YE + 4 SHIELDING WALL FOR CMS. SCOPE OF WORK. YE + 4 disks = 2 Nos. (12 Sectors each) Support Structures = 2Nos. AISI 1045 steel bar = 1 No. ( Dim. inspection 680 mm ( 0,-0.5) Fasteners = 1 set (Trial Assembly). YE + 4 SHIELDING WALL FOR CMS. MATERIAL PURCHASE.
E N D
YE+4 SHIELDING WALL FOR CMS SCOPE OF WORK • YE+4 disks = 2 Nos. (12 Sectors each) • Support Structures = 2Nos. • AISI 1045 steel bar = 1 No. ( Dim. inspection 680 mm (0,-0.5) • Fasteners = 1 set(Trial Assembly)
YE+4 SHIELDING WALL FOR CMS MATERIAL PURCHASE • Material ordered = 10th Dec., 2010 • Material shipped = 21st March, 2011 • Material received = 29th April, 2011 to 6th May, 2011 • Beam HEB-220 and Channel UPN-400 = (Procurement in progress) • 1 set of fasteners = -do-
YE+4 SHIELDING WALL FOR CMS MATERIAL LIST
YE+4 SHIELDING WALL FOR CMS MATERIAL LIST (Contd.)
YE+4 SHIELDING WALL FOR CMS MATERIAL TESTING AND ACCEPTANCE • Material testing = Completed • Certificates submitted to CERN = 25th May, 2011 • Mill Test Certificates and Cobalt Test reports • Material acceptance from CERN = 1st June, 2011
YE+4 SHIELDING WALL FOR CMS ENGINEERING REPORT • Documents submitted to CERN = 12th April, 2011 • Final cutting plan • Final weld Identification/ details • Quality Plan • Production Technology • Q -PLAN approved by CMS=1stJune, 2011
YE+4 SHIELDING WALL FOR CMS PRESENT STATUS • Marking and cutting of plates just started • Likely to be ready for pre assembly by Oct., 2011
YE+4 SHIELDING WALL FOR CMS Q/A AND INSPECTION • Inspection points not selected by CMS • Authorized inspector by CMS yet to be nominated