OVER-THE-RHINE. PLAYGROUND SCHEDULED TO BE COMPLETE OCTOBER 2011. SUMMER EVENT HIGHLIGHTS. Programming seven nights a week: Monday: Neighborhood Market Tuesday: Dancing Under the Stars Wednesday: Jazz Thursday: Bluegrass Friday Flow (R&B/Soul) Saturday:“Date Night” Movies
E N D
SUMMER EVENT HIGHLIGHTS • Programming seven nights a week: • Monday: Neighborhood Market • Tuesday: Dancing Under the Stars • Wednesday: Jazz • Thursday: Bluegrass • Friday Flow (R&B/Soul) • Saturday:“Date Night” Movies • Sunday: Performing Arts • Programming during the day on weekends: • Yoga and workout classes • “Curiosity Saturdays” for kids (with Public Library) • Dog Park activities • Possible visual art programming with Arts Wave
OTHER EVENT HIGHLIGHTS • City Flea (monthly May-September) • Crown Jewels of Jazz series (August) • Tender Mercies’ “Taste of OTR” (August) • 28th Over-the-Rhine Community Festival (August) • Cincinnati AVP Volleyball Tournament (Labor Day weekend) • Cincinnati Celtic Festival (September) • MidPoint Music Festival (September)
RESIDENTIAL SALES Gateway I,II,III & IV: 186 of the 186 condos (100%) are sold
RESIDENTIAL LEASING Gateway I,II,III & IV: 68 of the 68 apartments (100%) are leased
COMMERCIAL LEASING 89% of 105,329 SF commercial space leased. The Lackman Bakersfield 1215 Coffee Lab & Wine Bar Senate A Tavola Sloane Boutique
COMMERCIAL LEASING 89% of 105,329 SF commercial space leased. The Anchor Kaze Quán Hapa Quán Hapa The Anchor Kaze
COMMERCIAL LEASING ZULA, 1400 RACE STREET
COMMERCIAL LEASING • Coming Soon: • Holtman’s Donuts, 1332 Vine Street • The Eagle, 1338-42 Vine Street
3CDC OTR DEVELOPMENT Future/ Land Bank Complete/ Under Construction Mercer Commons/ Gateway V
MERCER COMMONS • Phase I • 3,900 SF Commercial/Office • 28 Condos • 340-space Parking Garage • CDF committed $2.56 million of state and federal NMTC • Phase II • 67 Apartments (30 affordable) • 10,600 SF commercial space • OHFA awarded project low income housing tax credits and also received historic tax credits from State of Ohio • Phase III • 59 Apartments • 3,100 SF commercial space
BAKERY LOFTS 1421-1423 RACE • Developer: Urbanis LLC (Schickel Design) • Project Cost: $2.45 million • Project Size: 10,402 Gross SF • Project Summary: • 9 for-sale units • Completed: • 7 condos under contract
BAKERY LOFTS 1421-1423 RACE
WESTFALEN LOFTS II 1426-1438 RACE • Developer: • 1438 Race LLC (Northpointe Group and John Hueber Homes - residential) • 3CDC - commercial • Project Cost: $8.6 million • Project Size: 32,798 Gross SF • Project Summary: • 33 for-sale units • 4,000 SF of commercial space • Estimated Completion Date: • September 2013
WESTFALEN LOFTS II 1426-1438 RACE
HUMMEL BUILDING 1401 ELM • Developer: Grandin Properties • Project Cost: $1.7 million • Project Size: 7,290 Gross SF • Project Summary: • 4 for-sale units • 1,880 SF commercial space • Estimated Completion Date: • May 2013
HUMMEL BUILDING 1401 ELM
NICOLAY 1410 REPUBLIC • Developer: • Northpointe Group – residential • 3CDC - commercial • Project Cost: $2.34 million • Project Size: 13,293 Gross SF • Project Summary: • 10 for-sale units • 1,035 SF of commercial space • Estimated Completion Date: • June 2013
NICOLAY 1410 REPUBLIC
REPUBLIC STREET LOFTS 1406 & 1412 REPUBLIC • Developer: Northpointe Group • Project Cost: $1.99 million • Project Size: 8,230 Gross SF • Project Summary: • 9 for-sale units • Estimated Completion Date: • June 2013
REPUBLIC STREET LOFTS 1406 & 1412 REPUBLIC
B-SIDE APARTMENTS 1437 REPUBLIC & 13 W 15th • Developer: Mottainai Developers, LLC and 3CDC • Project cost: $4.5 million • Project Size: 22,000 gross SF • Project Summary: • 14 rental units • Estimated Completion Date: • July 2013
TEA COMPANY TOWNHOMES 18-20 W 13th & 1307 REPUBLIC • Developer: • City Lofts- residential • 3CDC - commercial • Project cost: $2.99 million • Project Size: 12,600 Gross SF • Project Summary: • 9 for sale units • 1,065 SF of commercial space • Estimated Completion Date: • December 2013
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction Mercer Commons/ OTR Phase V
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction
MUSIC HALL RENOVATION • A development management agreement between 3CDC and MHRC has been drafted. • MHRC board approved the agreement on 4/8/13. • City Council approved a revised lease agreement on the building between the City and MHRC. • 3CDC board is expected to approve the development management agreement this Thursday.