Weekly Status UpdateData Conversion AP-MY Data conversion 9/23/2011
Agenda • Executive Summary • Status Update Overview – AP-MY
Executive Summary • Overall Summary • Previous Week Highlights • Mapping and cleansing continued • Next key activities • Continue Data Cleansing • Catch up on all late functional and technical mappings • Complete mapping activities due this week • Watch Points • Missing functional mapping prevents build and unit test completion. This will impact our Mock 1 start date • Missing configin DEV-600
AP-MY Preparation PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete
AP-MY Design / Fit Gap PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete
AP-MYData Conversion FIT / GAP Dashboard • Functional Mapping Completed 52/82 = 63% Overdue 20/72 = 28% • Data Construct Completed 32/81 = 40% Overdue 33/63 = 52% • Technical Design Completed 36/79 = 46% Overdue 33/69 = 48% • Total Completed = 50%
AP-MY Build PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete
AP-MYData Conversion BUILD Dashboard • Missing functional mapping prevents build and unit test completion. This will impact our Mock 1 start date and is reflected in the overdue CranSoft upload and DC rules overdue.
MY Deploy PhaseStatus Update Overview Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete
AP-MY Data Conversion • Detailed Status Update Behind schedule or at risk; able to recover Not started On schedule Behind schedule and at risk Complete