Metropolitan Transport Forum Clement Michel – Chief Operating Officer. 4 May 2011. Summary. Network The Melbourne context Capacity Achievements New Trams. Our Network. The Melbourne Context. 2010 public transport patronage. Trains 226.6 million Trams 176.5 million

libba
Download Presentation

Metropolitan Transport Forum Clement Michel – Chief Operating Officer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Metropolitan Transport ForumClement Michel – Chief Operating Officer 4 May 2011

  2. Summary • Network • The Melbourne context • Capacity • Achievements • New Trams

  3. Our Network

  4. The Melbourne Context

  5. 2010 public transport patronage • Trains 226.6 million • Trams 176.5 million • Buses 101.5 million Despite only operating in the inner suburbs, trams carry 35% of all Public Transport travellers.

  6. Not good enough …

  7. Ageing infrastructure …

  8. Capacity - Overloading 2007:

  9. Capacity - Overloading 2010:

  10. Capacity - Overloading 2020:

  11. Decline in average speed: timetable comparison 1950 to 2010 40% increase in travel time on route 96 – in its northern section only!

  12. Insufficient tram priorityinternational comparison of time spent a traffic signals Source: Keolis study

  13. Tram PriorityWhy? • Drivers for tram priority: • Journey Time Savings • Regularity / Punctuality • Total Economic Benefit

  14. Our Achievements

  15. Performance Results Since the inception of the KDR franchise, Yarra Trams has exceeded the service delivery target of 98% and the punctuality performance target of 77%, for every single month. This has been achieved through a complete reorganisation of the maintenance and service delivery. However, we think the people of Melbourne deserve a more reliable service.

  16. Think like a passenger – One year onSafety Safety Campaigns AO Response Unit

  17. Think like a passenger – One year onPassenger Information New Maps

  18. Infrastructure Track renewals and overhead works are inconvenient, but indispensable. Physical assets can only be economically maintained for up to to 30 years, After which capital replacement is the most cost effective and safest option.

  19. St Kilda Road Re-design

  20. Our vision • Safe & reliable • Fully accessible • Sustainable • Fully segregated • Full priority at signals • Intermodal • Intuitive & informative • Comfortable & clean From a “tram” to a “light rail”

  21. Priority = Capacity Route 96 • Analysis • VicRoads trialling tram priority on Nicholson Street • VicRoads modelling tram priority on Bourke Street

  22. Priority ModellingDynamic Priority for Trams • A dynamic tram priority system in simulation that calls tram phases on-demand and utilises: • Green time extension • Minimum phases Example: Swanston St