290 likes | 295 Views
Updates on the Lafayette New Terminal Program, including cooperative agreements, capital outlay applications, grant applications, airline negotiations, enabling demo progress, and construction timelines.
E N D
Lafayette New Terminal Program Update December 12, 2018
LA FP&C • Received Cooperative Agreement for FP&C contribution to QTA • Coordinating with FP&C to confirm bid process and eligible items for terminal contribution • 2019 Capital Outlay Application submitted • Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application • Revised EDA grant application submitted. Currently on the December Decision Committee Agenda TSA OTA Application • Submitted Grant Application, Waiting on Feedback Terminal Program Update
Airlines • Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return • Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates • Bids received – contractor recommendation on Agenda • Once approved will work with FP&C on approvals for NTP Concessions Terminal Program Update
Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete • Fill Material and Asphalt – Complete • Seeding/Sod Placed – Ongoing • Punch List Meeting – 12/7/18 Terminal Program Update
Enabling Demo – drone photo Terminal Program Update
Terminal Program Update Asphalt patching at gate Fill material placed at demolished vault area
Terminal Program Update Card Readers Installed Striping Complete
Terminal Program Update Fill placed at 310 Shepard Fill placed at John Glenn
QTA Timeline: • Oct. 2018: Commission Approved Updated CFC • Nov. 2018: Construction Bids Due • Dec. 2018: Award of Contract • Jan. 2019: Notice to Proceed • Oct. 2019: Construction Complete Terminal Program Update
GMP 1: • GMP 1 approved 9/25 • Notice to Proceed 11/12 • Schedule Starts: • Nov. 2018: RTR Relocation and Enabling Parking • Parking Impacts • Nov. 2018: RTR Facility Construction • Jan. 2019: Terminal Foundation Construction GMP 2: • Structural Steel Construction/Elevations and Escalators • Bids being received by Lemoine-Manhattan in December • January 2019 Approval - does not affect critical path GMP 3 • 100% Design is on Schedule in February • April 2019 Approval Terminal Program Update
Site prep- laydown area and access road GMP 1 – Project 2 RTR Facility Hydro excavating the ILS Cable Concrete encased ILS Cable
GMP 1 – Project 2 RTR Facility Stripping site Site stripping and grading
GMP 1 – Project 5 Enabling Parking Jersey Barriers placed in Economy Lot Tree Removed Pavement demolition of Economy Lot
GMP 1 – Project 5 Enabling Parking Storm drain across Terminal Drive Fillcrete poured over storm drain