Road Infrastructure in Bulgaria Munich, 30 September 2010
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation • Tendencies in the development of the world economy: • Process of stabilization of the world commerce, growth in the business activity, in the production as well as the services sectors. • Expectations for growth of the EU economy from 0.7% in 2010 to 2.4% in 2013. • Expectations for weak economic growth of 0.5% during 2010. • Tendencies in the development of the national economy: • GDP growth from 3.6% in 2011 to 4.9% in 2013 • Expectations for export growth from 5.9% in 2010 to 6.2% in 2011. • Maintenance of inflation at a relatively low level around 3% until 2013. • Recovery of the positive dynamics of the labor market. • Unemployment - 9.14 % toward August 2010
Foreign investments direct flows, mln. Euro,2004 – Ist half of 2010* *Forecast data of the Bulgarian National Bank
Production of building companies of some European countriesin June 2010 towards June 2009According data from Eurostat ФИНАСОВ РЕСУРС ПО СХЕМА BG161PO001/2.1-01/2007
Production of the construction companies,2004 – I half of 2010, mln. leva Comparative growth of the production in % *Forecast data of National Statistic Institution
Production of the construction and building enterprises Ist half of 2007 – Ist half of 2010* *Forecast data of the National Statistic Institution
Investments in national roads 2001-2013г. [mil.lv] mil.lv 800 751 750 694 687 700 650 586 600 538 550 500 473 450 421 398 400 341 350 316 300 234 250 186 211 189 200 171 129 146 166 143 135 133 132 150 120 102 110 110 110 96 92 92 95 102 78 86 79 100 64 59 62 55 50 0 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010* 2011** 2012** 2013** Rehabilitation New construction Current repair and maintenance
Planned investments for programmes with financing by EU for the period 2007-2013: • Operational Programme Transport(Indicative cost ): 990 mln. Euro • Operational Programme Regional development 255mln. Euro Other Road programmes – Budget Financing 2010-2013 • Programme for rehabilitation and reconstruction of bridges – 64 bridges, indicative cost 60 mln. Euro • Road safety programme – 100 dangerous road crossings. Indicative cost 30 mln. Euro • Road maintenance – new approach and contracts 60 to 100 mln. Euro per year • EIB Transit Roads V - 100 – 200 mln. Euro per year • World Bank – 80 mln. Euro until 2013
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation • Perspectives: • Operational Programme Transport Programme period 2014 – 2020 - • 4Billion Euro • Operational Programme Regional Development 2014 – 2020 - • 1 Billion Euro • Danube Strategy – “Connectivity” axis priority • Other programmes financed by the state budget 1 Billion Euro
OPT – 2007-2013 PROGRAMME PERIOD OPT – 2014-2020 PROGRAMME PERIOD
Projects in Operational Programme Transport2007 - 2013 1. Trakia MW (from Sofia to Burgas) 117 km Budget 350 Mln. Euro/Contracted 250 mln. Euro 2. Mariza MW (from BG to TR)67 km Budget 208 Mln. Euro 3. Struma MW (from BG to GR) 65 km Budget 250 Mln. Euro 4. Kardzhali – Podkova (from BG to GR)28 km Budget 32 Mln. Euro 5. Hemus MW(from Sofia to Varna) 8,5 km Budget 32 Mln. Euro 6. Е-79, Vratsa – Botevgrad (north of Sofia) 31 km Budget 85 Mln. Euro 7. Е-79, Vidin – Montana (from RO to BG)20 km Budget 32 Mln. Euro ∑ 990 Million Euro
