An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Helping AMHS Roll-out in Europe(HARE) • Speaker Richard Papior • Organisation EUROCONTROL • Date and venue July 2006, Brussels

  2. Helping AMHS Roll-out in EuropePurpose • Present background information on the HARE Programme • Recent activities • Current status

  3. Helping AMHS Roll-out in EuropeWhere are we today with AMHS? ECIP Pan-European Objectives COM05 2008 2008 What goes here? 2006 2006 Operational AMHS link Frankfurt-Madrid AMC EUR AMHS Manual SPACE Study ECG ICAO SARPS ITUT X.400 CCITT X.400 1984

  4. Helping AMHS Roll-out in EuropeWhat goes here? • SPACE recommendations including Common Facilities • Inter-Regional interoperability • Support for ANSP implementations • Safety, security and performance • Interoperability, testing and approvals

  5. Helping AMHS Roll-out in EuropeSPACE Recommendations SPACE Common Facilities Testing / Training Facility Regional Helpdesk Off-line Mgmt Centre Directory Services Regional XMIB Service Region Boundary COM Centres Underlying Transport Network Security Forum Implementation Group

  6. Helping AMHS Roll-out in EuropeHARE Programme H A R E Helping AMHS Rollout in Europe

  7. Helping AMHS Roll-out in EuropeHARE Programme

  8. HARE Programme Positioning ECIP Pan-European Objectives COM05 2008 2008 HARE 2006 2006 Operational AMHS link Frankfurt-Madrid AMC EUR AMHS Manual SPACE Study ECG ICAO SARPS ITUT X.400 CCITT X.400 1984

  9. HARE ProgrammeMain Objectives • Accelerate AMHS roll-out • Helping ANSPs during their initial implementation and testing phases • Provide support to ICAO • Support the creation of a critical mass of AMHS implementations

  10. HARE ProgrammeActivities Support Functions Common Facilities ICAO CMC/AMC Co-ordination Support to States Directory feasibility Users group Training facilities PENS Co-ordination Regional XMIB Workshops HARE Programme Test Tool Development Security Forum Testing Infrastructure Safety Requirements Approval process Testing Facility Security Requirements Safety & Performance Testing & Approval

  11. HARE ProgrammeWork Packages Programme Management Common Facilities Support Functions Safety & Security Testing & Approval Programme Initiation Co-ord with AMC (8, 14) Support to States AMHS Safety Certification Process Programme Management Co-ordination with PENS (13) Organisation of Workshops AMHS Security Development of Test Tool Regional Testing Facility Impact / Risk Analysis Regional XMIB Service (19) Training Quality Assurance Regional Directory Services (15) IP Testing Infrastructure AMHS Reference Sys. Participation in ICAO activities Maintenance of Ref docs Representation at COM Team Web Site Maintenance Notes: Figures in brackets (n) are SPACE recommendation numbers Publicity & Marketing

  12. HARE ProgrammeMain Deliverables • Common Facilities • Testing and inter-operability facilities • Safety and Security policies • Roll-out support

  13. HARE Programme Where we are today • HARE is at the programme initiation stage • Strategy paper published • COMT35 supported, in principle, the establishment of a HARE Programme • Recommended that Steering/Monitoring be performed by AFSG • Steering Group Terms of Reference Discussed with AFSG

  14. HARE Programme Co-ordination with ICAO COM Team EANPG AFSG HARE Operations Group Steering Committee Planning Group AMHS Management Centre

  15. HARE Programme Steering Committee • The Steering Group will review and give advice on the approval of the: • Programme Management Plan and its subsequent updates; • Programme Risk Plan and its subsequent updates; • Resources required, and the impact of resource limitations; • Programme Strategy document and the other key deliverables of the Programme; • Progress and cost performance; • Start of each programme phase.

  16. HARE Programme Next Steps • HARE proposal will proceed through internal appraisal and stakeholders consultation • PMP and Business Case • Risk management • Steering Group to review PMP, etc.

  17. Helping AMHS Roll-out in Europe End