1 / 10

CEDAR Support Structure and existing PM Head Modifications.

CEDAR Support Structure and existing PM Head Modifications. Peter Sutcliffe University of Liverpool 1 st September – University of Birmingham. Proposed CEDAR Concept Design. N2 Environmental Casing. Cooling and Electronics. Insulation ( all yellow parts). Light Guide. Mirror.

libba
Download Presentation

CEDAR Support Structure and existing PM Head Modifications.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CEDAR Support Structure and existing PM Head Modifications. Peter Sutcliffe University of Liverpool 1st September – University of Birmingham

  2. Proposed CEDAR Concept Design N2 Environmental Casing Cooling and Electronics Insulation (all yellow parts) Light Guide Mirror Existing PMT Head Detector Frame Existing 1251mm (to be shortened) New Detector Support

  3. New Support Cylinder and Modified PMT Head Arrangement New M12 Holes added to Existing PMT Head • Support Cylinder Manufactured from Carbon Steel (Drawing NP53-01-13) • Flanges BS1560 GR 43 C or Similar. • Centre tube manufactured from standard 16” Diameter Schedule 20 seem welded pipe and skimmed to final dimensions. • Existing PMT Support Head (drawing EA8086.596.0) to be Modified with the addition of 12 M12 ‘blind’ holes. (new drawing NP51-01-13) • 1mm Neoprene gasket used as an N2 seal. (Drawing NP51-01-14) • New support cylinder to be Located using 2 dowel screws at 90° and 270 ° 12-M12 Cap Head Screws Neoprene Gasket M12 Dowel Screws at this position New Support Cylinder

  4. Modified PMT Head • 12 - M12 Holes to be added at CERN. • 1st hole to be at TDC • No further processing is required.

  5. New Detector Support • Flanges Manufactured from Carbon Steel BS1560 GR 43C (or similar) • Cylinder 16” NB Schedule 20 carbon steel pipe, inner and outer diameters machined to clean up. • All manufacture including welding to be done at Liverpool. • No coded welders here, so we will have to go to a sub contractor for X Ray NDT or possibly use dye penetrant testing methods. • Surface to be chemi blacked for corrosion resistance.

  6. FE Analysis Flanges • FE Mesh and physical constraints • Finite Element Software used: ANSYS • Material: Carbon Steel • E = 196 GN/m2 • Density = 7854 Kg/m3 • Loads Applied:200Kg in the form of a solid cylinder representing the supported detector. Cylinder Load applied Flange constraints

  7. FE Results This figure shows the maximum stress of 1.2MPa which is very low. Maximum Yield stress for carbon steel is around 220MPa This figure shows the maximum deflection in Y of 0.055mm, due to gravity with a 100Kg Load representing the detector.

  8. Details of Concept

  9. Installation • Head assembly will be in place at time of beam line installation. • Frame and Environmental casing is split. Each half will be pre-assembled and tested. • Cooling will be fixed in place and electronics, pmt’s and light guide can be replaced by sliding a complete assembly out and repairing and replacing faulty components. • Tapes and cooling tubes to be fed out at the bottom, through the environmental casing.

  10. Current Concept...comments?

More Related