b Reserve Projects /Operational Programme Transport 2007 - 2013/: - 207 - 2013 • “Sofia – Kalotina” Motorway, Lot 1,2,3 50 km 150 Million Euro • Montana By-pass I-1 (E-79) 12,5 km 25 Million Euro • Vratsa By- pass I- 1 (E-79) 6,8 km 13 Million Euro • Gabrovo By-pass I-5 (E-85) 31 km 42 Million Euro • Ten-T Rehabilitation 50 Million Euro ∑ 1,3 Billion Euro
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation “Trakia” Motorway, Lot 2 Stara Zagora–Nova Zagora km 210+100 - 241+900 Length – 31,800 km Costs : 70,5 Mio. Euro (2,2 Mio. Euro/km) Contractor : Magistrala Trace Joint Venture (BG) Start of construction: 09 June 2010 Construction time: 25 months End of construction: June 2012
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation “Trakia” Motorway, Lot 3 Nova Zagora – Yambol km 241+900 - 276+200 Length – 34,300 km Costs: 65 Mio. Euro (1,9 Mio. Euro/km) Contractor: Aktor (GR) Start of construction: 02 August 2010 Construction time: 25 months End of construction: August 2012
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation “Trakia” Motorway, Lot 4 Yambol - Karnobat km 276+200 - 325+280 Length – 49,080 km Costs: 107 Mio. Euro (2,1 Mio. Euro/km) Constructor: Trakia IV Joint Venture (BG) Start of construction: 03 September 2010 Construction time: 28 months End of construction: December 2012
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation “Maritza” Motorway (connection Trakia MW – Turkish border) km 5+000 - 71+011 Length – 66,011 km Division in 2 Lots • Lot 1 Orizovo – Dimitrovgrad (km 5+000 - 36+600) = 31,6 km • Lot 2 Dimitrovgrad – Harmanli (km 36+600 – 71+011) = 34,411 km • Tentative costs: 209 Mio. Euro (3,2 Mio. Euro/km); • Announcement (for two Lots): October 2010; • Start of construction: April/June 2011; • Construction time: 26/25 months; • End of construction: May/June 2013.
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Struma Motorway Corridor № IV, Sofia to Greek border Road programmes in preparation Lot 1 Dolna Dikania – Dupnitsa km 305+220 - 322+000 = 16,78 km Lot 2 Dupnitsa - Blagoevrad km 322+000 - 356+000 = 34 km Lot 4 Sandanski - Kulata km 423+500 - 438+500 = 15 km Total length of Lot 1, Lot 2 and Lot 4: 65.78 km. Tentative cost: 250 Mio.Euro Lot 3 (Blagoevgrad – Sandanski) will be constructed in the next programming period 2014-2020. Design Lot 3 in year 2011; Tender procedures for construction and supervision of Lot 1 and Lot 4. Announcement: Winter 2010/2011 Start of construction: Lot 1 - July 2011; Lot 4 – September 2011 Construction time: 23/22 months End of construction: May/June 2013
МИНИСТЕРСТВО НА РЕГИОНАЛНОТО РАЗВИТИЕИ БЛАГОУСТРОЙСТВОТО MINISTRY OFREGIONAL DEVELOPMENT AND PUBLIC WORKS Road programmes in preparation „Hemus” Motorway Section : „Sofia Ring Road – “Yana” road junction”km 0+000- 8+460 Tentative costs: 32 Mio. Euro Announcement: November 2010 Start of construction: May 2011 Construction time: 20 months End of construction: December 2012
1. “Struma” Motorway Lot 367.5 km 500 MillionEuro 2. “Hemus” Motorway 286 km 1.500 Million Euro 3. “Cherno more” Motorway 100 km 350 Million Euro 4. “Sofia – Kalotina” Motorway 72 km 200 Million Euro5. Express way “Sofia – Gyueshevo” 85 km 200 Million Euro 6. Express way “Ruse – Shumen” 112 km 150 MillionEuro7. Express way “Ruse – Veliko Tarnovo – Gabrovo”, 150 km350 Million Euro incl. “Shipka tunnel – Stara Zagora8. Express way “Rila” 80 km 200 Million Euro 9.Bridges on the Danube river – Silistra-Kalarash, Oryahovo-Beket 400 Million Euro10. Express way E-79 60 km 150 Million Euro∑ 4 Billion Euro Operational Programme Transport 2014 - 2020