11 T Dipole Project Cold mass integration status & plan

F. Savary / TE-MSC-LMF. 11 T Dipole Project Cold mass integration status & plan. Outline. Cold mass assembly Short term plan Status Tooling Short term plan Status Staffing. Cold Mass Assembly. Short term plan. “Short term” means objectives for end 2013

lily
Download Presentation

11 T Dipole Project Cold mass integration status & plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. F. Savary / TE-MSC-LMF 11 T Dipole Project Cold mass integration status & plan

  2. Outline • Cold mass assembly • Short term plan • Status • Tooling • Short term plan • Status • Staffing Cold mass integration status and plans

  3. Cold Mass Assembly Cold mass integration status and plans

  4. Short term plan • “Short term” means objectives for end 2013 • Develop a functional specification • 2 months for a draft • Develop a conceptual design • Byend 2013 • 3D models, a few 2D sections showing the main size, the main sub-assemblies (Assembly Breakdown Structure), and the maininterfaces • Develop a detailed plan for the construction and test of (a) prototype(s), aiming at final technical specification for IT for series production • Schedule • Cost • Staffing • Tooling • Components Cold mass integration status and plans

  5. Functional specification • Description of the 11 T dipole magnet • Description of the functional requirements • Field strength • Field quality • … • Definition of the physical/functional interfaces • Space contraints • Interface with cryogenics (heat exchanger tube, cooling requirements), vacuum (beam pipe, beam screen?, …), physics (correctors, aperture, meaning e.g. straightness, …), power supply, protection, cryostat, collimator, neighbor magnet, … Cold mass integration status and plans

  6. Status • So far, nothing done … at least not significant enough to be mentioned Cold mass integration status and plans

  7. After short term plan • We need a conceptual design review to initiate the final design and engineering phase • Needs to cover, and be consistent with • First results of short model program • Integration design, taking into account all interfaces • In March 2014? Cold mass integration status and plans

  8. Tooling Cold mass integration status and plans

  9. Short term plan • Winding machine • End January 2014 to start winding trials on racetrack, then cos(θ) coil with bare Cu-cable, and then first practice coil with insulated Cu-cable to react and impregnate (Mikko) • Short welding press • Next week, welding of the first mechanical mock-up • Reaction furnace • Contract launched (company GERO) • Delivery scheduledend March 2014 • Impregnation chamber • IT-3898/TE launched • Deadline for bidding on 21-06-2013 • Design winding mandrel, molds for binder curing, and for coil heat treatment Cold mass integration status and plans

  10. Status – Welding press • Company EWM • to sent report on welding tests carried out at their premises • to come @ CERN next week to weld the mock-up, with equipment Cold mass integration status and plans

  11. Status winding machine • Design work on-going (EN-MME) • Integrate 2nd spool holder • Make it shorter (with possible return to longer configuration) • Revamp control system • Company CERATEC (contract needs to be placed, offer received last week) Cold mass integration status and plans

  12. Staffing Cold mass integration status and plans

  13. Staffing plan • Currently • CERN staff, 2 CpC, 1 fellow + 1CpE part time soon • FSU, (very) limited contribution • EN-MME design office • Soon • Service contracts (FC next week) • Alstom as from September 2013 • Babcock Noell as from January 2014 • ASG Superconductor as from May 2015 • Later (after LS1, July/August 2014) • LMF staff, and FSU Cold mass integration status and plans

  14. Service contracts Cold mass integration status and plans