1 / 22

11 T Dipole Project HL-LHC WP-11

11 T Dipole Project HL-LHC WP-11. Kick-off meeting M. Karppinen TE-MSC. Outline. DS-upgrade project Project goals Status and plans Milestones Organization Communication. DS Upgrade.

emilia
Download Presentation

11 T Dipole Project HL-LHC WP-11

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 11 T Dipole ProjectHL-LHC WP-11 Kick-off meeting M. Karppinen TE-MSC

  2. Outline • DS-upgrade project • Project goals • Status and plans • Milestones • Organization • Communication M. Karppinen 6 Nov -14

  3. DS Upgrade • Create space for additional collimators by replacing 8.33 T MB with 11 T Nb3Sn dipoles compatible with LHC lattice and main systems. • 119 Tm @ 11.85 kA (in series with MB) • Joint development program between CERN and FNAL underway since Oct-2010. • LS2 : IR-2 • 2/4 MB => 4/8 x 5.5 m CM + spares • LS3 : IR-1,5 and Point-3,7 • 4 x 4 MB => 32 x 5.5 m CM + spares MB.B8R/L MB.B11R/L 15,66 m (IC to IC plane) 11 T Nb3Sn 3 m Collim 5.5 m Nb3Sn 5.5 m Nb3Sn 5.5 m Nb3Sn 3 m Collim. 5.5 m Nb3Sn M. Karppinen 6 Nov -14

  4. 11 T Dipole Project Goals • Demonstrate the feasibility of Nb3Sn technology for the DS collimation upgrade with an accelerator quality 5.5-m-long twin-aperture 11 T prototype dipole by 2015 • Design and construct 15.6-m-long cryo-assembly comprising the 11 T dipole and collimator compatible with LHC lattice and main systems • Prepare for the series production of 11 T collimator cryo-assemblies according to the LHC upgrade schedule • Ultimately deliver 2 fully tested cryo-assembly units for IR2(* during LS2 and 16 units for the LS3 (IR1,5 and Point-3,7) *)Present understanding prioritizing the ion run over Point-7 and protons. M. Karppinen 6 Nov -14

  5. Project Status and Plans • Emphasis currently on the short model magnet development to master the Nb3Sn technology and validate the magnet design • Two short 1-in-1 magnets tested at FNAL. First CERN model magnet test expected in March -14 • Work on scale-up to 5.5 m magnets has commenced and first long magnet test expected in 2015 • Cold mass and cryo-assembly integration studies are in progress • Machine integration studies in progress (beam dynamics, protection, beam losses) or first pre-studies made (powering, vacuum, cryogenics,..) (* *)Cold collimator feasibility WG chaired by V. Parma M. Karppinen 6 Nov -14

  6. Project Milestones (1/3) • Short Models: • FNAL (1 m) : • Mirror test Nov-13 • 2 x 1-in-1 model test Feb-14 and Apr-14 • 2-in-1 model test Jul-14 • CERN (2 m): • 2 x 1-in-1model test Mar-14 and May-14 • 2-in-1 model test Aug-14 • 1-in-1 model test Mar-15 and May-15 • 2-in-1 model test Jul-15 M. Karppinen 6 Nov -14

  7. Project Milestones (2/3) • Long 5.5 m Prototype Magnet: • Coil fabrication: • Cu-practice coil Jul-14 • Low-performance Nb3Sn coil Nov-14 • Nb3Sn coil #1 Mar-15 • Single coil test (mirror?) Jun-15 • 4 Nb3Sn coils (RRP & PIT) Oct-15 • Cold mass assembly: • Collared coil #1 Dec-15 • Collared coil #2 Apr-16 • 2-in-1 Cold mass May-16 • Cryostat integration and cold test in SM-18 Aug-16 M. Karppinen 6 Nov -14

  8. Project Milestones (3/3) • 11 T dipole cryo-assemblies for IR2 (LS2): • 11 T Dipole #1: • 2 x collared coil Jun-17 • Coldmass assembly and cold test in SM18 Oct-17 • 11 T Dipole #2: • 2 x collared coil Aug-17 • Coldmass assembly and cold test in SM18 Dec-17 • 11 T Dipole Cryo-assembly #1 Feb-18 • Cold test in SM-18 Apr-18 • 11 T Dipole #3: • 2 x collared coil Nov-17 • Coldmass assembly and cold test in SM18 Mar-18 • 11 T Dipole #4: • 2 x collared coil Aug-17 • Coldmass assembly and cold test in SM18 May-18 • 11 T Dipole Cryo-assembly #2 Jul-18 • Cold test in SM-18 Aug-18 M. Karppinen 6 Nov -14

