210 likes | 257 Views
LNG READY SOLUTION USING A MARK FIT LNG FUEL TANK OPERATING UP TO 2 BARG: THE CASE OF VLOC. Jacques Danton– GTT. Introduction. Emission control area coming into effect -> LNG fuel interesting alternative for marine propulsion GTT offering new solutions for the use of LNG as a fuel:
E N D
LNG READY SOLUTION USING A MARK FIT LNG FUEL TANK OPERATING UP TO 2 BARG: THE CASE OF VLOC Jacques Danton– GTT
Introduction • Emission control area coming into effect -> LNG fuel interesting alternative for marine propulsion • GTT offering new solutions for the use of LNG as a fuel: • New Mark FIT technology -> better use of space inside the ship • New approach regarding the installation of LNG tanks on ships • Raising of pressure inside the tank to 2 bar -> more flexibility • LNG fuel especially interesting for Australia due to local ressources
Mark FIT: volumetric efficiency • Mark FIT allows a wide range of possible angles • Mark FIT optimizes the space dedicated to LNG fuel thanks to unmatched volumetric efficiency
VLOC • LNG interesting for Very Large Ore Carrier • Several possibilities regarding the retrofit philosophy • Typical VLOC: LOA = 300m; up to 250000 dwt • Range: 12000 nm -> 5000m3 of LNG required • One specifity: 1 additional cargo for use for LNG containment
Newbuild • Identical approach as LNG Carriers • Membrane installed directly on the hull during construction • Maximization of the LNG volume • Cheapest solution for LNG use
Retrofit • Several option for retrofit operation: • Installation of membrane inside the hold n°8 • Jumboisation • Installation of an exoskeleton inside the hold n°8 • Installation of an exoskeleton on deck • Necessity to prepare LNG conversion at design stage to insure feasibility and avoid additional cost during retrofit operation • Retrofit of engines (if not dual fuel) must also be considered and anticipated
Retrofit by jumboisation • Section containing fully equipped LNG tank and fuel gas handling system is added to the ship • No loss of cargo space
Retrofit using an exoskeleton • A self standing tank equipped with membrane is installed on the ship • Work mostly done in the shipyard before ship immobilization -> reduced immobilization time • Possibility to include the fuel gas handling system in the structure
Exoskeleton on deck • First option: install the exoskeleton on deck • Easy and quick operation • Minimal welding work • No additional hold is needed by room on deck is required
Exoskeleton inside the hull • Other option is to install the tank inside a hold • More complex operation • No wasted space • Weight optimization by integrating the tank to the hull
Cost of using LNG • 20% more CAPEX for newbuilding LNG fuelled ship compared to conventional • 5% more compared to ships with scrubbers and EGR / SCR • LNG ready ship a little more expensive than conventional but most of the cost comes from the retrofit operation • Loss of cargo space depending on LNG tank location • Loss of vessel time due to retrofit operation to be taken into account
Why 2 barg? • Longer holding time, with or without spraying, during blackout periods or extended period at anchor -> more flexibility during ship operation • Boil-off gas generated during bunkering operations is kept inside the tank for future use -> more flexibility • Ability to bunker warmer LNG -> More flexibility toward LNG supply Holding time for a small tank; Larger tanks will result in longer holding time
IGF and 2 barg • Pressure inside LNG tanks historically limited to 0.7 barg in IGC Code • MARVS usually at 0.25 bar on LNGC -> decision not justified by the code but by other consideration (additional weight, operational needs…) • FEA now extremely common and reliable -> no problem in dimensioning a structure supporting 2 barg • No problem for membrane technology • 2 possibilities in the code to go to 2 barg • Alternative design • Limit state design
Impact of 2 barg on the ship • No impact on GTT membrane • No impact on the ship if exoskeleton is on deck but around 50% more steel in the exoskeleton • If tank integrated to the hull, impact on the ship is dependant of the scantling. In case of VLOC, scantling are important enough due to heavy cargo loads
Impact of 2 barg on cost • CAPEX: • Only related to additional steel weight • Not significant on VLOC (already very strong hull) • 15 additional tons for liquid and gas dome • OPEX: • No need to use Boil-off gas management solution thanks to longer holding time
Conclusion • Mark FIT is an interesting option to comply with new norms: • Based on reliable and sea-proven technical choices • Maximization of the volume of LNG stored • Retrofit options for all configurations • Abundance of LNG in Australia make supply easier and cheaper • Most significant problems regarding flexibility solved by raising pressure to 2 bar: • LNG supply • Ease of use by the crew