LHC Injection System

LHC Injection System. LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger. What do we need to inject? Interfaces Testing. What do we need to inject? (1). MKI. Transfer line. Q5. Q4. D2. TDI. MSI. TCLIA + TCLIB. IP2. TCDD.

linore
Download Presentation

LHC Injection System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Injection System LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger • What do we need to inject? • Interfaces • Testing Nov 08, 2007

  2. What do we need to inject? (1) MKI Transfer line Q5 Q4 D2 TDI MSI TCLIA + TCLIB IP2 TCDD kicks in the vertical plane • Last 200 m of transfer line • Injection Septum MSI (5 magnets, MSIB and MSIA, one power converter) • Injection kicker MKI (4 magnets, 54 kV) • Injection stopper TDI • Mask TCDD • (Auxiliary collimators TCLIA and TCLIB) Nov 08, 2007

  3. What do we need to inject? (2) • BI in the LHC • BTVs – application: Fabio • For point 2: BTVSS.6L2.B1, BTVSI.C5L2.B1, BTVSI.A5L2.B1, BTVST.A4L2 • BLMs (relevant for injection tuning) – partly SPS timing, partly LHC timing • Injection acquisition for LHC BLMs: application? • 5 LHC BLMs on the MSI AND 5 SPS BLMs on the MSI (the last TI2 and TI8 ones) • 3 LHC BLMs on the TDI • no BLM on TCDD, but at entrance of D1 • (BLMs for TCLIA/TCLIB) • (no mention of LHC BPMs, nothing special for injection region) MKI Transfer line Q5 Q4 D2 TDI MSI TCLIA + TCLIB IP2 TCDD Nov 08, 2007

  4. Interfaces (1) • Interlocking • Supervision application for East and West Extraction in SPS will be updated to include injection BICs • MKI needs injection permit to pulse remotely • ALICE ZDC unmaskable • LHC beam permit unmaskable • Masking needs LHC Safe Beam Flag (SLP, timing) • Master BIC will be updated using the ‘real’ logic (next year) • SMP generator box for: • Beam presence • LHC SB • SPS probe flag • SPS SB Injection BIC still missing Nov 08, 2007

  5. Interfaces (2) • RF – pre-pulse • optical fiber link to point 4 • LBDS – abort gap watch dog • direct fiber link with point 6 • OASIS: • injection permit • BETS window • watch dog window (AGK) • PFN voltage • circulating intensity • like to have this as a fixed display • Timing • “Next Injection Ring” event • Injection warning (1000 ms before injection) • SLP energy for BETS SPS example, no AGK Nov 08, 2007

  6. Transfer lines • Power converters: • Power converters including MSI: SPS MUGEFs • hardware commissioned (heat run,…) • settings available – SPS timing – SPS cycle • interlocking via transfer line BICs (ROCS surveillance) • BI: • All applications ready • All equipment already defined for • logging (DB and SDDS) • fixed displays • dedicated applications (BTVs, BLMs, BTCs, YASP) • still missing: critical settings for BLMs • TCDIs: • Only three collimators in TI 2 hardware commissioned • Not connected to BICs yet • (Two partly beam commissioned • setting up methods still to be worked on) • Application available • critical settings do not exist yet Nov 08, 2007

  7. MKI • Interlock to ring BIC • Local/remote • SIS: temperatures • Interlock to injection BIC • State • Settings: LSA settings and critical settings • LhcMKIstate • standby, on, off • LhcMKIkick • delay, length, strength (57 kV), enable/disable • windows: critical settings • Application in progress (Georges-Henry) • BETS like MKE in SPS • uses SLP energy • Logging still needs to be discussed • Alarms still to be defined for OP Nov 08, 2007

  8. TDI/TCDD - collimators • Needs LSA settings and critical settings via collimator control • User permit to Injection BIC • TDI needs to be in “protect” during injection • User permit to Ring BIC, beam specific • TDI needs to be out after injection • TCDD in IR2 moveable (in/out) • User permit to Injection BIC → needs to be closed during injection • Alarms → needs to be open otherwise • Controls: collimator control • TCLIA/TCLIB → collimators, Stefano, interlocking like TDI TDIringBIC: TDIpos > TDIringBIC MKI standby: t0 TDIinjBIC: TDIpos < TDIinjBIC Nov 08, 2007

  9. Other stuff • Knobs for polarity changes of experimental magnets, separation on/off, crossing on/off: • experimental magnet, correctors, compensators, MKI • Orthogonal steering at MSI → YASP • Injection steering: • MKI part of it? • define LSA parameter angle for MKI → kV • Injection triggered acquisition!!!! Need to be able to correlate beam loss to injection event • Nothing foreseen for the BLMs • Only 1 Hz data publishing • → BLMs on TDI: LHC BLMs!!! • “Injection” logging? • to be defined • ‘SDA’ – XPOC like? • Fixed displays • to be defined • (Injection quality check → SIS) • not an issue for start-up Nov 08, 2007

  10. Testing…dry (1) • Full testing of injection equipment requires: • Timing • LHC cycling • SLP energy distributed and generated by the LBDS BETS • LHC beam permit – closed loop (LBDS armed → LHC closed!!), closing locally? • Alice ZDC giving green light (for point 2) • LHC Safe Beam Flag distributed • TDI, TCLIs, TCDIs masked • Functions defined for TDI (TCLIA/TCLIB as well) • TCDD controlled within collimator control system • Cooling (TDI, TCDD, …) • Logging defined • Sequencer: injection sequence, timing tables prepared • RF pre-pulse (simulation mode?) • LBDS synchronisation commissioned → abort gap watchdog • Full testing of injection interlocking requires: • Interlock functions defined for TDI (TCLIA/TCLIB) • Interlock functions defined for TCDIs • TL pulsing – MSI FMCM, MSI PC sum fault • Real Master BIC to verify injection permit result • LHC-SPS flag distribution Nov 08, 2007

  11. Testing…dry (2) • Scenario: interleaved injections: • Sequencer – injection sequencing • “Next Injection Ring” event used by MKIs to condition which one to pulse • ONE injection warning event: injection warning for charging PFNs • Pre-pulse for pulse • Scenario: injection – the whole chain: injector chain → first turns in the LHC: • Sequencer – injection sequencing • Mini-conditioning of MKIs?? • Uncoupled injection timing, simulated pre-pulse? • Timing table with all events • BI stuff as well: BLMs!!!??? • Injection logging Nov 08, 2007

  12. Testing…dry (3) • Scenario: inject & dump: • Sequencer… • Together with LBDS • Dump on first turn • Scenario: injection finished – prepare for ramp: • Downstream TEDs in • MKI disabled • MKI standby! (before moving TDI) • Move out TDI → state transition: injection permit, no state transition: beam permit • Move out TCLIA/TCLIB → like TDI • Move out TCDD in IR2 • … Nov 08, 2007

  13. Summary • Lots of stuff already there • Equipment partly already hardware commissioned • Applications • either just need to be configured for the LHC • or are under way • Logging and alarms still need some work • Triggered acquisition for BLMs during injection? • Testing needs to be worked out carefully • Parallelism • Lots of details to be defined Nov 08, 2007