330 likes | 523 Views
UK Offshore Wind 2002 17 th April 2002 Gunfleet Sands- A Progress Report Presented by Nigel Crowe Enron Wind. Where are we today ?. Planning Financing Construction Operation. Planning.
E N D
UK Offshore Wind 2002 17th April 2002 Gunfleet Sands- A Progress Report Presented by Nigel Crowe Enron Wind
Where are we today ? • Planning • Financing • Construction • Operation
Planning • Hydrosearch Associates Ltd. have been engaged to project manage the Environmental Impact Assessment process • Draft Environmental Impact Statement (EIS) to be circulated to all consultees for comments around May/June 2002
Environmental Impact Assessment • Geophysical Survey • Environmental Survey • Bird & Marine Mammal Survey • MetOcean Data Acquisition • Coastal Processes Model • Collision Risk Assessment Study • Commercial Fisheries Study • Other Studies in progress
GEOPHYSICAL SURVEY • Completed October 2001 by Titan Environmental Surveys Ltd. • Equipment utilised included Echosounder, Side Scan Sonar, Tow Boomer, Magnetometer • Parameters measured for licence area and cable route:- detailed bathymetry- seabed features & magnetometer contacts- shallow geology- shallow gas- sub-bottom geological profiles- isopachyte (seabed to base sands contours)
Bird & Marine Mammal Survey • Sea based observations and aerial transects • 15 day surveys have been completed to date with monitoring planned after installation of turbines • GPS referenced transects
Metocean Data Acquisition • 2 MetOcean Instruments mounted in seabed frames withsurface Dan buoys in water depths of approx. 12m • Parameters to be measured include:- Current velocity- Tidal height- Directional wave parameters- Turbidity • Instrumentation has been calibrated with Water Samples • Deployed by Thales Geosolutions on 17 January 2002 for 6 month duration • Service visits every 2 months • Data to feed into Coastal Processes Model, Design Layout & Foundation Design
Coastal Processes Model • ABP Research are assessing the baseline coastal processes • Then potential impacts of the development can be quantified over the life of the development • Model will include tides, waves, currents, sediment mobility beyond 1 tidal excursion of the licence area • Utilisation of Remotely Sensed Imagery
Collision Risk Assessment Study • 99% of traffic passes at least 3.7 nm from development area • Collision risk assessed for powered and drifting vessels • Highest risk around NE corner - collision return period of 34,013 years.
Commercial Fisheries Study • In consultation with local fishermen, study has identified: • Ports, Fishing Associations & Individual Fishermen • Fish species • Fishing methods • Importance of Gunfleet Sands • Sensitivities through the year • Spawning grounds
Commercial Fisheries Study • Most important species include: • Sole (main summer + autumn) • Bass (important summer +autumn) • Cod (normally main winter species) • Thornback (caught all year) • Grey Mullet (inshore - summer) • Whiting
Other Studies In Progress • Marine Archaeology • Landscape & Seascape Assessment • Radar Interference Assessment • Terrestrial Ecology along the cable route • Socio Economic Study • Noise Study • Comprehensive Consultation Exercise with Open Days in Clacton • Web site
Financing • Primary objective at present to ensure bankability of Project • NFFO 4 for 30 MW of total 108MW • Watertight PPA agreement for remainder of off take • Reliable Wind Data – • Initial data from Gunfleet Lighthouse • Considered onshore data to supplement this but decided on offshore metmast to avoid any uncertainty • 60m lattice mast founded on a 32m monopile with measurements taken at 3 levels with GPS data collection
Construction • 30 no. EW 3.6MW Turbines – 100m rotor diameter, 70-90m tower giving 108MW • Integrated Foundation Solution • Connection 10Km (7km offshore, 3km Onshore) at 132Kv to Holland–on–Sea
EW 3.x platform = Onshore: EW 3.2s + Offshore: EW 3.6
EW 3.6 offshore Proven elements • concept analogous to more than 880 EW 1.5 since 1996 • separated drive train • variable-speed, variable-pitch • double-fed asynchronous generator • frequency converter • recommended suppliers New elements • experience EW 1.5 offshore at Utgrunden • annual maintenance • over-specified design • crane system • E-container at nacelle • 3.3 kV generator • external heat exchanger • helicopter hoisting platform (optional)
14 m 4.5 m Layout EW 3.x: Separated drive train & crane system
Prototype EW 3.6: 100 m hybrid tower in Spain • Barrax site, close to Madrid • Transport restrictions prototype for inland sites and hub height up to 140 m • 70 m pre-stressed concrete plus 26.5 m steel segment
Operation Efficient Operation is critical to financial viability Reliability, Availability,Maintainability, Serviceability • proven technology (see EW 1.5) • next offshore generation: • i.e. new offshore design • rather than marinised MW-class • larger & proven turbines • lower O&M costs
Enron Wind 3.x: Internal crane system capable of all main components • 40 t slewing crane (activated on-demand) - container - generator - gear box - main shaft - hub - blades • 2 t gantry crane (hoisting inside and outside nacelle)
Gunfleet Sands Progress Summary • Environmental Impact Assessment approaching completion • Comprehensive consultation process underway • Data collection being taken seriously to inhance funding opportunities • Construction programme is underway now with excellent progress being made with the EW3.6 • Operation and maintenance strategy being considered upfront and given necessary importance