  9. HL-LHC WP-11: 11 T 2-in-1 Dipole Organization WPL M. Karppinen M. Karppinen 6 Nov -14

  10. Task 1: Magnet Design, Development, and Analysis TL M. Karppinen & A. Zlobin (FNAL) M. Karppinen 6 Nov -14

  11. Task 1 Goals & Deliverables • Magnetic and mechanical design meeting the requirements of the LHC lattice • Development and supply of Nb3Sn conductor and cable • Development and qualification of magnet protection system • Analysis of magnet tests M. Karppinen 6 Nov -14

  12. Task 2: Short Model Magnets TL D. Smekens & A. Nobrega (FNAL) M. Karppinen 6 Nov -14

  13. Task 2 Goals & Deliverables • Demonstrate the accelerator quality magnet performance with short 2-in-1 model magnets • Material and insulation development and qualification • Fabrication tooling development and validation • Fabrication process development and validation • Construction and testing of short (1..2 m) model magnets (see milestones) • Technology transfer for 5.5 m coldmass development M. Karppinen 6 Nov -14

  14. Task 3: 5.5 m Coldmass TL F. Savary M. Karppinen 6 Nov -14

  15. Task 3 Goals & Deliverables • Demonstrate the accelerator quality magnet performance with 5.5 m prototype magnet • Fabrication tooling development and validation • Fabrication process development and validation • Coldmass design and procurement of components • Construction of 5.5 m coldmass and test cryostat (see milestones) • Preparation and technology transfer for 5.5 m coldmass series production according to LHC upgrade schedule M. Karppinen 6 Nov -14

  16. Task 4: 11 T Dipole Cryo-assembly (15.6 m) & Technical coordination and integration TL V. Parma M. Karppinen 6 Nov -14

  17. Task 4 Goals & Deliverables • Design and construction of 15.6 m cryo-assembly meeting the requirements of the installation in the LHC • Interface definition: • Collimator • Powering • Cooling • Vacuum • Instrumentation • Coldmass integration including design, procurement of components and tooling, and assembly • Cryostat design and procurement • Delivery of fully tested cryo-assemblies according LHC upgrade schedule M. Karppinen 6 Nov -14

  18. Task 5: Machine Integration TL M. Karppinen & V. Parma M. Karppinen 6 Nov -14

  19. Task 5 Goals & Deliverables • Definition of the powering scheme for the 11 T Dipole and integration in the LHC powering systems • Definition of the 11 T Dipole magnet protection scheme and integration in the LHC protection systems • Definition of ELQA requirements for the 11 T Dipole in view of integration and commissioning in LHC machine • Definition of magnet alignment system • Definition of transport and handling requirements of 11 T Dipole sub-assemblies and completed cryo-assemblies. M. Karppinen 6 Nov -14

  20. Communication & Documentation • General project meeting: • Topical • Short status from Tasks • 1-2 / month • Task meetings: • According to needs • Documentation: • Indico for meetings: • Projects/HL-LHC/WP-11 • DFS-workspace for working docs: • \\CERN\dfs\Projects\HL-LHC_WP-11_11T_Dipole • smb://cerndata74/P-HL-LHC_$ (Mac) • EDMS for reference docs: • HL-LHC/WP Workspace/11 T Dipole M. Karppinen 6 Nov -14

  21. Equipment codes • MBH - Magnet Bending High Field • MBHSP - Magnet Models or Prototypes Single aperture • MBHDP - Magnet Models or Prototypes Double aperture • LMBH - Cold Mass for the High Field Dipole • QBB - Cryostat for the High Field Dipole • LBH - Cryo-Magnet assembly for High Field Dipole M. Karppinen 6 Nov -14

  22. Topics for next meetings.. • Beam dynamics studies update (B. Holzer) • Short model magnet status (D. Smekens) • Cryo-assembly integration challenges (D. Duarte Ramos, T Sahner) • Coldmass assembly status and options (F. Savary) • Powering options (H. Thiessen) • Magnet protection studies (S. Izquierdo-Bermudez) • …..? M. Karppinen 6 Nov -14