1 / 21

04/10/2013 New injection system - concept

LIU-SPS 50 ns Pb ion injection system review. 04/10/2013 New injection system - concept

lilli
Download Presentation

04/10/2013 New injection system - concept

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LIU-SPS 50 ns Pb ion injection system review 04/10/2013 New injection system - concept B.Goddard, O.Aberle, B.Balhan, J.Borburgh, E.Carlier, K.Cornelis, L.Ducimetière, L.K.Jensen, T.Kramer, D.Manglunki, A.Mereghetti, V.Mertens, D.Nisbet, B.Salvant, L.Sermeus, J.Uythoven, F.Velotti

  2. Motivation • Strong request from LIU-ION to study improving injection rise time, to 50 ns • For Pb ions only • Keeping existing injection energy for ions (rigidity of 60 Tm) • Not impacting negatively on injection for p+ or other ions • Flat top to allow injection of 4 bunches at 50 ns spacing (i.e. ~160 ns) • “Acceptable” emittance growth (can assume damper) – so 2-98% rise-time to respect in B field

  3. SPS injection • LHC p+ injection (26 GeV/c) uses all kickers, at 52.0 kV (225 ns) • CNGS p+ injection (14 GeV/c) uses MKPA/C, at 49.2 kV (< 1000 ns) • Pb82+ ion injection (17 GeV/c per charge) • used MKPA/C, at 52 kV for Q26 (200 ns) • uses all kickers at ~40 kV for Q20 (225 ns) • TBSJ is injection dump (use MDSH119 to improve centering) MSI TBSJ MKP MKPAC

  4. Present ion injection • Present “ion” kickers type MKP-S • Were designed to reach 115 ns (with PFLs, never installed…) • Measured at <150 ns (2-98%) with present PFNs • Need also to use “LHC p+” MKP-L kickers for Q20 • Imposes 225 ns rise-time • Look at split tunes, or back to Q26 for ions, to reach 150 ns with present layout • Addition of PFLs to the present MKP-S magnets is possible (already foreseen in BA layout) • Will give 125 ns for sure, maybe 100 ns • No additional tunnel equipment • Kick strength then only sufficient for ≤13 GeV/c depending on optics

  5. MKP usage for ions(from discussion with Django) • 2011 • Q26 optics, use first three tanks only (MKP-S) • Pushed voltage to 52 kV and tweaked trajectories and orbits to make a 17 GeV/c be injected in a system which was designed for 13 GeV/c • Rise time used was 200 ns • The MKP-S measured rise time 2 % - 98 % is 148 ns. See later slide from 2000. • 2012 • Q20 optics – less help from quad in front of MKP • Used the fourth tank (MKP-L) as well, which was not modified 13 years ago • Rise time used, as for LHC protons: 225 ns, due to the slower MKP-L

  6. Concepts studied • Rebuild entire injection kicker system • Add thin pulsed septum and rebuild entire injection kicker system • Add separate new ion kicker and new thin pulsed septum, for ion injection only • Add PFLs to existing kickers, with new thin pulsed septum • Do nothing to existing kickers, either with or without new thin pulsed septum

  7. Option (i) • Rebuild existing magnets completely • Higher impedance (16.6 -> 25 Ohm) • Much shorter magnets (0.6-0.7 -> 0.28 m) • Many more individual magnets (12 -> 48) • Much longer magnetic length needed (8 -> 12 m) • No aperture for dumping p+ beam • Extremely expensive even if possible • Discarded: does not look feasible • Many integration issues • Many technical issues • No aperture for dumped beam • Huge cost and investment even if solutions could be found

  8. Option (ii) • Add thin in-vacuum septum and rebuild existing MKP, with rearrangement of layout • Only need to rebuild a subset of the MKP • Same issues with very short 28 cm magnets • More issues with magnet aperture (vertical gap not enough) • No solution found to dump p+ beam cleanly • Discarded: does not look feasible • Some integration issues • Some technical issues • Aperture limits in vertical plane • No way to dump p+ beam • Large cost and investment

  9. Option iii: the minimalist • Don’t change anything and we can probably go down to 150 ns rise time (2 – 98 %) • If we want to have more margin / less tweaked orbits and trajectories one can install the MSI-V, but might not be strictly necessary • In this case the installation of an ion injection dump might be nice to keep it ‘clean’ • Without MSI-V Q20 clearly makes things more difficult – try split tunes? • More work on the MKP-S front cells in the PFN might make it possible to go down to 125 ns rise time • Would be available for tests after LS1

  10. Option iv: the intermediate • To go below 125 ns kicker rise time, aiming for 100 ns kicker rise time (2 – 98 %): install a PFL in parallel to the present PFNs on the MKP-S system. • No kicker magnets to be installed in the tunnel • This reduces the maximum voltage on the PFL to 40 kV and the installation of the MSI-V becomes obligatory • With MSI-V no problems with Q20 optics • The switching between PFN and PFL requires development and lab tests • Injection dump for ions would be nice, to control losses

  11. Option v: the full monty • Install the new MKP-I magnets & MSI-V • If all works well this would allow for a rise time of 75 ns (2 – 98 %). But not easy and a lot of work • Adds impedance to the machine – beam dynamics, and risk of kicker heating • Not sure that impedance shielding is possible with this rise time • New kickers and cables needed in highly radioactive zone downstream of TIDVG • Ion injection dump again needed, to stay clean

  12. Option v Layout in SPS MSI-V MKP-I

  13. Option v 17 GeV/c/u Pb82+ ionswithout injection bump

  14. Option v 14 GeV p+ (as done today)

  15. Option v • Could conceivably have a dump block in a new location just upstream QD.121 • Could misalign MBB.12070/90 by -10 mm in H ~1.4 m available

  16. Option v

  17. Considerations • Performance reach is one important aspect • Others are • Required effort level (resources, cost) vs. benefit • Radiation doses for installation, operation and maintenance • Technical risk • Compatibility with injection of p+ beams (aperture) • Compatibility with HL-LHC beams (impedance)

  18. LSS1 is a very active area… MSI-V MKP-I TBS-I TIDVG

  19. Summary of performance/costs

  20. fin

More Related