Risk Analysis

Risk Analysis. Based on E.M. Bennatan, On Time, Within Budget . John Wiley & Sons, 1995. Risk Analysis. A project management technique in which potential problems are identified, their probability and severity of impact estimated, and plans devised to address them should they occur.

libitha
Download Presentation

Risk Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Analysis Based on E.M. Bennatan, On Time, Within Budget. John Wiley & Sons, 1995.

  2. Risk Analysis • A project management technique in which potential problems are identified, their probability and severity of impact estimated, and plans devised to address them should they occur. • A problem that has been anticipated and planned for is far easier to solve than one that occurs unexpectedly.

  3. Risk Analysis Procedure • Anticipate problems. • Estimate the probability that the problem will occur. • Estimate the impact of the problem on the project. • Attribute a measure of severity to the problem. • Identify contingency plans for severe-impact problems.

  4. Anticipate Problems • Common SD problems: • Inadequate definition of requirements • Frequent changes (creeping requirements) • Poor estimates • Dependence on external sources • Difficulties in concluding the project • Staff turnover • Inadequate tracking and supervision

  5. Anticipate Problems …. • Review project technical and administrative plans: • Project plan (resources, schedule, task dependencies) • Requirements specification (difficulty in satisfying performance objectives) • Design specification (implementation decisions that may create problems)

  6. Anticipate Problems …. • Compile a list of potential problems, briefly describing each problem and its effect on the project, e.g., • Staff turnover: Given the tight schedule and dependence on staff expertise, the loss of Developer A or any long-term loss of other personnel will cause the project to slip significantly.

  7. Estimate Probability and Impact • Estimate the probability that the problem will occur, assigning an expectation number between 1 (low) and 10 (high) to each problem. • Estimate the severity of the problem’s impact, assigning a number between 1 (low impact) and 10 (high impact) to each problem. • Multiply the expectation number by the impact number to produce the measure of severity for each problem.

  8. Estimate Probability and Impact….

  9. Identify Contingency Plans • Decide the “cut-off point” in severity ratings (e.g., 15 or 20). • Devise a contingency plan for each high-severity problem. • Assign a “tracker” to track the problem and to alert the project manager when the contingency plan needs to be implemented.

  10. Identify Contingency Plans….

  11. When to Perform Risk Analysis • As part of the Project Plan • As planning for each major development stage: • Requirements Analysis • Design Specification • Implementation • Whenever a “significant event” occurs • Just as planning is an iterative process, so is risk analysis!

  12. Risk Analysis Costs and Benefits • RA is a kind of insurance. • Costs: • Time & effort to perform analysis • Cost of any fall-backs implemented • Benefits: • Minimized cost of problem resolution • Greater probability of successful project completion • Greater “peace of mind”