amp

  38. Load Factor (Duty Point) • Customer coal based power plant of 4 x 135 MW capacity • Total running load of power plant = 12 /13 MW. Size of the UAT itself is only 16 MVA. • Competition recommended (7) 3000 KVA engines. SpecSizer recommended (8) engines.

  39. Load Factor (Duty Point) • Customer coal based power plant of 4 x 135 MW capacity • Total running load of power plant = 12 /13 MW. Size of the UAT itself is only 16 MVA. • Competition recommended (7) 3000 KVA engines. SpecSizer recommended (8) engines. 19 total customer loads. Per spec, most loads’ Duty Point can be reduced from 100% to 75%. Reduced sizing from (8) to (6) 3100 kVA gensets.

  40. Help • Help Topics • Menu bar • SME Help File • On Power Net (for CAT Dealers) • SpecSizer landing page • Large 3-Phase Motors • Transformers • Sustained Voltage Dip

  41. Questions? • To order SpecSizer • Cat.com http://www.cat.com/powergeneration/specsizer

  42. Hands-On Training • Optional: Participants create SpecSizer files for Competitive Sizing Options. • Instructor review Sizing Files with Participants • Restrictive Fdip / Vdip • Wizard • 20 Steps, Optimum step • Motor Starting • Reduced Voltage Starters • Motor Starting, Low Inertia Motors • Non-linear loads, Filters & Pulse Rectifiers • Efficiency, Air Conditioners • EER & SEER • Voltage Regulator Optimization • @Site Voltage (Amps) • Load Factor (Duty Point)

  43. Thank You Steven Baker EP Commercial Marketing