An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design of UAV Systems c 2002 LM Corporation Sorties rates • Lesson objective - to discuss • Sortie rate analysis • including … • - Mission planning and preparation • - Aircraft preparation and maintenance • - Preflight / execution / debrief • - Crew considerations Expectations - You will understand the basic elements of a sortie and be able to make sortie rate estimates 7-1

  2. Design of UAV Systems c 2002 LM Corporation Sorties rates Definitions • Sortie (Webster’s New Collegiate Dictionary) • – One mission by a single aircraft • Sortie rate (The RAND Corporation*) • – The number of missions one aircraft can fly in one day including time in the air and on the ground or • SR = 24hours/[FT + GT] • where • FT = flight time  2target distance/block speed • GT = ground time = TAT + MT • and • TAT = turn around time  3 hours • MT = maintenance time * http://www.rand.org/publications/MR/MR1028/ 7-2

  3. Design of UAV Systems c 2002 LM Corporation Sorties rates Sortie elements • Mission planning and preparation time • Military - time required to plan and communicate an overall air operation and translate it into individual aircraft flight plans that everybody understands • - Typically planned for days or weeks and conducted daily • Civilian - time required to prepare and file a flight plan and receive a clearance • - Manned aircraft can plan a simple flight and get an IFR clearance in a minimum of an hour • - VFR flight preparations could be done in minutes • - Unmanned aircraft may have to negotiate approvals far in advance (varies by country and region) 7-3

  4. Design of UAV Systems c 2002 LM Corporation Sorties rates Sortie elements • Aircraft maintenance and preparation time • All aircraft require servicing (fuel, oil, etc.), loading and scheduled maintenance (oil and filter change, etc) • - Servicing can often be done during mission planning • - Loading time varies widely • - Military aircraft require special preparations to include weapons assembly and check out • - Minimum “turn time” is typically 15-30 minutes • Unscheduled maintenance also occurs and often must be done before flights can be resumed • - Flight critical items must be fixed, others can be “placarded’ and fixed later • - Many operators do phase maintenance (periodic replacement) to minimize schedule disruptions 7-4

  5. Design of UAV Systems c 2002 LM Corporation Sorties rates Sortie elements • Pre-flight, loading and system checks • All aircraft require external pre-flight ground checks • - From simple “walk-around” to thorough inspection • - Typically takes 5 to 10 minutes • All manned aircraft require loading • - Includes pilot, crew and passengers • - Time varies from 1 minute (pilot only) to 30 minutes • Non-perishable cargo can be loaded during aircraft maintenance and preparation • All aircraft require pre-start system checks • - Unmanned aircraft require the most time • - Minutes to hours • - Manned aircraft time varies from 1 to 15 minutes 7-5

  6. Design of UAV Systems • Flying the mission…. • Start/check the engine(s) - 1 to 5 minutes • Get ground clearances - seconds to minutes • Taxi to active runway - 2 to 15 minutes • Perform pre-takeoff checks - 0 to 5 minutes • Takeoff - 1 minute • Climb - Seconds to 10s of minutes • Cruise/ingress - function of mission distance & speed • Pre-penetration refuel - 15 to 30 minutes • Loiter/surveil - minutes to hours • Engage in combat - 2 to 5 minutes • Deliver cargo - minutes (drop) to hours (land) • Post-penetration refuel - 15 to 30 minutes Cruise/egress - function of mission distance & speed • Get clearances and land - 1 to 10s of minutes • Post mission checks (military aircraft) - 0 to 5 minutes • Taxi and shut down - 2 to 15 minutes or or c 2002 LM Corporation Sorties rates Sortie elements “Useful Work” 7-6

  7. Design of UAV Systems c 2002 LM Corporation Sorties rates Sortie elements • Debrief - the time required to report and/or document the results of a mission • Civilian debriefs focus on record keeping and incident and maintenance reports • - 2 to 30 minutes • Military debriefs are extensive • - Everything included in civil debriefs plus … • - Mission assessments • - Intelligence information • - Procedures • - Etc. • - Can take hours 7-7

  8. Design of UAV Systems c 2002 LM Corporation Sorties rates Crew considerations • Civilian and peacetime military ground crews typically operate 8 hours per day, 5 days per week. • Civilian air crews operate on flight hour basis • Air transport crews are typically limited to a 14 hour duty day or 10 flight hours for reasons of safety • - Duty day includes air and ground time • On deployments, military air and ground crews operate 12 hours per day, 7 days per week • - Crew:aircraft ratio usually > 1, e.g. 1.25 for fighters • UAV crews (ground and flight) operate on 8 or 12 hour duty day basis Aircraft sortie rates typically are limited by crew considerations - most aircraft can fly more hours than their crews can work - including UAVs 7-8

  9. Design of UAV Systems c 2002 LM Corporation Sorties rates Figures of merit • Civilian figures of merit (FOM) are typically expressed in terms of numbers of revenue flights per day • Military figures of merit are typically expressed in terms of numbers of sorties generated per day per aircraft (strike missions) or sorties for required coverage (surveillance missions) under 2 conditions: • Surge - what can be done in an “all-out” effort for short periods of time • Sustained - what can be done in continuous effort over long periods of time • Cost is an important part of military FOMs also 7-9

  10. Design of UAV Systems Mission Control Ground crew Mission Planning and Preparation - min 180 Intelligence update 60 Flight plan 60 Clearances 60 Aircraft Preparation and Maintenance (parallel activity) - min 180 Scheduled maintenance 120 Fuel/oil and roll out 30 Ground checks 30 Above completed in advance Preflight - min 6 6 Load mission 2 2 Mission verification 2 2 Walk around inspection and system checks 2 2 Mission execution - min 20 241 Start engine 1 1 Clearances 1 1 Taxi 5 5 End of runway/pre-take off checks 3 3 Takeoff 1 Climb 10 Cruise out 10 Loiter/surveillance 180 Cruise back 10 Hold for landing 5 Land 5 3 3 End of runway inspection and safing Taxi 5 5 Shut down 2 2 Quick turn - min 15 15 “Thru flight” inspection and refuel 15 Reports 15 Sortie requirement (hr) 0.68 4.37 c 2002 LM Corporation Sorties rates Sortie rate example Above completed in advance SR = 24/7.37 = 3.3 FT = 3.6 hrs 7-10

  11. Design of UAV Systems TAT  3 hrs c 2002 LM Corporation Sorties rates RAND data • Therefore: • SR  24hours/[1.68FT + 6.4] SR (previous example) = 1.9 * http://www.rand.org/publications/MR/MR1028/ 7-11

  12. Design of UAV Systems c 2002 LM Corporation Sorties rates Intermission 7-13