GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 LAT meeting- V4 July 17, 03 Gunther Haller, JJ Russell haller@slac.stanford.edu (650) 926-4257. Key Milestones, new schedule (1). Key Milestones (2).

linus
Download Presentation

GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 LAT meeting- V4 July 17, 03 Gunther Haller, JJ Russell haller@slac.stanford.edu (650) 926-4257

  2. Key Milestones, new schedule (1)

  3. Key Milestones (2)

  4. Key Milestones (3)

  5. Main Interdependencies

  6. Flight Hardware Procurements • Req’s for Omnirels, MAXIM’s, EEPROM in purchasing • Writing req’s for Actels, MOSFET’s, memories, EMI filters, DC/DC hybrids

  7. Flight Hardware Manufacturing • First Board to be fabricated is TEM Qual • Need by Dec 1, 03 • Package for fab and assembly must be placed by Sept 1, 03 • All assembly drawings final by Aug 15, 03 • Tower Power Supply Module 2 weeks behind TEM • Others ~ Jan 04

  8. Engineering Model Testing • Continuous testing up to commitment for flight fab (of course continuous beyond that but changes have impact) • Must have full set of front-end electronics to verify DAQ hardware/software • Must have CAL/TKR Mini Twr with detectors to debug/test/verify DAQ system including trigger hardware & software

  9. Open Flight Design Issues • Detailed routing of wires in GASU (~3,000 wires in enclosure) • New Tower Power supply circuit needs to be tested

  10. Cost/Schedule Status • Pretty much on schedule (except TEM and TEM-PS, 4 weeks late, FSW is being assessed) • Cost: overrun will occur in • Front-end simulator • Had to be redone after move of project to SLAC • Storage interface board • Added in each crate to simplify software • FSW needs more man-power • Tower Power supply cost being assessed • EGSE test-stands

  11. Issues/Concerns • Concern of performance of Tower Power Supply • Need prototype to evaluate (Oct 1, 03) • Must connect to CAL and TKR tower and perform noise measurements • Needs to be done by Cal and TKR system • Concern that TKR and CAL will interfere with each other when integrated in TKR – CAL – TEM package (EMI/EMC) • Need detailed plan to test • Who is taking care of this? • Concern that DAQ HW and FSW may not have continuous access to TKR and CAL Mini TWR instrumented with detectors • Must plan for continuous access • Need more than 3-X and 3-Y layers • Concern that FSW is late • Need to add promised man-power